Chapter 30 - Bidding and Negotiating of Contracts Flashcards

1
Q

What’s the first step in CA?

A

finding a contractor and establishing an agreement between the owner and the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Contracts between owners and contractors can be done in two ways

A

bid or negotiated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

With a _____ contract, the owner (with the possible assistance of an interior designer) selects a contractor to do the work.

A

negotiated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

With a ___ contract, the drawings and specifications are completed by the interior designer (and other consultants if necessary) and then sent to several general contractors who bid on the work defined by the contract document

A

bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what type of selection of the contractor results in the lowest price?

A

competitive bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Does AIA provides a document called Instructions to Bidders that outlines typical procedures and documents for bidding?

A

yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Is bidding open to any contractor?

A

it can be or it can be limited to a list of contractors prequalified by the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

why prequalify bidders?

A

to select only those who meet certain standards of reliability, experience, financial stability, and performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

once bids are received, what are they mainly reviewed upon?

A

price
personnel
completion time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

there are two ways to advertise for bids

A
  1. public advertisement (in newspaper, trade magazine, or online)
  2. invitation to bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

when are prequalified bidders used?

A

when an invitation to bid will be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

where can bid documents be found?

A

designer’s office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

do contractors pay for the documents?

A

they typically put down a deposit and if the documents are returned in good condition, then they get their deposit back
electronic document services can also make the documents available online

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Should info about substitutions be included in the instructions to bidders?

A

yes–many contractor request that substitutions be considered for some materials. this most often happens when there are proprietary specs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

bidders have to submit the substitution request with backup. If the designer accepts it, what happens next?

A

the designer issues an addendum stating this fact and sends it to all the bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

During the bid process, there are always questions that need answers, errors that are discovered, and changes that the owner or interior designer decides to make. A(an) _________ is a written or graphic document issued by the interior designer before the execution of the contract that modifies or interprets the bidding documents by additions, deletions, clarifications, or corrections.

A

addendum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

when are addenda issued?

A

during the bidding process before bids are submitted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

is there a deadline for issuing an addendum?

A

yes- four days before the bids are due

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

what happens at a bid opening?

A

most are conducted by the interior designer, with the owner and bidders present. the bids are read aloud. a bid log is prepared to note the base bid amount, amounts of alternates (if any), whether receipt of any addenda was acknowledged, and other pertinent information. there should be no announcement of the apparent low bid at the bid opening

20
Q

A decision on contractor is usually made no more than __ days after the bid opening

A

10

21
Q

Who evaluates the bids?

A

the designer can help the owner evaluate the bid

22
Q

can the owner reject and or all bids?

A

yes

23
Q

if all the bids exceed the project budget and the owner-designer agreement fixes a limit on construction costs, the owner has four options

A
  1. rebid (or renegotiate)2. authorize an increase in the construction cost3. work with the designer to revise the scope to reduce costs4. abandon the project
24
Q

one advantage of having alternates in the drawings?

A

it’s a flexible way to deleting or substitute materials or construction elements to reduce the project cost if the bid is too high

25
Q

who prepares the bidding documents?

A

the interior designer using standard forms or forms provided by the owner

26
Q

where are the bidding documents located?

A

they are usually bound in the project manual , but the are not a legal part of the contract documents

27
Q

Bidding documents include:

A

advert or invitation to bid
instructions to bidders
bid forms
bid security information
requirements for a performance bond, if any
requirements for labor and material payment bond, if required

28
Q

what else is included in the bidding package?

A

drawings, specs, general and supplementary conditions of the contract, addenda issued before the receipt of bids, and a form of agreement between owner and contractor

29
Q

how are bids submitted?

A

in a sealed envelope with the name of the party receiving the bid on the outside along with the project name and the name of the company submitting it

30
Q

AIA produces a document entitled “Instructions to Bidders”These instructions normally include:

A

consideration of bids
bidders’ representation bidding documents
substitutions
bonds
interpretation or correction of bidding documents
addenda
modification or withdrawal of bid
post-bid information

31
Q

What happens if there’s an error inconsistency in the drawings that a bidder notices?

A

the bidder should alert the designer at least 7 days before bid opening and the designer should issue an addendum to all bidder answering the question

32
Q

If a bidder proposes a substitution, who does the burden of the proof of the merit of the substitution rest on?

A

the bidder

33
Q

can substitutions be considered after the contract is awarded?

A

no (unless there is a valid reason)

34
Q

_____ is used to ensure that the successful bidder will enter into a contract with the owner

A

bid security

35
Q

is bid security used more often on small or large projects?

A

large

36
Q

The final decision concerning the requirements for bid security is the ________’s

A

owner’s

37
Q

Form of bid security?

A

certified check, cashier’s check, or bid bond

38
Q

How is the bid security used?

A

if the successful bidder does not enter into an agreement, the bid security may be retained to compensate for the difference between the low bid and the next lowest bid

39
Q

A _____ is a statement by a surety company that obligates the surety company to complete construction of the project should the contractor default on his or her obligations

A

performance bond

40
Q

Are performance bonds mandatory?

A

They are, on public work

41
Q

What is the cost of a performance bond?

A

usually around 3% and is ultimately paid by the owner because it is included in the total amount of the contract price

42
Q

A ________ is usually required along with a performance bond. This is because a performance bond ensure the completion of the contact, but it does not guarantee payment for labor and materials by a defaulting contractor

A

labor and material payment bond

43
Q

An ______ is a request included in the bidding documents asking the contractor to supply a price for some type of variation from the base bid.

A

alternate

44
Q

_______ are set costs for certain portions of the work based on individual quantities, such as linear feet or square yards, of installed material.

A

unit prices

45
Q

Why are unit prices used?

A

they are listed on the bid form and provide a basis for determining changes to the contract. ex: a cost per square foot for adding parquet flooring may be requested if the full extent of this type of flooring in unknown

46
Q

An _________ is a set amount of money estimated by the interior designer to cover a particular material or piece of equipment when the cost for that material is unknown

A

allowance

47
Q

where do you put allowances in the drawings?

A

in the specs