Chapter 8 - Permitting and Contracting Flashcards

1
Q

permitting & contracting process is where the designers ________________ are submitted to the ______________. It is reviewed and a ______ is issued and _______ are performed during the construction of the project.

A

plans and specifications
local building department
permit
inspections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Before the permitting process begins, the designer may…

A

work formally or informally with the local building department during design of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When does the formal permitting process begin?

A

after the interior designer has completed the drawings and specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who are the drawings and specifications given to first?

A

contractor - who has been selected through a bidding process or negotiation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The ________ is responsible for ____________ to the local building department.

A

contractor, submitting the documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In some instances, the _______ or ________________ may submit a permit application.

A

building owner, registered design professional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does the contractor submit to the AHJ?

A

A specific number of copies of the construction documents, a permit application, and a permit fee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When the AHJ receives the documents from the contractor, who are they reviewed by?

A

One or more plan examiners

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

For small projects, ___________ may review the documents.

A

only one person

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

For larger projects, who reviews the documents?

A

building plan examiner, electrical, mechanical, and structural plan examiners

a local fire marshal may also review the plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If the documents are found _________, they are ______ by the AHJ.

A

acceptable, stamped

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

________ is issued back to the contractor, who must ________ at the building site.

A

One set, keep a copy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens if the documents are not found acceptable by the AHJ?

A

the necessary changes must be made and resubmitted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Whose responsibility is it to make changes to the documents (if they are not found acceptable by the AHJ)?

A

Interior Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Although the contractor typically submits the construction documents, the interior designer is responsible for making sure _______________________.

A

the project design complies with all applicable building codes and regulations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Compliance with all building codes and regulations must be __________.

A

reflected in the documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Do building codes require that certain information appear on the set of construction documents submitted for plan review?

A

Yes, list will vary with jurisdiction, but IBC has a typical list to use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Construction documents must be of sufficient clarity to indicate the ________, ___________, and ________ of the proposed work and how it will ____________.

A

location, nature, and extent
conform to code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What do the construction documents required by the building departments (AHJ) normally include?

A

Floor plans, elevations, sections, details (for architectural, structural, mechanical, electrical and specialty construction), schedules, and written specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Are location plans required by the building departments (AHJ) in the construction documents?

A

Yes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What does a location plan show?

A

Shows the position of the interior space being designed in relation to the entire floor or building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Should the drawings show all portions of the means of egress?

A

Yes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

To show the means of egress on the drawings, the number of __________ to be accommodated on every _______, and in all ______, and _______ must be indicated.

A

occupants, floor, rooms, spaces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Along with construction details, ____________, ________, and other ________ must be shown.

A

Fire-rated partitions, doors, openings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The _________ of _________ and fire extinguishers must be shown.

A

locations, exit signs

26
Q

Fire protection ____________ may have to be submitted to show conformance with the code.

A

shop drawings

27
Q

Structural __________ may have to be submitted.

A

calculations

28
Q

Mechanical and Electrical drawings prepared by the consultant must also be submitted, _______________________________.

A

showing conformance to the mechanical and electrical portions of the code.

29
Q

The construction specifications must include the necessary details of _________, materials, __________, and the _________ standards used.

A

products, finishes, test

30
Q

What information would the local AHJ may want to see listed on the first sheet of the drawings?

A
  1. names and addresses of all design professionals responsible for the work
  2. street address or legal description of the property
  3. codes being used
  4. area of the space designed
  5. construction type and occupancy group or groups
  6. occupant load calculations
  7. indication of whether the space is sprinklered or not.
  8. the valuation of new construction represented by the plans and specifications.
31
Q

When can construction begin?

A

Only after all the requirements are met and the building permit is displayed at the job site.

32
Q

As construction proceeds the AHJ makes ____________ to ensure that the project is built according to the code requirements of the ________________ and complies with the applicable _______________.

A

onsite inspections, construction documents, building code

33
Q

Are the building inspector and plan examiner the same person?

A

Typically, no

34
Q

What type of inspections are there for interior design projects?

A

Framing, Gypsum wallboard, Plumbing, Mechanical, Electrical, Final inspection

35
Q

Who calls for the inspections at the appropriate time?

