Which of the following roles is MOST involved in checking the quality of the deliverables and supporting the project manager during the project? A Sponsor B Team leader C Tester D Project coordinator
C
Tester
A project sponsor informs the project manager that the project completion date must be moved one month earlier. Which of the following should the project manager do NEXT?
A
Recalculate the schedule and cost variance, and report the changes to the project stakeholders and sponsor.
B
Calculate the cost of crashing the schedule, and obtain the stakeholders’ approval for the new project WBS and timeline.
C
Calculate the additional resource requirements that are necessary to meet the new project deadline, and work with human resources to hire additional staff.
D
Recalculate the critical path, determine the new cost, schedule baselines, and initiate the change request process.
A
Recalculate the schedule and cost variance, and report the changes to the project stakeholders and sponsor.
An approved change was implemented. Which of the following should be accomplished NEXT? A Update the documentation. B Validate the impact. C Update the project sponsor. D Validate the change.
A
Update the documentation.
A company just announced all third-party vendors must provide ten cybersecurity resources within six weeks. Which of the following documents should the project manager create LAST? A RFI B MOU C RFQ D NDA
B
MOU
A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager do NEXT?
A
Change the resource to 60% of allocation and review the mitigation plan.
B
Ask the resource manager to deallocate the resource from the second project.
C
Ask the resource manager to assign a new resource with 40% of allocation.
D
Keep the resource 100% allocated in the project, as per the initial plan.
A
Change the resource to 60% of allocation and review the mitigation plan.
A project sponsor is reviewing the project dashboard and does not understand what a CPI of 0.87 and an SPI of 1.02 indicate. Which of the following describes the project status?
A
The project is over budget and ahead of schedule.
B
The project is under budget and behind schedule.
C
The project is under budget and ahead of schedule.
D
The project is over budget and behind schedule.
A
The project is over budget and ahead of schedule.
Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)
A
Qualitative assessments are more difficult.
B
Qualitative assessments better identify opportunities.
C
Qualitative assessments provide more accurate results.
D
Qualitative assessments require fewer resources.
E
Qualitative assessments are faster.
D
Qualitative assessments require fewer resources.
E
Qualitative assessments are faster.
The project manager is running a project in an organization with a strong PMO and a mature control process. Due to vendor delays, the project is scheduled to exceed the authorized timeline. The project manager has discovered that fast-tracking two tasks will mitigate the issue. Which of the following should the project manager do NEXT? A Initiate a change request. B Modify the schedule C Announce the fast track to the project team. D Obtain approval.
D
Obtain approval.
A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial.
This would MOST likely impact the project’s: (Choose two.) A effectiveness B requirements C scheduling D budget E scope F environment
A
effectiveness
C
scheduling
During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed. Which of the following does the project sponsor desire? A Schedule management plan B Status report C Project schedule D Task durations
B
Status report
A project manager wishes to track a project’s performance against the original approved schedule. Which of the following steps is necessary to capture the needed information? A Determine the critical path. B Determine the milestones. C Set a baseline. D Set phase gates
C
Set a baseline.
An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation? A Language barrier B Personal preference C Cultural difference D Technological factor
C
Cultural difference
A company recently discovered that it could save money by moving its call center to another country. The company entered into an agreement for call center services. Which of the following types of organizational change is this? A Relocation B Business process change C Business demerger/split D Outsourcing
A
Relocation
The quarterly financial statement has been released, and portfolios are losing funding for projects. Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.) A Ask for operational team support. B Request more time with a smaller project team. C Reduce the features being released. D Reduce quality control. E Shorten the project duration.
C
Reduce the features being released.
D
Reduce quality control.
A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
A
Provide the next task to the newly freed resource.
B
Communicate the success to the team.
C
Update the schedule and add lag to the next task.
D
Notify the project sponsor of the new completion date.
B
Communicate the success to the team.