Chapter 12 - Structural Systems Flashcards
Most newer construction are of _______ construction
post and beam
What can post and beam structures be made of?
Steel, concrete, or timber columns (posts) supporting a grid of beams on which the flooring is applied
4 types of structural systems:
- Steel
- Concrete
- Masonry
- Load bearing walls
Two most common steel structural systems
- beam-and-girder
- open-web joist
In the beam-and-girder system, large members, called _______, span between columns and smaller _____ are framed into them. The ______ span shorter distances because they carry the weight of the _____.
girders beams
girders beams
Typical spans for beam and girder system
25 to 40 feet
What happens on top of the beam and girder steel framing?
covered with steel decking, which spans between the beams. concrete topping is poured over the decking
Where is beam-and-girder most commonly used?
mid to high-rise office buildings
What is a downfall of beam and girder system?
limited space between the bottom of the girder and the suspended ceiling. adding ductwork or recessed light fixtures should be reviewed
In a ________ system, joists span between beams or bearing walls
open-web steel joist
Open-web steel joist system can span
20 to 144’
what goes on top of a the beam-and-girder system?
steel decking spans between joists and a concrete slab is poured on top of the decking
Where do you see open-web steel joists?
one-story or low-rise buildings with wide column spacing
what’s an upside of open-web steel joists?
mechanical and electrical service ducts, pipes, and conduit can easily be run between the web members. suspended ceilings and other lightweight interior elements can also easily b hung from the bottom of the joists
Two main types of concrete structural systems
Cast-in-place and precast
What is cast-in-place concrete?
concrete is poured into forms where it hardens before the forms are made
What is precast concrete?
components are usually formed in a plant and shipped to the job site, where they are set in place and rigidly connected to form the structure
Most cast-in-place concrete systems utilize only mild steel reinforcing set in the formwork before the concrete is placed. However, sometimes concrete is ________
post-tensioned
What is post-tensioned?
steel cables within the concrete are tightened after the concrete sets, creating extra compression forces in the beam or slab
If a slab is post-tensioned, what can you not do?
penetrate the slab for pipes or conduit
Five basic types of cast-in-place concrete systems
- beam-and-girder
- concrete joist
- flat plate
- flat slab
- waffle slab
Beam-and-girder
similar to the steel system. slab is poured with the beams
Concrete joist system
concrete members spaced 24 or 36 inches apart. because the joists are close together, it is more difficult to drill holes for small pipes and conduit
flat plate construction
floor slab is designed and reinforced to transfer loads directly to the columns which generally do not exceed 25’ spacing used when floor to floor height must be kept to a minimum difficult to drill these types of floors because of closely spaced reinforcing
Flat slab construction
similar to flat plate except drop panels (increased slab thickness around columns) are used to increase strength
waffle slab system
(two-way joist system) can provide support for heavier loads at slightly longer spans. often left exposed and lighting is integrated into the coffers.
Three types of pre-cast concrete floors
- single tee
- double tee
- hollow-core slab
advantage of single and double tee?
easy and fast to erect single and double team members simultaneously serve as beam AND floor decking
____ is generally limited to load bearing walls
masonry
Because masonry is so expensive, it is usually used as _______
a veneer over wood stud walls or over concrete block walls
Concrete block is the common term for ______
concrete masonry unit (CMU)
Most common CMU size?
8”x8”x16” nominal (actual dimensions are 3/8” less than nominal to count for mortar)