10.2 Explain Proactive and Reactive Responses to risks Flashcards

1
Q

What are the responses to risks ?

A

Accept
Avoid
Transfer
Reduce

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the responses to opportunities ?

A

Enhance
Exploit
Reject
Share

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Is avoiding a reactive or proactive response and why ?

A

Proactive - because it is planned and implemented in advance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why would a project manager avoid a risk

A

To avoid the impact the risk can have on the project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Depending on what , what would a project manager do to avoid a risk and why ?

A

Depending on the risk , the project manager could Change the projects objectives and practices to discount the cause of the risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What could changing a projects objectives and practices to avoid a risk be seen as and why ?

A

An inconvenience due to the nature of a risk where is is uncertain that the risk would actually occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How can a project manager determine whether it is worth avoiding a risk ?

A

Through the use of a risk register , determining the likelihood of a risk occurring and the impact a risk would have on a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When the project uses a risk register what does it allow the project manager to do when determining whether to avoid a risk and do what ?

A

Use it as baseline to decide whether to avoid a risk and therefore make changes to a project initial objective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does avoiding a risk seeks to do and how ?

A

Eliminate the risk by changing the cause of the risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

An example of avoiding a risk ?

A

Risk : insufficient resources may lead to project delay

Avoidance : adjusting the project schedules to ensure resources are available when needed or replacing or deaconing the project deliverables with something else

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does reducing a risk tackle ?

A

The source of the risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Is reducing a risk a proactive or reactive response and why ?

A

Proactive response as it focuses on the cause of risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is reducing a risk seen as ?

A

A preventive and good effective option for risk control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Actions to reduce a risk reduces what and in terms of what ?

A

Actions to reduce a risk reduces the impact of a threat in terms of

It’s probability of occurring or it’s impact on the project are considered and implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When reducing a risk what does a project manager implement and what is it usually associated with ?

A

A project would implement a preventative action usually associated with cost and time management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What could the action to reduce a threat potentially be to a project ?

A

The action to reduce a threat could potentially be a cost to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When reducing a risk What would the project manager need to ensure when implementing a preventive action is ?

A

Worthwhile and cost less than the expected risk value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Why would you need to monitor the risk and action when reducing a risk ?

A

The risk and action will need to be monitored to ensure that that action taken does in fact reduce the risk as expected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Is transferring a risk a proactive or reactive response and what happens ?

A

It is a proactive response where the risk os transferred from one party to another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Why is the risk / threat transferred , to who and why ?

A

If the risk / threat is deemed as outside the capacity or capability of the host organisation they may choose to transfer the risk to an external entity or a Third party who are deemed more capable of managing the risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What does transferring a risk not prevent and what would the project manager need to do and why ?

A

Transferring the risk does not prevent the risk from occurring therefore the project manager will need to understand how the 3rd party is managing the risk as it may still impact the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is another way of transferring a risk ?

A

Through insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the various reasons a project manager may choose to transfer a risk ?

A
  • lacking expertise or resource
  • mitigating financial risk
  • complying with legal regulations
  • focusing on core project activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is risk transfer and what does it ensure

A

Risk transfer is a strategic decision , made by the project manager ensuring that the risks are managed by those best equipped to do so

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What does transferring a risk require and why ?

A

Transferring a risk requires a balanced approach as it likely that elements of residual risk will remain on both sides

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Is accepting a risk a proactive or reactive response and what happens to the risk and how ?

A

A reactive response where the risk is accepted with a contingency plan to be implemented in case the risk materialises.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

When is the option of accepting a risk chosen ?

A

When the project manager and project sponsor agree there is no viable approach to avoid or reduce the risk or when the probability and/or impact of the risk is low

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Where does the risk remain when accepted and why ?

A

The risk / threat remains in the risk register and will continue to monitored in case the probability of the impact changes and a more proactive response needs to be chosen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What happens when a decision to accept a risk is choosen and in relation to what?

A

A contingency plan can be established in relation to the schedule and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What should happen to the status of an accepted risk and what should happen with the impact of an accepted risk ?

A

The status of the risk should be actively monitored and any impact of that risk on stakeholders should be reported accordingly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

When is the response to accept a risk chosen by the project sponsor ?

