Part 21 Flashcards

1
Q

Ann, a project manager, is working for a new company. On her first project, the assigned project resources do not follow her direction. She is not allowed to authorize contractors because they say she does not have the authority. Which of the following is the MOST likely explanation for what is happening?
A
Ann is new to the organization so no one trusts her
B
The project team is functional
C
Ann has not developed a communications plan
D
The project has not started

A

B

The project team is functional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
A project manager is scheduling activities and determines one activity cannot be completed until another activity is completed. Which of the following dependency relationships is represented?
 A
FS
 B
FF
 C
SF
 D
SS
A

B

FF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:
 A
risk management response
 B
change management response
 C
business change response
 D
business continuity response
A

A

risk management response

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
Which of the following should be included in an effective SOW?
 A
Corrective action plan
 B
Lessons learned
 C
Procurement process
 D
Project objectives
A

A

Corrective action plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
A project manager is assigned a project that is part of the company’s strategic objectives. Of which of the following is the project a part?
 A
Project management office
 B
Program
 C
Portfolio
 D
Mission statement
A

C

Portfolio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?
 A
Project team
 B
Stakeholders
 C
Project sponsor
 D
Scrum master
A

A

Project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the following project changes is the project manager most likely to consider FIRST?
 A
Requirements change
 B
Risk event
 C
Funding change
 D
Timeline change
A

D

Timeline change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
The managing director of a law firm has asked the project manager to create a scope statement for a new contract. Which of the following should be included in the scope statement? (Choose two.)
 A
Project schedule
 B
Deliverables
 C
Key performance indicators
 D
Scope creep
 E
Gate review
 F
Business requirements
A

B
Deliverables
F
Business requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
The project team is moving from high-level risks to detailed risks. Which of the following project phases is the project team moving between?
 A
Initiation to planning
 B
Execution to monitor and control
 C
Initiation to monitor and control
 D
Planning to execution
A

D

Planning to execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
Which of the following is the MOST important component against which the project manager can analyze project performance?
 A
KPIs
 B
Budget
 C
Project baselines
 D
Burn rate
A

A

KPIs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
 A
Environment
 B
Budget
 C
Requirements
 D
Lessons learned
A

B

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
 A
a dedicated resource pool
 B
a shared resource pool
 C
an allocated resource pool
 D
a benched resource pool
A

C

an allocated resource pool

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

An employee is assigned to a project and is developing a project charter. Which of the following are some of the constraints the employee would typically face at this stage of the project?
A
Budget, scope, quality, and schedule
B
Deliverables, scope, and budget environment
C
Environment, resources, requirements, and quality
D
Budget, quality, resources, and schedule

A

A

Budget, scope, quality, and schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of the following project management tools would help?
 A
Issue log
 B
Dashboard
 C
Project charter
 D
Meeting minutes
A

D

Meeting minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following are the roles involved in a Scrum project?
A
Scrum master, product owner, development team
B
Scrum master, business analyst, product owner
C
Scrum master, development team, quality coach
D
Scrum master, project sponsor, business analyst

A

A

Scrum master, product owner, development team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
Which of the following represents the order of the team development stages?
 A
Forming, performing, storming, norming
 B
Forming, norming, storming, performing
 C
Forming, norming, performing, storming
 D
Forming, storming, norming, performing
A

D

Forming, storming, norming, performing

17
Q

The following tasks are required to complete an IT project that is behind schedule:

pic 15

Which of the following is the critical path?
 A
3, 2, 4
 B
4, 1, 2, 3
 C
4, 2, 3
 D
3, 2, 1, 4
A

D

3, 2, 1, 4

18
Q
Which of the following are MOST likely the responsibilities of the PMO? (Choose two.)
 A
Act as an approval authority
 B
Provide governance
 C
Justify the business case
 D
Procure hardware
 E
Identify key performance indicators
 F
Steer the project
A

B
Provide governance

F
Steer the project

19
Q

A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm. The PMO declines to assign a project manager and refers to another department within the company. Which of the following is MOST likely the reason for this?
A
This is ongoing work the vendor has been hired to perform
B
The work does not align with the strategic objectives of the organization
C
There are not enough project managers available for additional work
D
The third party has a reputation for expertise in this area

A

D

The third party has a reputation for expertise in this area

20
Q
A project manager is reviewing project performance. Which of the following would be the BEST indicator of the total project cost?
 A
EAC
 B
ETC
 C
CPI
 D
AC
A

A

EAC

21
Q
Which of the following provides tools and standard documentation for the project team?
 A
Project steering committee
 B
Project manager
 C
Project management office
 D
Project coordinator
A

C

Project management office

22
Q

A team member has reported Task 3 will be completed ahead of schedule.

pic 16

Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
 A
10 days
 B
11 days
 C
8 days
 D
12 days
A

D

12 days

23
Q
A project needs two more months of work to be completed, but the deadline is in 35 days. The project manager heard the company recently hired an experienced person. The project manager scheduled a meeting with the functional manager to negotiate bringing the experienced person to the team. Which of the following strategies is the project manager trying to apply?
 A
Mitigate
 B
Accept
 C
Exploit
 D
Transfer
A

C

Exploit

24
Q
A project sponsor approaches the project manager with a change request. During the conversation, the project sponsor claims to understand the impact of the change to the project length and has the budget to handle the cost. The sponsor also tells the project manager to send whatever needs a signature. The project manager’s NEXT step should be to:
 A
document the change
 B
prioritize the change
 C
implement the change
 D
communicate the change
A

A

document the change

25
Q
A company was originally organized using a functional structure; however, the company has decided to go forward with a matrix structure to get the most utilization of resources. This is an example of:
 A
personal preference
 B
intraorganizational differences
 C
internal reorganization
 D
a business process change
A

C

internal reorganization