B3 - FInancial Considerations - Lt #4 Flashcards

1
Q

What is a progress payment?

A

Payments that are made to the contractor when certain stages of construction have been completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why are holdbacks used?

A

Give the the owner time to ensure that all subs and suppliers have been paid or to cover unfinished or defective work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How long is the holdback period and how long does an unpaid party have to file under the Builder’s Lien Act?

A

The holdback period is usually 55 days, after substantial completion. Builders Lien Act allows 45 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why are allowances used in a contract?

A

Cash allowances are used where precise details of certain portions of the work are unknown at the time of bidding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is it important to have a clear scope of work for each allowance?

A

So that no overlap occurs between the allowance and the rest of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a contingency allowance used for?

A

Cover work that is unforeseen and unpredictable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe the three types of bonding required for a construction project.

A

1)Bid bond for entering into a contract
2)labor & material bond payment bond for covering payment to contractors & suppliers
3) Performance bond to make sure the job is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How can contractors protect themselves since they purchase materials in a job?

A

Contractors request payment for materials in advance as a down payment or once the materials have been delivered to the job site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the 10% holdback at the end of the project for?

A

A 55-day holdback at the end of the contract is to give the owner time to confirm that all suppliers and subcontractors have been paid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Small claims court can be used for claims less than:

A

25,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are allowances often used for in a contract?

A

Flooring, cabinets, and light fixtures. Contract allowances do not include taxes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If the actual cost of the work equals or is less than the allowance:

A

no overhead or profit is added to the cost of the work. If the cost of work exceeds the allowance, then the contractor can add on overhead and profit to the amount that exceeds the allowance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

During the project, when actual costs become known for each allowance, the price of the contract is amended with:

A

Change order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

It is very important to define the scope of work for each allowance why?

A

No overlap occurs between the allowance and the rest of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a contingency used for

A

To pad a contract bid price to cover missed items.

A contingency allowance is built into contracts for larger projects to cover work that is unforeseen and unpredictable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is bonding?

A

Insurance for a specific use and is paid for in a lump sum.

17
Q

What size jobs require bonding?

A

Larger jobs, in the hundreds of thousands of dollars, often millions.

18
Q

The company that issues the bond is called the:

A

Surety in the contract documents.

19
Q

What is a bid bond?

A

Usually, 10% of the bid price, must accompany the bid. Guarantee that the contractor will actually take the job if they are the low bidder.

20
Q

What is the labor and material bond?

A

Used to protect the owner from the liability of the wages and material costs should the contractor go broke.

21
Q

What is the performance bond?

A

To protect the owner in case the contractor cant finish the job. Usually in the amount of 50% to 100% of the bid price for the job.

22
Q

When bonds are in place, the owner is:

A

Well and protected, should the contractor not be able to fulfill the contract. Even with the bonding in place, the owner hires a PM to ensure the contractor is meeting goals.