F3 - LT#3 - Planning excavations and shoring Flashcards

1
Q

What factors affect the depth of excavations for a building?

A

1) Building design/loading
2) Soil type and bearing strength
3) Climate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

For big projects, what type of equipment is used to move large amounts of materials?

A

Caterpillar tractors, scrapers & large hoes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why should water not be allowed to stand where foundations are to be placed?

A

It destabilizes and weakens the bearing capacity of soil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If gravity drainage is not possible, how should rain and groundwater be controlled?

A

Using sump or wells

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What should be located before you dig?

A

Underground utilities such as gas, electricity and sewer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

List 5 safety precautions to be used while working around excavation equipment.

A

1) Stay out of the circle
2) Stay well back from the rear
3) Don’t walk under boom

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why are signs posted near a blast site?

A

So people are aware of the signals and warning procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do 12 short whistle signals indicate?

A

Warning preceding a blast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How long must a blaster wait before initiating the blast after the signal that warns of an impending blast?

A

Two minutes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is an “All clear” sound signal used during blasting?

A

5 second whistle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is used to prevent the public from falling in an open excavation?

A

Barricades and hoarding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How deep can excavations be before a ladder is required?

A

4 feet. (1.2 meters)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the minimum width of walkways at excavations?

A

20 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is the width of a strip footing determined?

A

By the type of soil that supports the footing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When possible, should you save topsoil?

A

Can be re-used during landscaping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What should be done before the excavation process?

A

Locate all services that are in the area of the excavation. Shut off, or isolate hazardous services

17
Q

Where do water services start from?

A

Enter below footings, below frost line, come up through basement floor close to a wall. Equipped with water meter.

18
Q

What pipes are connected to the storm sewer?

A

Perimeter drainage tile and drainage from under the building foundation are connected to the storm sewer. Runoff from the roof is directed to the storm sewer through rainwater leaders.

19
Q

Can you put a gas line under the driveway?

A

Usually, yes you can but it is expensive to rip them up if a leak were to occur.

19
Q

Gas lines must be located, staked, installed and removed by:

A

Certified Gas Fitter

19
Q

How do you avoid gas leaks in a house?

A

The gas line must be outside of the building and topped by a meter.

20
Q

The electrical conduit must be about how far above the roof.

A

1220 MM so that no conductor is closer than 915 mm

21
Q

Electrical conductors must be no closer than:

A

4575 from the ground above vehicle areas and 3660 MM from the ground otherwise

22
Q

Service conductors are usually raised about:

A

5490 MM when accompanied by the telephone lines to avoid contact between them.

23
Service conductors must be raised to:
5490 MM when accompanied by a telephone line.
24
Underground electric services will be buried at
at least 610 mm deep, and 915 mm deep where it passes under an on-grade slab or driveway
25
The Electrical meter must be installed how?
1525 to 1830 mm above finished grade, it is turned to face the exterior of the building
26
How are telephone lines attached to the house?
Must be anchored to a mast on the fascia.
27
How deep must the trench be for the telephone line?
460 MM deep
28
What is one strategy to deal with water tables building up where foundations will bear?
Wells will be drilled and water will be pumped to maintain a low water table.
29
How far must building excavations pile from edge? (NOT TRENCH)
4 feet minimum
30
How far must excavation pile from edge of TRENCH?
2 feet minimum
31
Who regulates the locations of service conduits?
BC Electrical Inspector
32
Who is allowed to conduct blasting on job sites?
Only registered blasting contractors.
33