Part 11 Flashcards

1
Q

A project team is currently three weeks behind in a project with six more weeks to go. Although the project manager believes the project can be fast tracked to save a week, this is not the case.

Which of the following represents the slack along the critical path?
A
0 weeks

B
3 weeks

C
-3 weeks

D
-2 weeks

E
2 weeks

A

B

3 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.

Which of the following should the project manager do NEXT?
A
Ask the resource to improve performance to target with commitment date.
B
Ask the functional manager to provide a resource with the same level of allocation.
C
Remove 20 of allocation of the resource from the secondary project.
D
Ask the PMO to mitigate the risk related to insufficient resources.

A

C

Remove 20 of allocation of the resource from the secondary project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A project sponsor decides to cut the project budget and reduce the scope. As a mitigation plan, the team decides to promote the project internally to gain support from other areas.

Which of the following describes the BEST combination of communication methods that can be used to attract more people?
A
Gate reviews, face-to-face meetings, and kickoff meeting
B
Social media, email, and printed media
C
Instant messaging, kickoff meeting, and town hall meetings
D
Text messaging, instant messaging, and meetings

A

A

Gate reviews, face-to-face meetings, and kickoff meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A key stakeholder has asked project team members to work overtime on special projects. This is undermining the success of a time-sensitive project because the project team is too tired to complete the deliverables.

Which of the following steps should the project manager take to BEST resolve the issue?
A
Ask the project sponsor for dedicated resources for the time-sensitive project.
B
Ask the project sponsor for shared resources for the key stakeholder’s project.
C
Ask the key stakeholder for low-quality resources for the time-sensitive project.
D
Ask the project sponsor for benched resources for the time-sensitive project.

A

A

Ask the project sponsor for dedicated resources for the time-sensitive project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

During a project status meeting, the project manager states the project is running ahead of schedule. However, the executive committee, which is unfamiliar with the project manager’s work, does not think it will finish on time.

Which of the following is the MOST likely cause?
 A
Relationship building
 B
Interorganizational differences
 C
Specific communication
 D
personal preferences
A

C

Specific communication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A mandatory evacuation has been ordered due to a natural disaster.

Which of the following should be applied?
 A
Incident response plan
 B
Emergency plan
 C
Business risk plan
 D
Business continuity plan
A

D

Business continuity plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A project to implement Voice over Internet Protocol for a contact center has been expanded to include the entire organization.

Which of the following BEST describes the constraints involved?
 A
Schedule, quality, and deliverables
 B
Resources, requirements, and scope
 C
Deliverables, schedule, and resources
 D
Stakeholders, scope, and schedule
A

D

Stakeholders, scope, and schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A project manager is planning a wedding that will take place during the rainy season. The possibility of rain is very high, so the project manager proposes alternatives to having an outdoor wedding.

This is an example of:
 A
mitigation.
 B
transference.
 C
exploitation.
 D
acceptance.
A

A

mitigation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
Which of the following roles would be tasked with project steering?
 A
Key project stakeholders
 B
Project management office
 C
Project manager
 D
Project coordinators
A

A

Key project stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project manager wants to determine the percentage of a project’s budgeted costs versus expenditures.

Which of the following calculations should the project manager perform?
 A
Burn rate
 B
Critical path analysis
 C
EV
 D
EAC
A

A

Burn rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A project manager failed to include quality testing in a software development project plan and must now add it while the project is underway.

Which of the following BEST describes the relationship that quality will have on the triple constraint?
A
Time and scope will remain static, and costs will increase.
B
Time, cost, and scope will decrease.
C
Time will remain static, and scope and costs will increase.
D
Time and cost will increase, and scope will remain constant.

A

D

Time and cost will increase, and scope will remain constant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Management announces the PMO will assume all research and development efforts.

Which of the following BEST describes this scenario?
 A
Outsourcing
 B
Relocation
 C
Process change
 D
Business merger
A

C

Process change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A critical change has been implemented, which the project manager needs to communicate to the project team.