A

The response to accept a risk is usually choose by the project sponsor on two situations:

  1. Where the risk is within the risk tolerance
  2. The cost of reducing the risk is to high
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Accepting a risk is a _________ response where the risk is accepted with a __________ to be implemented should the risk ____________

A

Reactive
Contingency plan
Materialise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

A risk is accepted when the project manager and sponsor agree that there are no viable approaches to _______ or _______ the risk or the _______and/or _______ of the risk is ________

A

Reduce
Avoid
Impact
Likelihood
Low

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

When a risk is accepted the threat remains on the _________ and will continue to be _________ in case either the _______ or the _______ changes and a more proactive approach needs to be chooses

A

Risk register
Monitored
Impact
Probability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Where a decision to accept a risk is chosen a __________ can be established in relation to ___________ and ________ and the status of the risk should be actively _______ on a ___________ and any impact of this risk on __________ should be ______ accordingly

A

Contingency plan
Cost and schedule
Monitored
Regular Basis
Stakeholders
Reported

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

The response to accept a risk is usually agreed by the sponsor in two situations : the risk is within the ________or the cost of trying to ________ the risk is too ____

A

Risk tolerance
Reduce
High

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Transferring a risk is a _________ response where the risk is ______ from one ______ to ______

A

Proactive
Transferred
Party
Another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

A risk is transferred if the risk / threat is deemed as _______ the ______ and ______ of the ________ they may choose to transfer the risk to ________ or a ______ who are deemed _______ of ______ the risk

A

Outside
Capacity
Capability
Host organisation
An external Entity
Third party
Capable
Managing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Transferring a risk does not ________ the risk from ______ therefore the project manager will need to understand how the third party is __________ the risk as it can still _______ the project

A

Prevent
Occurring
Managing
Impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

When transferring a risk the third party will need to be the one to _________ an ______ to ________ with the risk and be the ones to _____ any ______ associated with that action

A

Implement
Action
Deal
Bare
Cost

41
Q

Another way of transferring a risk is through taking out ______

A

Insurance

42
Q

A project manager may choose to transfer a risk for various reasons :

Lacking _____ or ______
________ Financial risk
_______ with ______________
Or focusing on ___________

A

Resources or expertise
Mitigating
Complying with legal regulations
Core project activity

43
Q

Transferring a risk is a _______ made by the _________ and ensures that the risks are _______ by those best _______ to do so

A

Strategic decision
Project manager
Managed
Equipped

44
Q

Transferring a risk requires a _____________ as it is likely that ______ of _________ risk will remain on _______

A

Balanced approach
Elements
Residual
Both sides

45
Q

Reducing a risk tackles ……?

A

The source of the risk

46
Q

Reducing a risk is a ________ response and focuses on the ______ of the risk

A

Proactive
Cause

47
Q

Reducing a risk is seen as a _______ and good _______ option for _______

A

Preventive and good effective option for risk control

48
Q

When reducing a risk actions either reduce the _________of the threat in terms of the ___________ of ______________ or its ___________ on a project is_______ and ________

A

Impact of the threat in terms of the probability of occurring or it’s impact are considered and implemented

49
Q

When reducing a risk the project manager would implement an __________ action usually associated with ________

A

Preventive
Cost and time

50
Q

When reducing a risk the project manager needs to ensure that the cost of _______the preventive action is _______ and __________ than the expected ________

A

Implementing
Worthwhile and cost lest than the expected risk value

51
Q

The action to reduce a threat could potentially be a _____________ therefore the risk and ________ implemented will need to be _______ to ensure that the __________ does ___________ risk as expected

A

Cost to the project
Action
Monitored
Action taken
Reduce

52
Q

Avoiding a risk is a ________ response as it is ________ and _________ in advanced

A

Proactive
Planned
Implemented

53
Q

Avoiding a risk avoids the _________ the risk could have on the projects _______ where depending on the ________ the project manager could change the projects __________ or __________ in order to ________ the _______ of the risk

A

Impact
Objectives
Risk
Objectives or practices
Discount
Cause

54
Q

Avoiding a risk can be seen as an __________ due to the ________ of risks where it is ________ that the risk will actually _______. However through the use of a __________ and determining the __________ of the risk ________ and the ________ the risk would have on the project the PM can use that as a ___________ to decide to ________ the risk and therefore make _________ to the initial _________

A

Inconvenience
Nature
Uncertain
Occur
Risk register and defending the Likelihood of the risk Occurring
Impact the risk would have in the project
Baseline to decide to avoid
Changes
Objectives

55
Q

Avoiding a risk seeks to ___________ a risk by changing the _______ of the _______.

