Which of the following defines a group of projects that work together to achieve a common goal? A Program B Product C Project plan D Portfolio
A
Program
Which of the following is the primary purpose of an MOA or an MOU?
A
Provide transparency to competitors regarding all signatory parties.
B
Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
C
Enumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
D
State expectations of all signatory parties to reduce potential misunderstandings.
D
State expectations of all signatory parties to reduce potential misunderstandings.
A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?
A
Send an email outlining the concerns to the team member.
B
Send a project team meeting to obtain feedback from everyone.
C
Post the issue on the wiki page for input from stakeholders.
D
Conduct a face-to-face or telephone meeting with the team member.
D
Conduct a face-to-face or telephone meeting with the team member.
When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk? A Status report B Issue log C Risk register D Risk management plan E Communications plan
C
Risk register
After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
A
Hold a full team workshop to review the complete WBS.
B
Use milestones identified in the project charter.
C
Use data based on past knowledge.
D
Collaborate with other project managers.
B
Use milestones identified in the project charter.
Which of the following documents should be used to provide high-level reporting to key stakeholders? A Dashboard B Project charter C Statement of work D Communication plan
A
Dashboard
A milestone task on the critical path has been completed.
Which of the following should the project manager notify? A Owner of predecessor task B Project team C Project steering committee D Project sponsor
D
Project sponsor
Assuming an iterative approach, which of the following will be conducted at the end of each iteration? A Budget baseline B Kickoff meeting C SCRUM retrospective D Risk review
C
SCRUM retrospective
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as: A compromising. B smoothing. C forcing. D avoiding.
C
forcing.
A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements.
Which of the following actions would be BEST for the project manager to take?
A
Ask the client to provide requirements in the native language of the team.
B
Purchase a language translation program.
C
Hire a translator to help the key team member
D
Ask the client to provide additional language resources to the team.
A
Ask the client to provide requirements in the native language of the team.
A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements? A Project management office B Sponsor C Project manager D Project team
B
Sponsor
The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor’s areas of poor performance? A WBS B Post-project evaluation C PERT D Balanced score card
D
Balanced score card
The executive sponsor asks a project manager to summarize the following for a project:
- Final capital expenditures.
- Anticipated cost of new employee resources to support the solution.
- Maintenance estimates.
Which of the following information should the project manager provide? A Burn rate B Cost variance report C Total project cost D Cost baseline
D
Cost baseline
A company hires an outside vendor to provide 24/7 support.
Which of the following documents would determine the contractual obligations? A MOU B PO C LOI D SLA
D
SLA
Which of the following are characteristics of a project? (Choose two.) A Temporary B Consisting of milestones C Restricting the budget D Achieving a goal E Start and finish F Ongoing
A
Temporary
E
Start and finish