Which of the following would be the BEST method for communicating the change?
 A
Printed mailing
 B
Fax
 C
Social media
 D
Email
 E
Text message
A

D

Email

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A functional manager pulled a resource from a current project to work on a higher-priority project but did not offer a backfill resource.

Which of the following should the project manager do FIRST?
A
Report the project as at risk and share the issue with the project team.
B
Delay the task in the schedule and inform the sponsor.
C
Meet with the functional manager to discuss the issue.
D
Open a change request to reduce the project scope.

A

C

Meet with the functional manager to discuss the issue.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A sensitive project requires activities to occur with very specific, to-the-minute timing. Which of the following would BEST ensure on-time delivery?
 A
Text messaging
 B
Video conferencing
 C
Face-to-face activity monitoring
 D
Voice conferencing
A

B

Video conferencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
Which of the following is MOST commonly associated with the WBS and used to develop a project timeline?
 A
Process diagram
 B
Gantt chart
 C
Network diagram
 D
RACI matrix
A

B

Gantt chart

17
Q
Which of the following project team members would MOST likely be tasked with maintaining project documents?
 A
Project sponsor
 B
Project champion
 C
Project scheduler
 D
Project manager
 E
Project coordinator
A

D

Project manager

18
Q

A project is out of control because project team members are completing tasks based on preference and suggestions from project stakeholders, instead of following the project schedule.

Which of the following is an indication that this project is out of control?
A
Stakeholders are not properly engaged.
B
Work is being accomplished faster than planned.
C
Performance relative to the plan is unknown.
D
There is no project manager named.

A

C

Performance relative to the plan is unknown.

19
Q
According to best practices, the average duration of a Scrum sprint should be:
 A
two to four months.
 B
one to five months.
 C
one to five weeks.
 D
two to four weeks.
A

D

two to four weeks.

20
Q
After accepting and assigning a positive risk, risk owners have a responsibility to:
 A
determine a mitigation strategy.
 B
update the risk register.
 C
maximize the probability.
 D
minimize the impact.
A

B

update the risk register.

21
Q

In a highway construction project, the project team has identified the need to utilize additional land for staging equipment.

After documenting the change request, which of the following should be accomplished NEXT?
 A
Audit the documentation
 B
Communicate with the stakeholders
 C
Identify the approval authority
 D
Obtain approval
A

C

Identify the approval authority

22
Q
A project portfolio will MOST likely align to:
 A
consumer demand.
 B
lessons learned.
 C
PMO guidelines.
 D
corporate strategy.
A

D

corporate strategy.

23
Q
Which of the following is responsible for key decisions within a project?
 A
Project management office
 B
Project manager
 C
Project champion
 D
Project team
A

B

Project manager

24
Q

During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training.

Which of the following communication methods should be used?
 A
Project status report
 B
Project schedule
 C
Project communications plan
 D
Project dashboard
A

A

Project status report

25
Q
While working with a project team to create the project schedule, which of the following must occur for performance measurement?
 A
Identify resource costs
 B
Create status reports
 C
Set the baseline
 D
Manage issues
A

C

Set the baseline

26
Q

During a meeting, a new member of the PMO says, “If this project fails, then the portfolio fails, and the program as a whole ultimately fails.”

Which of the following errors is the new PMO member making?
A
The new PMO member has not had an opportunity to review the company’s project list.
B
The new PMO member has not review the intra organizational strategy.
C
The new PMO member does not realize that although a project can fail, a program cannot, as it contains all projects in a company.
D
The new PMO member has confused the relationship between portfolio and program.

A

D

The new PMO member has confused the relationship between portfolio and program.

27
Q

Top-level managers are considering joining certain projects, programs, and operations to be managed as a group.

Which of the following is being considered?
 A
Program development
 B
Project interdependencies
 C
Organizational changes
 D
PMO establishments
A

B

Project interdependencies

28
Q

A project sponsor would like the status of a key deliverable at the first project milestone.

Which of the following is a characteristic of a milestone?
 A
Resource assigned
 B
High cost
 C
Zero duration
 D
Ongoing
A

C

Zero duration