PMP Formulas Flashcards
EV (Earned Value)
EV= Percentage complete x BAC
SV (Schedule Variance)
SV = EV – PV • Are you ahead or behind schedule? • See if the project is proceeding as planned • Zero at completion • Negative = behind schedule • Positive = ahead of schedule
CV (Cost Variance)
CV = EV – AC • Are you above or below budget? • See if the project is spending more/less/the same as planned. • Negative = cost overrun • Positive = cost savings
SPI (Schedule Performance Index)
SPI = EV/PV • Measure of schedule efficiency • Ratio of earned value to planned value • +1 = ahead of schedule • -1 = behind schedule
CPI (Cost Performance Index)
CPI = EV/AC • Measure of cost efficiency • Ratio of earned value to actual cost • Allows comparison across projects • Also known as “burn rate” • +1 = cost savings • -1 = cost overrun
EAC (Estimate At Completion) • EAC forecast for ETC work performed at the budgeted rate
EAC = AC + (BAC – EV)
EAC (Estimate At Completion) • EAC forecast for ETC work performed at the present CPI
EAC = BAC/CPI
EAC (Estimate At Completion) • EAC forecast for ETC work considering both SPI and CPI
EAC = AC + (BAC – EV) / (CPI x SPI)
EAC (Estimate At Completion)
EAC = AC + Bottom-up ETC
ETC (Estimate To Complete) • Estimate for the cost of all the remaining work in the project •
ETC = EAC – AC
TCPI (To Complete Performance Index)
TCPI = Working remaining/Funds remaining
“A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.”
TCPI = (BAC – EV) / (BAC – AC) • Greater than 1 • Harder to complete within budget • Take corrective action • Less than/equal to 1 • Performing better than expected
VAC (Varence At Completion)
VAC= BAC - EAC The result will tell you as of today if you will be over or under budget at the end of the project.
VAC% (Varence At Completion) Expresses the VAC as a percentage. Negative is over budget.
VAC= VAC / BAC x100
PV (Planned Value)
PV = Planned % x BAC
Three-Point Estimating or Triangle Distribution
= (P + M + O) / 3