Q

What system components does SATS provide diagnostics for?

A

PPS Comparators
Contact-to-Logic level Converter Modules
2/3 Logic Modules
Div Logic Modules
Reactor Mode Selector Switch
Rod Clutch Coil Controller (RCCC) Logic Circuits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Is SATS safety-related?

A

No. SATs auto function can instead be done manually if malfunctioning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where is SATS powered from?

A

Commercial Power E390. (1st basement)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Draw the SATS interface.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the impact of SATS testing on PPS?

A

SATS testing does not inhibit PPS to respond to an event, nor does it contribute to reactor shutdown.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where are the SATS interface units located?

A

The 4 SATS interface units are located in each PPS room.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What types of signal comm paths are used by SATS?

A

Type A - apply and remove PPS test voltages
Type B - data transfer path from PPS to SATS
Type C - request a computer interrupt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What components separate SATS inputs/outputs from PPS?

A

Buffer Amplifiers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How often must functional channel testing be performed on PPS?

A

Every 48 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does EFIS vessel level inoperability impact SATS?

A

Tripping vessel level system (EFIS/PPS vessel level) render SATS unable to meet TSR requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why is isolation required from PPS during SATS computer system startup?

A

Spurious signals generated during computer power-up can cause an inadvertent reactor scram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the SATS room temperature limit?

A

85F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What date sensitivity impacts SATS?

A

Y2K sensitive (unsure if this is still the case after upgrade)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the PPS signal latch response time?

A

27 msec (SATS is faster than this, which is why it does not cause a trip)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the two modes of SATS TESTA program?

A

AUTO - automatically tests PPS system by executing the complete SATS test series.
SINGLE - executes a specified test number.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of SATS Initial Status Tests?

A

Determines which mode the reactor is operating in.

17
Q

What is he purpose of SATS Instrument Subsystem Tests?

A

Checks analog comparator will trip at setpoint and operability of analog and contact to logic level converter.
Ensures that channel trip will be seen by all 2/3 logic modules.
Also verifies that no PPS module failure is causing a false request for a trip

18
Q

What is the SATS Logic Test?

A

checks all combination of trip/resets to 2/3 logic module, div logic modules, and RCCC to ensure operation is correct

19
Q

What are SATS Final Status Tests?

A

similar to initial status tests. Also perform initial and final data comparisons to ensure everything remains within tolerance.

20
Q

What is the SATS Flow Coast Down Test (FLOW)?

A

Run while shutting down last primary pump.
Collects AC/DC ECP flows. 700 samples taken one second apart.

21
Q

What is the SATS Temperature Coast Down Test (TEMPS)?

A

Run at scram time to monitor temp decay curves of Rx.
4 Quad DTs
Reactor inlet and outlet temps
700 samples taken one second apart.

22
Q

What three SATS setpoint plateaus are there?

A

Two-pump
Three-pump
Depressurized

23
Q

What exception exists for EFIS vessel instruments concerning SATS?

A

EFIS Vessel Pressure instruments are not required in depressurized shutdown or operation and may be bypassed when irradiated fuel is removed from the vessel.

24
Q

What is the definition of Irradiated Fuel?

A

Fuel element after operation in the core with Rx power >20 kW unless the FE has been shown to have decay heat generation <30W.

25
Q

When does Shutdown PPS Checkout DOP not apply?

A

DOP 2.7.26 does not apply when <2 PCPs are operating.

26
Q

When must EFIS vessel level alarms or PPS vessel alarms be operable?

A

EFIS/PPS Vessel alarms must be operable with EFIS in manual and irradiated fuel elements in the vessel.