What are the primary causes of project failures?

A

Change in org. Priorities
Poor Requirements gathering
Change in project objectives
Poor upfront planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the TOC 5-step process of focusing?

A

Identify
Exploit
Subordinate
Elevate
Start Over

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Parkinson’s Law

A

Work expands to fill (and usually exceed) the time allowed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the 3 Minute Egg Rule

A

It’s not quality if a task is finished before the time us up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Sandbagging

A

Holding Completed Work until the deadline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is “Aggressive, but Possible Times” ABPT

A

When someone estimates their time to complete a task, cut it in half and use that.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Critical Chain

A

Find the longest sequence of dependent events that prevents the project from completing sooner, based on ABPT Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How much safety buffer do you use for projects?

A

you use about half of the safety removed from the tasks from ABPT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Steps in Critical Chain Project Management

A

Determinte ABPT for each step
Identify critical chain
Add in project feeders, with buffers
Use Buffer Management to monitor project progress
Avoide multi tasking