A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST? A RFO B RFQ C RFI D RFP
C
RFI
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time? A Crashing B Resource leveling C Resource smoothing D Throttling
A
Crashing
Several team members report that meeting objectives are not being met.
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)
A
Create a corrective action plan prior to each meeting and adhere to it.
B
Create a lessons learned list prior to each meeting and adhere to it.
C
Create a project charter prior to each meeting and adhere to it.
D
Create an action item list during the meeting and adhere to it.
E
Create a WBS prior to each meeting and adhere to it.
F
Create a meeting agenda prior to each meeting and adhere to it.
G
Create an SOW prior to each meeting and adhere to it.
D
Create an action item list during the meeting and adhere to it.
F
Create a meeting agenda prior to each meeting and adhere to it.
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information? A A list of decomposed activities B A sequenced list of project tasks C A document describing agreed-upon communication methods D A list of realized risks
D
A list of realized risks
A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT? A Evaluate the impact to the baseline. B Issue a change request. C Update the project management plan. D Revise the project charter.
A
Evaluate the impact to the baseline.
A project manager is creating the WBS.
In which of the following phases is the project? A Initiation B Execution C Closing D Planning
D
Planning
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending? A EAC B BAC C CPI D ETC
C
CPI
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items? A Requirements document B Business case C Task plan D Project timeline
A
Requirements document
A stakeholder is unaware of a project’s status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.) A Communication plan B Status report C RACI matrix D Organizational chart E Meeting minutes
B
Status report
E
Meeting minutes
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?
A
Announce the project will end early due to lack of funds.
B
Alert the project sponsor of the situation.
C
Contact the customer and request more funding.
D
Attempt to save money in downstream activities.
B
Alert the project sponsor of the situation.
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized? A Avoiding B Forcing C Smoothing D Compromising
B
Forcing
An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects? A Project coordinator B HR C Project sponsor D PMO
C
Project sponsor
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take? A Review the task start and finish dates. B Assess the risk register’s new items. C Analyze the assigned hours. D Obtain additional resources.
B
Assess the risk register’s new items.
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?
A
Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
B
Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
C
Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
D
Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
B
Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step? A Auditing B Validation C Implementation D Approval
D
Approval