Project Management Flashcards

1
Q

What is critical path analysis?

A

A method of organising the different activities involved in a project in order to find the most efficient means of completing a task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the aim of cpa?

A

To complete the project in the shortest time possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is CPA used?

A
  • To prevent machines/labour sitting idle

- To ensure materials are delivered well before they are needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the first steps of CPA?

A
  • Identify all tasks
  • See how long each task will take
  • Determine in which order the tasks need to be completed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are parallel tasks in CPA?

A

Tasks that can be done simultaneously

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are dependent tasks in CPA?

A

Tasks that can’t be started until the previous task has been completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is the critical path established?

A

When the EST = LFT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does it mean if a task isn’t on the critical path?

A

There is an element of float/leighway

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the issues with CPA?

A
  • Can encourage rigidity if managers stick to plan and miss opportunities for flexibility: opportunity cost
  • All timescales are estimated: bias depending who has made it - overoptimism
  • Focus is on speed - could compromise quality
  • Complex tasks may be difficult to represent effectively
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a PERT?

A

Programme Evaluation and Review Technique, pessimistic version of CPA, focuses on duration and finds optimistic time, pessimistic time and most likely time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the formula for the expected time in a PERT analysis?

A

E = O + (4 x m) + P / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of PERT?

A
  • More realistic as considers the pessimistic time
  • Simple formula to apply
  • Able to see a critical path
  • A lot of data can be visually represented to aid decisions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the disadvantages of PERT?

A
  • Gauging the optimistic times is guesswork unless the project has been done before
  • Gauging the pessimistic times is guesswork
  • Complicated to use
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is total float?

A

Total float is the amount of time an activity can be delayed without delaying the project completion date. On a critical path, the total float is zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is free float?

A

Free float is the amount of time an activity can be delayed without delaying the Early Start of the next activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is total float calculated?

A

LFT of current activity - duration of current activity - EST of current activity

17
Q

How is free float calculated?

A

EST of next activity - duration of current activity - EST of current activity

18
Q

What is a Gantt chart?

A

A graphical representation of the order and duration of given tasks within a project.