A project team is working on a project with high public visibility and excitement. The project sponsor is concerned the public may lose interest due to the long delivery timeline. Which of the following is the BEST way to keep the external stakeholders informed and engaged throughout the project? A Email B Social media C Instant messaging D Video conferencing
B
Social media
The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy. Based on the following entry:
pic 17
Which of the following should be modified to BEST eliminate confusion?
A
Change the status to issue and include it in the issue log
B
Change the strategy to mitigate
C
Change the owner to sponsor
D
Change the name to identify the problem clearly
B
Change the strategy to mitigate
A project scheduler has calculated the project’s critical path. Which of the following activities would most likely occur NEXT? A Dependency determination B Additional task decomposition C Resource allocation D Task duration identification
C
Resource allocation
A PM has a complex project that requires coordination among numerous stakeholders. Which of the following is the MOST appropriate type of meeting for the stakeholders to hold? A Virtual B Impromptu C In-person D One-on-one
A
Virtual
During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated? A Business continuity plan B Project plan C Incident response D Risk register
C
Incident response
According to the communication management plan, the project scheduler is required to post weekly status reports on the project’s intranet site. From the stakeholders’ point of view, accessing the weekly report is an example of: A the interactive method B personal preferences C the pull method D interorganizational preferences
C
the pull method
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
A
Review the communications plan to ensure proper involvement
B
Publish the project schedule to the functional manager
C
Add the incident to the issue log and seek resolution
D
Ensure the functional manager is on the status report distribution list
E
Update the project charter to include the functional manager as a key stakeholder
A
Review the communications plan to ensure proper involvement
E
Update the project charter to include the functional manager as a key stakeholder
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path? A Six days B Seven days C Eight days D Five days
A
Six days
Which of the following will identify the MOST potential project risks? A Benchmarking B Project budget C Cost-benefit analysis D Past project documentation
D
Past project documentation
Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
A
Create the risk register
B
Determine procurement needs to meet the project demands
C
Determine the flexibility between the project constraints
D
Hold a kick-off meeting with the project team
B
Determine procurement needs to meet the project demands
A company purchased a parachute supplier and is now sending parachutes to the research and development department. Which of the following has occurred? A Outsourcing B Risk avoidance C Business acquisition D Business demerger
C
Business acquisition
Which of the following should a project manager consider as part of a make or buy analysis? A Organization type B KPIs C Project charter D Trade secrets
B
KPIs
A PM is asked to keep the Chief Information Officer (CIO) informed of a project’s health at a high level on a daily basis. Which of the following is the BEST way for the PM to provide this information? A Email B Status report C Dashboard D Meeting minutes
A
In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders? A The project has float available B The project needs a gate review C The project is behind schedule D The project is over budget
C
The project is behind schedule
Which of the following documents are considered mutually binding? (Choose two.) A PO B RFP C NDA D WBS E KPI
B
RFP
C
NDA