A

Eliminate a risk
Cause of the thread

56
Q

Examples of avoiding a risk - insufficient ________ may lead to _________ . This can be avoided by ___________ additional ________ or by ________ the projects _________ to ensure _________ are ________ when needed.

A

Resources may lead to project delays
Allocating additional resources
Changing the project schedule
Resources are available when needed

57
Q

Is exploiting a risk a proactive or reactive response ?

A

A proactive response

58
Q

What does exploiting a risk do and how ?

A

Maximises both the probability and impact of the opportunity by implanting a action to exploit the risk and gain maximum benefit/ advantage

59
Q

What does exploiting a risk allow you to do ?

A

Gain maximum benefit/advantages

60
Q

How does exploiting a risk allow you to gain maximum benefit / advantage ?

A

By implementing an action to exploit the risk

61
Q

What needs to be clearly understood when exploiting a risk and who does it need to be agreed by

A

The implications need to be clearly understood and agreed to by all stakeholders

62
Q

Why does the implications of exploiting a risk need to be clearly understood and agreed to by all stakeholders ?

A

Because exploiting a risk often requires a change during the project

63
Q

What kind of change does exploiting a risk often require ? And may benefit what ?

A

A change in scope , acceptance of more risks , or a change to timescales and budget and may only benefit so stakeholders

64
Q

Exploiting a risk is taking advantage of what ? And to do what?

A

Favourable conditions to Maximise project benefits

65
Q

Examples of exploiting a risk could be ? And results in what ?

A

Strategically allocating resources or accelerating timelines.

Resulting in cost savings or efficiency gains

66
Q

Is enhancing an opportunity a proactive or reactive response and why ?

A

Proactive , Enhancing a risk is strategic / tactical to enhance the opportunity by increasing it likelihood and or impact.

67
Q

What does enhancing a risk do to an opportunity ?

A

Increases the likelihood and or impact

68
Q

What is an example of enhancing a risk and what would the project do ?

A

An opportunity could be identified to deliver the project earlier and achieve a reward payment from the client.

The project could take a practical approach and revise the project schedule and fast track tasks while adding resource to shorten their duration

69
Q

What is important to consider when enhancing a risk and why ?

A

It is important to consider the cost of the actions when enhancing a risk as it should not be more that the reward pavement on offer

70
Q

What does enhancing an opportunity further increase ?

A

Enhancing an opportunity further increases the potential benefits and value derived from a favourable risk

71
Q

What is the difference between exploiting and enhancing a risk ?

A

Exploiting a risk maximises the probability and or impact of a risk

Enhancing a risk increases the likelihood and or impact of a risk

72
Q

Is sharing a risk proactive or reactive ?

A

Sharing a risk is proactive

73
Q

What happens when a risk is shared ? And why ?

A

Collaboration takes place to increase the chances of the opportunity being realised through sharing some of the responsibility with another party

74
Q

How does sharing a risk increase the chances of the opportunity being realised ?

A

Through sharing some of the responsibility with another party.

75
Q

Why would the risk be shared with another party ?

A

They may be better placed to help realise the benefits associated with the risk

76
Q

What may the other party be better placed to realise when sharing a risk ?

A

The benefits associated with that risk

77
Q

What is likely to be required from both parties when sharing a risk ?

A

A cost investment from both sides is likely to be required when sharing a risk

78
Q

Example of sharing a risk :

A

A contract has a bonus to be gained from delivering early the project could share the opportunity with the supplier

Incentivising them to finish earlier in support of the end goal

79
Q

What does sharing a risk promote and leverage ? And what are the result of this ?

