[HR] Radwaste HVAC Flashcards
[HR]
Functions? (3)
-maintain ventilation in process equipment areas
-personnel safety in access areas
-restrict spreading of airborne radioactivity
[HR]
Which location features recirculation of air?
How is fresh air and pressurization introduced to recirc location?
-RW Control Room
-Recirc Air mixes w/ RW AHU Supply Air
[HR]
What temp is RW CR maintained?
70 – 80F
[HR]
Why does the system maintain RW Bldg at a negative pressure?
Minimizes amount of uncontrolled/unmonitored release of potentially radioactivity air from RW to O/S atmosphere
[HR]
What 6 systems vent to [HR]?
[GR] Gaseous Radwaste (GR)
[LR] Liquid Radwaste (LR)
[SR] Solid Radwaste (SR)
[CH] Chemical and Volume Control (CH)
- VCT
[SS] Nuclear Sampling (SS)
[RD] Radioactive Waste (RD)
[HR] and [DS]?
[DS] Provides water to air washers (RW A/C)
[HR]
What provides cooling water to the RW CR ACU?
[WC] Normal Chilled Water System
[HR]
What [GR] components vent to the [HR]? (2)
[GR] Waste Gas Surge Tank relief
[GR] Compressor pre-filter, suction filter and package
System release path discharges upstream of the AFUs
[HR]
What components of the [LR] Liquid Radwaste system vent to the [HR] system? (5)
Evaporator,
surface condenser
and heater
Concentrate Monitor tanks
LR system Holdup Tanks
[HR]
What [CH] components vent to [HR]? (2)
- BAC condensate & ion exchanger
[HR] What component of [SS] Nuclear Sampling System vents to [HR]?
O2 Analyzer Exhaust
[HR]
What part of [RD] Radioactive Waste Drain System vents to HR system?
[RD] RW sump
[HR]
What system provides air to the HR air dampers?
What happens if air is lost?
[IA] Instrument air
If [IA] is lost, the dampers fail closed causing the AHUs / AFUs to trip on overload
[HR]
Which radiation monitor tracks the GR system release flowpath?
RU-12
Which radiation monitors keeps track of the plant vent?
RU-143 and 144
The discharge of the Radwaste Building HVAC system is monitored by what component? Where is thi component located?
RU-14, upstream of the AFUs
RW building roof
What HR exhaust does RU-15 monitor? Where is this monitor located?
Combined exhaust from the Waste Gas System area
140’
Where do the Radwaste Building HVAC normal AHUs drain/overflow to?
OW, Control Building West sump
Concerning the Radwaste Control Room Normal AHU, when would the Duct Heater energize?
Supply air temperature is low (<50F), if the heater airflow is not low and if the heater supply breaker is closed
Where are the Normal supply AHUs located?
Radwaste Building roof
[HR] Normal Supply AHUs
-how are fans and dampers interlocked?
Each damper interlocked w/ fan
(fan is running the damper is open)
(fan is stopped the damper is closed)
[HR]
Normal Supply AHU Duct heater energizes when?
RW exhaust air temperature <75F
and if the associated AHU fan is running
Where are the controls for the HR system located at?
Radwaste Control Panel in the Radwaste Control room on the 120’ level of the Radwaste Building
How many signals are required to start the air washer pumps and where do those signals come from?
Two signals
A permissive signal from the associated running AHU fan and a signal from the intake air temperature controller when the outside air is 80F or above