PRECEDENCE DIAGRAMMING METHOD Flashcards
A logical relationship in which a successor activity cannot start until a predecessor activity has finished. For example, installing the operating system on a PC (successor) cannot start until the PC hardware is assembled (predecessor).
Finish-to-start (FS).
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. For example, writing a document (predecessor) is required to finish before editing the document (successor) can finish.
Finish-to-finish (FF).
A logical relationship in which a successor activity cannot start until a predecessor activity has started. For example, level concrete (successor) cannot begin until pour foundation (predecessor) begins.
Start-to-start (SS).
A logical relationship in which a successor activity cannot finish until a predecessor activity has started. For example, a new accounts payable system (successor) has to start before the old accounts payable system can be shut down (predecessor).
Start-to-finish (SF).
In PDM, _______ is the most commonly used type of precedence relationship.
FS
The _______ relationship is very rarely used, but is included to present a complete list of the PDM relationship types.
SF
_________ loops are also not recommended in logical relationships.
Closed
_____ activities can have two logical relationships at the same time (for example, SS and FF). Multiple relationships between the same activities are not recommended, so a decision has to be made to select the relationship with the highest impact.
Two