Part 6 Flashcards

1
Q

A project team has determined it will need to source data from a system that was not part of the project scope.

The role of the project manager is to analyze which of the following impacts?
 A
Schedule, budget, and quality
 B
Business process impacts and resourcing
 C
Technical design, schedule, and budget
 D
New software and hardware requirements
A

D

New software and hardware requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
An industry leader may be joining the project team and can potentially provide additional expertise. Which of the following strategies should the project manager employ?
 A
Transfer
 B
Acceptance
 C
Validation
 D
Exploitation
A

C

Validation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The design activity of a project has the following cost attributes:

PV = 100,000
EV = 20,000
AC = 90,000
Based on this scenario, calculate the schedule variance.
 A
120,000
 B
10,000
 C
-80,000
 D
-70,000
A

C

-80,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
 A
affected team members.
 B
full project team.
 C
internal project team.
 D
key stakeholders.
A

D

key stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
Which of the following risk strategies is represented by the purchase of insurance?
 A
Accept
 B
Avoid
 C
Mitigate
 D
Transfer
A

D

Transfer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account.

Which of the following should the project manager do to ensure stakeholder expectations are met?
A
Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.
B
Organize a requirements workshop to capture any gaps.
C
Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps.
D
Escalate the issue to the project steering committee that Ann is criticizing the project quality.

A

A

Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?
 A
Critical Path Method
 B
Precedence Diagramming Method
 C
Critical Chain Method
 D
Arrow Diagramming Method
A

B

Precedence Diagramming Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is the MOST likely reason for the failed inspection?
A
The CCB was not contacted.
B
The prior document version was not reviewed.
C
Version control processes were not applied.
D
There were insufficient resources assigned to the task.

A

C

Version control processes were not applied.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A post implementation review is being performed as a part of project closure. Which of the following are applicable areas that the review should cover? (Choose two.)
A
Provide a recap of the overall solution.
B
Gathering and centralizing project documentation.
C
Produce operational support documentation.
D
Identify the key project achievements.
E
Organizing the communication of project closure.
F
Lessons learned during the project.

A

D
Identify the key project achievements.
F
Lessons learned during the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST explanation?
A
In the beginning, projects start with detailed inputs that need to be explained.
B
In the beginning, projects have start and finish dates that require elaboration.
C
In the beginning, projects entail a degree of uncertainty that needs to be specified.
D
In the beginning, projects are part of a program that requires coordination.

A

C

In the beginning, projects entail a degree of uncertainty that needs to be specified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
The project team is not comfortable moving an expensive material.
A third party is hired to move the material. This is an example of risk:
 A
Acceptance
 B
Sharing
 C
Avoidance
 D
Transference
A

D

Transference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

Project completion | total hours | amount cost

6 months | 420 | $25200
4 Months | 620 | $37200

Which of the following represents the cost variance for both project completions?
 A
$4.8K and -$7K
 B
-$4.8K and -$7K
 C
$4.8K and $7K
 D
-$4.9K and $7K
A

A

$4.8K and -$7K

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
 A
Functional
 B
Projectized
 C
Balanced matrix
 D
Strong matrix
A

D

Strong matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project. Which of the following MOST likely occurred?
 A
The company received a C&D.
 B
A higher-priority project needed the expertise.
 C
An SLA prevented new team members.
 D
The new member did not sign an NDA.
A

A

The company received a C&D.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
Team members have reported poor sound quality during critical, time-sensitive conference calls. Which of the following may be a more effective means of communication?
 A
One-on-one meetings
 B
Social media
 C
Text messages
 D
Project wiki
A

A

One-on-one meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future event on an entity outside the organization?
 A
Risk avoidance:e
 B
Risk transfer
 C
Risk mitigation
 D
Risk exploitation
A

B

Risk transfer

17
Q
The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?
 A
Ahead of schedule and over budget
 B
Behind schedule and under budget
 C
Ahead of schedule and under budget
 D
Behind schedule and over budget
A

C

Ahead of schedule and under budget

18
Q

A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution.

Which of the following is the BEST risk mitigation strategy that the project manager should use?
A
Raise a risk in the risk register, identify the likelihood and the consequence of the risk occurring.
B
Escalate this as an issue to the project control board and ensure that there is adequate discussion.
C
Have the project adequately document the solution and ensure a transition is in place.
D
Organize adequate training and have one of the operational staff as part of the project team.

A

D

Organize adequate training and have one of the operational staff as part of the project team.

19
Q
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
 A
Schedule
 B
Time
 C
Scope
 D
Cost
A

D

Cost

20
Q

A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users.

In which of the following components of the project plan should this be documented?
 A
Scope statement
 B
WBS
 C
Change form
 D
Issues log
A

D

Issues log

21
Q
A project team is spread between two countries on different continents. Which of the following factors are MOST likely to influence communication methods selected for the communication plan? (Choose two.)
 A
Language barriers
 B
Interorganizational constraints
 C
Personal preferences
 D
Cultural differences
 E
Confidentiality constraints
A

A
Language barriers

D
Cultural differences

22
Q
A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?
 A
Allocating resources
 B
Resource loading
 C
Prioritizing tasks
 D
Resource leveling
A

A

Allocating resources

23
Q
Which of the following tools would a project manager use to determine the root cause of an issue?
 A
Histogram
 B
Ishikawa Diagram
 C
Monte Carlo Analysis
 D
Pareto Chart
A

B

Ishikawa Diagram

24
Q
A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?
 A
Pareto chart
 B
Run chart
 C
Process diagram
 D
Fishbone diagram
A

D

Fishbone diagram

25
Q

The project’s network map has a loop with multiple project outcomes.

This is the result of which of the following scheduling tools?
 A
Establishing project schedule baselines
 B
Critical Chain Method
 C
Critical Path Analysis
 D
Graphical evaluation and review technique
A

D

Graphical evaluation and review technique