Part 7 Flashcards

1
Q

A project team on a four-year project has a shortage of workspace within an office. Which of the following is the MOST viable solution for the project team while ensuring work hours are not wasted?
A
Secure a new facility, permit remote work, and reduce staff.
B
Reduce staff, implement BYOD, and permit remote work.
C
Permit remote work, utilize shared workspaces, and implement BYOD.
D
Implement BYOD, secure a new facility, and utilize shared workspaces.

A

C

Permit remote work, utilize shared workspaces, and implement BYOD.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?
 A
Business analysts
 B
Key stakeholders
 C
Resources
 D
Vendors
 E
Project team
A

E

Project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?
A
Dashboard information, action items, project schedule, and status report
B
Project charter, organization chart, scope statement, and issue log
C
Project management plan, scope statement, communication plan, and meeting agendas
D
Project schedule, project management plan, communication plan, and issue log

A

B

Project charter, organization chart, scope statement, and issue log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
A
Speak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
B
Schedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.
C
Wait until the change requests are approved by the CCB.
D
Approve the changes because the additional functionality is required to complete the process.

A

C

Wait until the change requests are approved by the CCB.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?
 A
Utilize positive float.
 B
Crash the schedule.
 C
Remove the critical path
 D
Fast-track the tasks.
A

D

Fast-track the tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?
 A
Intra-organizational differences
 B
Time zone
 C
Culture
 D
Personal preference
A

B

Time zone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?
 A
RF1
 B
Request for bid
 C
RFP
 D
Change request
 E
RFQ
A

B

Request for bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following is an example of a project?
A
Implementing a health awareness program at an organization
B
Conducting semi-annual blood drives at an organization
C
Presenting a scripted workshop at an organization’s three locations
D
Purchasing pedometers from local retail stores for employees

A

Implementing a health awareness program at an organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.

Which of the following best describes what the PM should work on FIRST?
 A
Responsibility assignment matrix
 B
Meeting agenda
 C
Risk register
 D
Project charter
 E
Project schedule
A

E

Project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?
 A
Kickoff
 B
Update
 C
Scheduling
 D
Review
A

C

Scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
 A
SCRUM retrospective meeting
 B
Review meeting
 C
Daily standup meeting
 D
Sprint planning meeting
A

D

Sprint planning meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?
 A
Add tasks.
 B
Add the start and finish dates
 C
Add durations.
 D
Add resources.
A

A

Add tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?
 A
Dashboard information
 B
Issue log
 C
Communication plan
 D
Action items
A

B

Issue log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?
 A
RFP
 B
SLA
 C
Change request
 D
SOW
A

D

SOW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A project manager has been assigned a complex project and does not know all the activities required to complete it.

Which of the following if the BEST approach to determine the work packages for the WBS?
 A
Forward pass
 B
Analogous
 C
Bottom-up
 D
Brainstorming
A

C

Bottom-up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.

insert image 1

Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).
 A
Lag
 B
Float
 C
Cost
 D
Subtasks
 E
Predecessors
 F
Resource loading
 G
Durations
A

C
Cost

F
Resource loading

17
Q
A project’s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
 A
Corrective action plan
 B
Project schedule
 C
KPI
 D
WBS
 E
Cost performance parameter
A

B
Project schedule

D
WBS

18
Q
Which of the following roles has approval authority for project funding?
 A
Champion
 B
Chief Financial Officer (CFO)
 C
Project Management Office (PMO)
 D
Sponsor
A

D

Sponsor

19
Q

A project has activities on the critical path that must be completed before other activities can start.

Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.

Which of the following is the appropriate ordering of the critical path?
 A
B, C, A, D
 B
D, A, C
 C
B, A, D
 D
C, B, D, A
A

A

B, C, A, D

20
Q
A new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
 A
Implement the change.
 B
Identify and document the risk.
 C
Evaluate the impact and justification.
 D
Update the documents and plans.
A

D

Update the documents and plans.

21
Q
A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?
 A
Get approval from the CCB.
 B
Communicate the change to stakeholders.
 C
Submit a change request.
 D
Evaluate the impact of the change.
A

D

Evaluate the impact of the change.

22
Q

The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?
A
Arrange an impromptu team meeting with the chairperson.
B
Schedule a conference call for the team meeting and invite the chairperson.
C
Invite the chairperson to the next project team meeting
D
Email the chairperson the meeting minutes from the scheduled meeting

A

A

Arrange an impromptu team meeting with the chairperson.

23
Q
The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?
 A
Collaboration website
 B
Phone call
 C
Video conference
 D
Instant messaging
A

C

Video conference

24
Q

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

magine 2

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
 A
16 days
 B
12 days
 C
17 days
 D
22 days
A

D

22 days

25
Q
Which of the following inherently affects quality standards?
 A
MOU
 B
MOA
 C
SLA
 D
WBS
A

D

WBS