10.2 Explain Proactive and Reactive Responses to risks Flashcards
What are the responses to risks ?
Accept
Avoid
Transfer
Reduce
What are the responses to opportunities ?
Enhance
Exploit
Reject
Share
Is avoiding a reactive or proactive response and why ?
Proactive - because it is planned and implemented in advance
Why would a project manager avoid a risk
To avoid the impact the risk can have on the project objectives
Depending on what , what would a project manager do to avoid a risk and why ?
Depending on the risk , the project manager could Change the projects objectives and practices to discount the cause of the risk
What could changing a projects objectives and practices to avoid a risk be seen as and why ?
An inconvenience due to the nature of a risk where is is uncertain that the risk would actually occur
How can a project manager determine whether it is worth avoiding a risk ?
Through the use of a risk register , determining the likelihood of a risk occurring and the impact a risk would have on a project
When the project uses a risk register what does it allow the project manager to do when determining whether to avoid a risk and do what ?
Use it as baseline to decide whether to avoid a risk and therefore make changes to a project initial objective.
What does avoiding a risk seeks to do and how ?
Eliminate the risk by changing the cause of the risk
An example of avoiding a risk ?
Risk : insufficient resources may lead to project delay
Avoidance : adjusting the project schedules to ensure resources are available when needed or replacing or deaconing the project deliverables with something else
What does reducing a risk tackle ?
The source of the risk
Is reducing a risk a proactive or reactive response and why ?
Proactive response as it focuses on the cause of risk
What is reducing a risk seen as ?
A preventive and good effective option for risk control
Actions to reduce a risk reduces what and in terms of what ?
Actions to reduce a risk reduces the impact of a threat in terms of
It’s probability of occurring or it’s impact on the project are considered and implemented
When reducing a risk what does a project manager implement and what is it usually associated with ?
A project would implement a preventative action usually associated with cost and time management
What could the action to reduce a threat potentially be to a project ?
The action to reduce a threat could potentially be a cost to the project
When reducing a risk What would the project manager need to ensure when implementing a preventive action is ?
Worthwhile and cost less than the expected risk value
Why would you need to monitor the risk and action when reducing a risk ?
The risk and action will need to be monitored to ensure that that action taken does in fact reduce the risk as expected
Is transferring a risk a proactive or reactive response and what happens ?
It is a proactive response where the risk os transferred from one party to another
Why is the risk / threat transferred , to who and why ?
If the risk / threat is deemed as outside the capacity or capability of the host organisation they may choose to transfer the risk to an external entity or a Third party who are deemed more capable of managing the risk
What does transferring a risk not prevent and what would the project manager need to do and why ?
Transferring the risk does not prevent the risk from occurring therefore the project manager will need to understand how the 3rd party is managing the risk as it may still impact the project
What is another way of transferring a risk ?
Through insurance
What are the various reasons a project manager may choose to transfer a risk ?
- lacking expertise or resource
- mitigating financial risk
- complying with legal regulations
- focusing on core project activities
What is risk transfer and what does it ensure
Risk transfer is a strategic decision , made by the project manager ensuring that the risks are managed by those best equipped to do so
What does transferring a risk require and why ?
Transferring a risk requires a balanced approach as it likely that elements of residual risk will remain on both sides
Is accepting a risk a proactive or reactive response and what happens to the risk and how ?
A reactive response where the risk is accepted with a contingency plan to be implemented in case the risk materialises.
When is the option of accepting a risk chosen ?
When the project manager and project sponsor agree there is no viable approach to avoid or reduce the risk or when the probability and/or impact of the risk is low
Where does the risk remain when accepted and why ?
The risk / threat remains in the risk register and will continue to monitored in case the probability of the impact changes and a more proactive response needs to be chosen.
What happens when a decision to accept a risk is choosen and in relation to what?
A contingency plan can be established in relation to the schedule and cost
What should happen to the status of an accepted risk and what should happen with the impact of an accepted risk ?
The status of the risk should be actively monitored and any impact of that risk on stakeholders should be reported accordingly
When is the response to accept a risk chosen by the project sponsor ?
The response to accept a risk is usually choose by the project sponsor on two situations:
- Where the risk is within the risk tolerance
- The cost of reducing the risk is to high
Accepting a risk is a _________ response where the risk is accepted with a __________ to be implemented should the risk ____________
Reactive
Contingency plan
Materialise
A risk is accepted when the project manager and sponsor agree that there are no viable approaches to _______ or _______ the risk or the _______and/or _______ of the risk is ________
Reduce
Avoid
Impact
Likelihood
Low
When a risk is accepted the threat remains on the _________ and will continue to be _________ in case either the _______ or the _______ changes and a more proactive approach needs to be chooses
Risk register
Monitored
Impact
Probability
Where a decision to accept a risk is chosen a __________ can be established in relation to ___________ and ________ and the status of the risk should be actively _______ on a ___________ and any impact of this risk on __________ should be ______ accordingly
Contingency plan
Cost and schedule
Monitored
Regular Basis
Stakeholders
Reported
The response to accept a risk is usually agreed by the sponsor in two situations : the risk is within the ________or the cost of trying to ________ the risk is too ____
Risk tolerance
Reduce
High
Transferring a risk is a _________ response where the risk is ______ from one ______ to ______
Proactive
Transferred
Party
Another
A risk is transferred if the risk / threat is deemed as _______ the ______ and ______ of the ________ they may choose to transfer the risk to ________ or a ______ who are deemed _______ of ______ the risk
Outside
Capacity
Capability
Host organisation
An external Entity
Third party
Capable
Managing
Transferring a risk does not ________ the risk from ______ therefore the project manager will need to understand how the third party is __________ the risk as it can still _______ the project
Prevent
Occurring
Managing
Impact