Project Documents Flashcards

1
Q

Multiple attributes associated with each schedule activity that can be included within the activity list.

A

Activity Attributes

Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A project document used to record all assumptions and constraints throughout the project life cycle.

A

Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a document that identifies the logic, data, methodology and calculations used to estimate the resources required to perform a specific task or group of related tasks.

A

Basis of Estimate (BOE)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A comprehensive list of changes submitted during the project and their current status

A

Change Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

the approximation of the cost of a program, project, or operation.

A

cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

is a process you can use to adapt cost planning to constantly changing circumstances.

A

cost forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

the estimation of the amount of time required by a certain project activity given the available resources

A

Duration Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project document where information about issues is recorded and monitored.

A

Issue Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project document used to record knowledge gained during a project so that it can be used in the current project and entered into the lessons learned repository.

A

lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

__________ list is a project management document that identifies all project milestone

A

milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The documentation of the material, equipment, supplies, locations, and other physical resources that will be used during the project.

A

Physical resource assignments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A calendar that identifies working days and shifts that are available for scheduled activities. More than one may be required to allow for different work periods for some activities.
Created in:

Develop Schedule (P)
Updated in:
Develop Schedule (P)
Input to:
Control Schedule (M&C)
Part of:

Project documents

A

project calendar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Documents such as performance reports, deliverable status, schedule progress, cost incurred, presentations, and other information required by stakeholders.

Created in:

Manage Communications (E)
Updated in:
Manage Communications (E)
Input to:

Direct and Manage Project Work (E)
Monitor Communications (M&C)
Monitor Stakeholder Engagement (M&C)
Close Project or Phase (C)

A

project communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.

A

project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A graphical representation of the logical relationships among the project schedule activities

A

Project Schedule Network Diagram

17
Q

The description of the project scope, major deliverables, assumptions, and constraints

A

Project Scope Statement

18
Q

Documentation recording the team members and their roles and responsibilities for the project.

A

project team assignments

19
Q

The documented results of control quality activities.

A

Quality Control Measurements

20
Q

are used to directly translate customer needs into acceptable performance measures in both products and processes

A

Quality Metrics

21
Q

A project document that includes quality management issues, recommendations for corrective actions, and a summary of findings from quality control activities and may include recommendations for process, project, and product improvements.

A

Quality Report

22
Q

A description of how individual requirements meet the business need for the project

A

Requirements Documentation

23
Q

A grid that links product requirements from their origin to the deliverables that satisfy them.

A

Requirements Traceability Matrix

24
Q

A hierarchical representation of resources by category and type.

A

resource breakdown structure

25
Q

A calendar that identifies the working days and shifts upon which each specific resource is available.

A

Resource Calendar

26
Q

The types and quantities of resources required for each activity in a work package.

A

Resource Requirements

27
Q

A repository in which outputs of risk management processes are recorded

A

Risk Register

28
Q

A project document developed progressively throughout the Project Risk Management processes, which summarizes information on individual project risks and the level of overall project risk.

A

Risk Report

29
Q

The collection of information for describing and controlling the schedule.

A

Schedule Data

30
Q

Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated.

A

Schedule Forecasts

31
Q

A project document including the identification, assessment, and classification of project stakeholders.

A

Stakeholder Register

32
Q

A document that records the team values, agreements, and operating guidelines, as well as establishing clear expectations regarding acceptable behavior by project team members.

A

Team Charter

33
Q

Project documents that describe the activities used to determine if the product meets the quality objectives stated in the quality management plan.

A

Test and Evaluation Documents