PMBOK Acronyms Flashcards

1
Q

AC

A

actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

BAC

A

budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CCB

A

change control board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

COQ

A

cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CPAF

A

cost plus award fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPFF

A

cost plus fixed fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI

A

cost performance index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPIF

A

cost plus incentive fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CPM

A

critical path method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CV

A

cost variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EAC

A

estimate at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EF

A

early finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

ES

A

early start date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

ETC

A

estimate to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EV

A

earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

AC

A

actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

BAC

A

budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

CCB

A

change control board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

COQ

A

cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

CPAF

A

cost plus award fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

CPFF

A

cost plus fixed fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

CPI

A

cost performance index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

CPIF

A

cost plus incentive fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

CPM

A

critical path method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

CV

A

cost variance

26
Q

EAC

A

estimate at completion

27
Q

EF

A

early finish date

28
Q

ES

A

early start date

29
Q

ETC

A

estimate to complete

30
Q

EV

A

earned value

31
Q

EVM

A

earned value management

32
Q

FF

A

finish-to-finish

33
Q

FFP

A

firm fixed price

34
Q

FPEPA

A

fixed price with economic price adjustment

35
Q

FPIF

A

fixed price incentive fee

36
Q

FS

A

finish to start

37
Q

IFB

A

invitation for bid

38
Q

LF

A

late finish date

39
Q

LOE

A

level of effort

40
Q

LS

A

late start date

41
Q

OBS

A

organizational breakdown structure

42
Q

PDM

A

precedence diagramming method

43
Q

PMBOK

A

Project Management Body of Knowledge

44
Q

PV

A

planned value

45
Q

QFD

A

quality function deployment

46
Q

RACI

A

responsible, accountable, consult, and inform

47
Q

RAM

A

responsibility assignment matrix

48
Q

RBS

A

risk breakdown structure

49
Q

RFI

A

request for information

50
Q

RFP

A

request for proposal

51
Q

RFQ

A

request for quotation

52
Q

SF

A

start-to-finish

53
Q

SOW

A

statement of work

54
Q

SPI

A

schedule performance index

55
Q

SS

A

start-to-start

56
Q

SV

A

schedule variance

57
Q

SWOT

A

strengths, weaknesses, opportunities, and threats

58
Q

T&M

A

time and material contract”

59
Q

VAC

A

variance at completion

60
Q

WBS

A

work breakdown structure