A

The contractor

36
Q

What is a TCO? and what’s another name for it?

A

Temporary Certificate of Occupancy, Partial Certificate of Occupancy

37
Q

What does a TCO do?

A

Allows the client to occupy a portion of the space while the remainder is completed.

38
Q

The building official will only issue a TCO if there is no danger with __________________.

A

Partial occupancy

38
Q

If an agreement cannot be reached with the local official (AHJ) an appeal can be made to the _________________.

A

Board of Appeals

39
Q

The appeals process is a formal process by which a request is ____________________________ why the designer feels the proposed design meets the ______________.

A

made in writing stating the reasons, intent of the code.

40
Q

The Board of Appeals may consult with other professionals and issue a __________, either ________ the application or __________ __ __________.

A

ruling, denying, issuing a variance

41
Q

An enclosed exit access component that defines and provides a path of egress travel to an exit. A __________ may or may not be protected depending on the particular requirements of the code.

A

Corridor

42
Q

A door or access point along the path of egress travel from an occupied room, area, or space where the path of egress enters an intervening room, corridor, unenclosed exit access stair, or unenclosed exit access ramp.

A

Exit Access Doorway

43
Q

A court or yard (considered part of an exit discharge) that provides access to a public way for one or more required exits. This was formerly called an exit court.

A

Egress court

44
Q

A fully enclosed portion of an exit that is only used as a means of egress and provides for a protected path of egress either in a vertical or horizontal direction. In most instances, however, _____ __________ mean protected stairways. Depending on construction and building type, an exit enclosure must have either a 1-hour or 2-hour rating, and all openings must be protected. An exit enclosure must lead to an exit discharge or public way.

A

Exit Enclosure

exit enclosures

45
Q

A horizontal fully enclosed portion of an exit that is only used as a means of egress. An _____ _________ leads from an exit doorway to an exit discharge or public way. A common example is an exit from the door at the ground level of an interior stairway that leads through the building to an outside door.

A

Exit passageway
exit passageway

46
Q

An exit through a minimum 2-hour rated wall that divides a building into two or more separate exit access areas to afford safety from fire and smoke.

A

Horizontal Exit

47
Q

A change in elevation, consisting of one or more risers.

A

Stair

48
Q

One or more flights of stairs with the necessary landings and platforms connecting them, to form a continuous and uninterrupted passage from one level to another.

A

Stairway

49
Q

The measurement of the distance between the most remote occupiable point of an area or room to the entrance of the nearest exit that serves it. It is part of the exit access and is measured in a straight line along the path of exit travel.

A

Travel Distance

50
Q

An interior designer will prepare a ________ _________ to authorize changes in contract time and or contract cost after the execution of the ________.

A

change order, contract

51
Q

A change order must be signed by the ____________, ___________, and ___________.

A

contractor, designer, owner

52
Q

Contract time is the interval from the _________ date established in the contract to the date of _______________ ______________.

A

starting, substantial completion

53
Q

Contract time may be extended with a change order if _______ beyond the contractor’s control make it ____________ ___ _______ by the original duration.

A

delays, impossible to abide

54
Q

An Addendum is a written or graphic document issued by the ______________________________ the execution of the contract that modifies or interprets the bidding documents by additions, ____________, ______________, or corrections.

A

the interior designer BEFORE, deletions, clarifications

55
Q

Addenda are issued ___________ the bidding process _________ bids are submitted.

A

during, before

56
Q

When an addendum is issued it is sent to ____ bidders no later than __________ before _________ of bids, to give all the bidders ample opportunity to study the document and _________ their proposals accordingly.

A

all, 4 days, receipt, modify

57
Q

On some projects, it is advantageous to hold a ________ _______________.

A

prebid conference

58
Q

A prebid conference is a meeting with who?

A

Interior designer, owner, architect, engineering consultants, and bidders

59
Q

During the prebid conference, bidders can __________________ and the _________ ____________ and _____________ can emphasize particularly important conditions of the project.

A

ask questions, interior designer, owner

60
Q

During conferences (for very large projects), the interior designer should ________________________________, then have ________________ sent to all _________ (whether or not they were in attendance).

A

have someone take complete notes, a copy of the notes, bidders