Part 20 Flashcards
A project manager is assigned to a project with an unfamiliar domain area. The project manager is compiling a list of stakeholders and their roles in a chart. The project manager lists SMEs in the project domain to be: A instructed B delegated C employed D consulted
D
consulted
A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager work? A Projectized B Strong matrix C Flat D Functional
D
Functional
While planning a project, the project team estimates known expenses but also applies a margin of error for unknown expenses. Which of the following is the project team trying to determine? A Total project cost B Expenditures C Cost of quality D Burn rate
A
Total project cost
A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk? A Quality plan B Regression plan C Change validation D Application version control
C
Change validation
A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question? A Project schedule B Project charter C Project management plan D Staffing matrix
C
Project management plan
Which of the following are the components of a RACI matrix?
A
Responsibility, authority, support, inform
B
Responsible, accountable, consulted, informed
C
Reliability, accountability, support, inform
D
Responsibility, acquired, consulted, informed
B
Responsible, accountable, consulted, informed
Rather than sending emails to communicate all project information, the project manager:
Makes telephone calls to key stakeholders for urgent information
Sends emails for routine information
Posts on the project intranet site for required but minimally used information
Which of the following BEST represents what the project manager is doing?
A
Tailoring the method based on message content
B
Adjusting the method based on confidentiality constraints
C
Prioritizing based on personal preferences
D
Demonstrating concern for technological factors
A
Tailoring the method based on message content
A construction company is building a plant in a territory that is prone to earthquakes. To address the risk and consequences of potential earthquakes during and after plant construction, the company purchases additional insurance. Which of the following risk responses has occurred? A Mitigating B Avoiding C Accepting D Transferring
D
Transferring
Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used? A Ishikawa, quality control B Scatter, determining resources C Histogram, forecasting D Gantt, leveraging resources
A
Ishikawa, quality control
After SOW and contract approvals, the project manager plans to schedule a meeting with the business analyst and several end users. The project manager’s main objective in this meeting is to: A create deliverables B define requirements C identify resources D baseline the schedule
B
define requirements
The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report? A Process diagram B Scatter chart C Run chart D Gantt chart
D
Gantt chart
A project sponsor wants to know which tasks are next in the project but is unable to find this information. Which of the following may need to be adjusted? A Status report B Risk log C Scope document D Issue log
A
Status report
Which of the following organization types requires the project manager to report performance issues to another department? A Functional B Projectized C Strong matrix D Weak matrix
D
Weak matrix
A project team has just finished one phase of product development and is gathering requirements for the next phase. Which of the following methodologies is being applied? A Agile B Waterfall C Top-down D PRINCE2
B
Waterfall
The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project.
pic 14
Which of the following changes would BEST satisfy the project sponsor?
A
Add a new line to the communications plan to provide a weekly status report with a dashboard
B
Include the project sponsor in the daily stand-up with the entire project team
C
Add the project sponsor to all project email correspondence moving forward
D
Include the project sponsor in all project meetings moving forward
C
Add the project sponsor to all project email correspondence moving forward