HJ-Control building HVAC Flashcards

1
Q

[HJ]

[HJ] purpose?

A

Provides the required environment for personnel occupancy and equipment operation in the Control Building, including the Control and Computer Rooms during normal and emergency plant operation

Also responsible for isolating the Control Room against intrusion of poisonous gases, smoke or airborne radioactivity from the outside

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

[HJ]

To what level of radiation exposure does the HJ system limit personnel to during an event?

A

5 Rem

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How does HJ supports operations during a Station Blackout?

A

Provides environment to support equipment operation during the 16 hour coping period following a Station Blackout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What rooms does the HJ AHU supply on the 74’ level?

A

Air Handling Equipment Rooms A and B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What rooms does the HJ AHU supply on the 100’ level?

A

Train A and B Switchgear Rooms
Class A, B, C, D battery rooms
Remote Shutdown Rooms
DC Equipment Rooms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What rooms does the HJ AHU supply on the 120’ level?

A

Lower Cable Spreading Room
Inverter Room and Communication Equipment room
Corridor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What rooms does the HJ AHU supply on the 160’ level?

A

Upper Cable Spreading Room
Microwave Room
Lobby

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What system provides the makeup water for HJ Normal OSA AHU air washer? What provides the spray motive force?

A

Domestic Water

air washer pump

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Where are the HJ Outside Air Normal AHU and Air washer pump located?

A

74’ level Control Building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Where does the Control Room Normal AHU take suction from and where does it discharge to?

A

From an intake plenum being fed from:

120’ Communications Room and Inverter Room
140’ level
Control building OSA Normal AHU

Discharges back to the Control Room Complex, Comms Room, and Inverter Room

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Where does the Control Building AHU take suction from? Where is it located?

A

The Control Building normal return duct and the outlet of the Control Building OSA Normal AHU

74’ control building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of the ESF Switchgear Room Normal AHU?

A

Assists the Control Building Normal AHU in cooling the DC equipment and ESF Switchgear rooms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When would the Control Room Essential AHU be used? Where is it located?

A

Starts on a SIAS, CSAS, CRVIAS, CREFAS or LOP

74’ control building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When would the ESF Switchgear Room Essential AHUs be used and where do they send air to?

A

SIAS or LOP, will send conditioned air to the ESF switchgear rooms, battery rooms, and remote shutdown rooms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When would the ESF Equipment Room Essential AHU be used and where does it send air to?

A

SIAS or LOP, will send conditioned air to the DC equipment, ESF switchgear rooms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When would the Battery Ventilation Essential Exhaust Fans be used? What trips them?

A

SIAS or LOP

high D/P

17
Q

When would the discharge dampers of the Control Room Toilet and Control Room Kitchen Exhaust get isolated? Where are the hand switches controlled from?

A

Upon a LOP, SIAS, CREFAS, or CRVIAS
Fan will stay running

locally

18
Q

What does WC do for HJ?

A

Provides chilled water for control room normal, control building normal and ESF switch gear room normal (both trains) cooling coils

19
Q

What is the interlock associated with starting the Control Room Normal AHU?

A

Will not start unless both discharge dampers are open. A closure of either damper will trip the AHU

20
Q

What would cause the Control Room Normal AHU isolation dampers to close?

A

SIAS, LOP, CREFAS or CRVIAS

21
Q

What two elevations does the Control Room Normal AHU supply to?

A

120’, 140’

22
Q

When would the Battery Room Normal Exhaust fans auto stop?

A

When its respective room CO2 flood system actuates or the associated Essential Exhaust fan starts (Sensed by a high D/P across the Essential Fan)

23
Q

What must be done prior to start the Smoke Removal fan?

A

Align a suction path

24
Q

How many levels can I align the Smoke Removal to?

A

One at a time

25
Q

A LOP, SIAS, CRVIAS or CREFAS signal will prevent smoke removal of what level?

A

140’

26
Q

A LOP or SIAS signal will prevent smoke removal from what level?

A

100’

27
Q

What does EC do for the HJ system?

A

chilled water for switch gear and equipment room essential train A and B AHU cooling coils

28
Q

Why are there isolation dampers installed in the control building normal ventilation system?

A

it shares the ductwork with the control building essential units so the dampers isolate the normal and essential units from each other

29
Q

During smoke removal in the control building, where is fresh air drawn in form?

A

outside air intake plenum

30
Q

Why are the fire dampers in the class switchgear and battery rooms interlocked with the fire protection system?

A

if a CO2 discharge takes place, fire dampers are prevented from closing for 3.5 minutes to avoid over pressurization