Experiment Insertion/Removal Flashcards

TRA00052

1
Q

What is the purpose of the High Point Vents for experiments?

A

Prevent IPT from lowering to the point of uncovering the test.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where are the high point vents located?

A

Actuated using reach rods from the reactor top area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe the covering for high point vents.

A

Have a plug cover that is considered part of confinement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the power supply for the 40/10 ton crane for experiment handling?

A

Commercial Power 670-E-10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the power supply for the 2-ton crane for experiment handling?

A

Diesel power 670-E-11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where is the disconnect for the 2-ton crane?

A

Northeast corner of the reactor main floor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the power supply for the Cask Console?

A

Diesel Commercial 670-E-67

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the prerequisites for experiment removal?

A

Reactor shutdown
Loop cooled and depressurized
Loop pressure sources isolated by LOTO
Posting on loop primary and secondary cubicles
Posting on subpile room
Preop check of crane and rigging DOP-2.1.17
Radiation monitor setpoints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the specific experiment removal loop preparations for 2E or MUCH (1C/D)?

A

Remove TSP from shield cylinder
Disconnect impulse lines
Remove Missile suppression plug

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the specific experiment removal loop preparations for PALM?

A

Remove PALM hydrotest closure plug
Install PALM lifting adapter
Disconnect TCs (alarm in LOCS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the weight of the TSP?

A

10,400 lb

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of the shield cylinder (donut)?

A

Restricts transient dose when transferring test.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why do we open crane disconnect prior to raising the experiment on the bayonet?

A

Prevents radiation exposure due to runaway crane (use chain hoist instead)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the purpose of the Removal Sleeve?

A

Provide a waterfilled connection between the cask and the top head closure plate for removal of the test.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the purpose of the top head rotoflex pump?

A

Removes excess water from the refueling ports and donut area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe ATR-1 Cask.

A

Sized for all tests - used for transfers within ATR (can’t leave the building)
Uses cable winch system with load tensioner.

17
Q

Describe TRC-1 and 2 Casks.

A

All stainless steel shielding (no lead)
More complex and time-consuming
Uses chain hoist with remote camera.

18
Q

Describe flushing of casks.

A

Cask is typically flushed if cask previously handled a fueled test and will be handling a non-fueled test
Always flush after use on 2A-C
Cask is set on catcher can for flushing.

19
Q

Describe shipping of TRC cask?

A

Move cask to storage stand.
Bolt on bottom shielding and plug assembly
Load onto transport for shipment to NRF

20
Q

Describe use of ATR-1 after loaded.

A

Move cask to CTS over empty storage can
Clear nozzle trench of personnel
Lower test into can (seated by activation of LOW LOAD alarm at 32 feet)D

21
Q

Describe lessons learned from ATR-1.

A

TRC spacer under storage can when using ATR-1 cask caused crushed can.

22
Q

What is the purpose of the hydrotest closure plug?

A

Allows loop to be pressurized without a test installed.

23
Q

What is the purpose of the configuration gauge check?

A

Verifies that closure sleeve locking ring has not backed out.
Verifies that closure plug locking ring is tightened.

24
Q

What action is required on a water on reactor top alarm from removal sleeve not sealing to IPT?

A

Start Reactor Top Pump

25
Q

What to do when IPT level Lo is received?

A

Fill cask with LDW (either hose or regular).

26
Q
A