A

Sharing a risk promotes collaboration and leverages expertise enhancing the likelihood of successfully releasing the opportunity

80
Q

Is rejecting a risk proactive or reactive and why does it happen ?

A

Rejecting a risk is proactive and may be chosen as a response when the proactive pursuit of an opportunity is rejected because it is deemed of little value or the benefits associated with it are not deemed significant enough to justify actions

81
Q

Why may a risk be rejected ?

A

When the proactive pursuit of the risk is deemed of little value or the benefits associated with it are deemed not significant enough to justify action

82
Q

What is deemed of little value when rejecting a risk?

A

The proactive pursuit of the opportunity

83
Q

What is deemed as not significant enough to justify an action when rejecting a risk ?

A

The benefits associated with it

84
Q

A risk may rejected because the cost or time needed to implement an action may ?

A

Outweigh the benefits associated with releasing the opportunity

85
Q

What is the reason for a project team rejecting a rosk ?

A

A project team would naturally take advantage of the opportunity should it arise but not take proactive steps to pursue it further

86
Q

Exploiting a risk is a _________ response to _________ both the _________ and ______ of the opportunity by ________ an ________ to ________ the risk and gain maximum ______ / ________

A

Proactive
Maximise
Probability
Likelihood
Implementing
Action
Maximise
Benefit / advantage

87
Q

When exploiting a risk the ________ needs to be clearly _________ and agreed upon by all _________ because exploiting a risk often requires a ________ during the ______ e.g a change in _______ acceptance of more ______ or a change to _____ and _____ and may only benefit ___________

A

Implications
Understood
Stakeholders
Change
Project

Scope
Risk
Budget and timescales
Some stakeholders

88
Q

Exploiting a risk is taken _________ of ___________ to maximise project ______ e,g strategically allocating ___________ or accelerating _______ resulting in _________ savings or _______ gains

A

Advantage
Favourable conditions
Benefits
Resources
Timelines
Cost savings or gains

89
Q

Enhancing a risk is a _______ response because it is _________\ to enhance the opportunity by ________ its ________ and or _______

A

Proactive response
Strategic / tactical
Increasing
Likelihood and or impact

90
Q

An example of enabling a risk could be an opportunity identified to __________ the project _____ and achieve a _____________ from the client. The project team may take a _________ approach by revisiting the projects ___________ and fast__________ tasks , whilst also adding ____________ to task to shorten their ______

A

Deliver
Early
Reward payment
Tactical approach
Schedule
Fast tracking
Addicaonal resources to tasks
Duration

91
Q

When enabling a a risk it is important to consider the _____ these actions as it should not be ______ than the ____________ on offer

A

Cost
More
Reward payment on offer

92
Q

Enhancing an opportunity further increase the potential __________ and _______ derived from a ___________

A

Benefits
Value
Favourable situation

93
Q

Sharing a risk is a ________ response where ______ takes place to _________ the chances of the opportunity being ________ through sharing some of the _________ with another ______ who may be better placed to help _________ the __________ associated with the opportunity

A

Proactive
Collaboration
Increase
Realased
Responsibility
Party
Realise
Benefits

94
Q

When sharing a risk a ______________ from _______is likely to be _______ for example if a contract has a _______ to be gained from delivering the project early, the project could choose to _______ the opportunity with the _______ incentivising them to finish earlier in support of the end goal.

A

Cost investment
Both side
Required
Bonus
Share
Supplier

95
Q

Sharing a risk promotes _________ and _______ expertise enhancing the ________ likelihood of ________ realising the opportunity

A

Collaboration
Leverages
Successfully

96
Q

Rejecting a risk is a __________ response and may be chosen when the _______ pursuit of an opportunity is _______because it is deemed of _________ or the benefits associated with it are deemed not _______ enough to justify actions

A

Proactive
Proactive pursuit
Rejected
Little value
Significant

97
Q

A risk may be rejected because the _____ or _______ needed to implement an action may ________ the benefits associated with _____ the opportunity

A

Cost or time
Our weight
Realising the opportunity

98
Q

In cases of rejecting a risk , the project team would naturally __________ of the opportunity should it arise _______ but not take ________to pursue it further

A

Take advantage
Natural
Proactive steps