B3 - FInancial Considerations - Lt #4 Flashcards
What is a progress payment?
Payments that are made to the contractor when certain stages of construction have been completed.
Why are holdbacks used?
Give the the owner time to ensure that all subs and suppliers have been paid or to cover unfinished or defective work.
How long is the holdback period and how long does an unpaid party have to file under the Builder’s Lien Act?
The holdback period is usually 55 days, after substantial completion. Builders Lien Act allows 45 days.
Why are allowances used in a contract?
Cash allowances are used where precise details of certain portions of the work are unknown at the time of bidding.
Why is it important to have a clear scope of work for each allowance?
So that no overlap occurs between the allowance and the rest of the contract.
What is a contingency allowance used for?
Cover work that is unforeseen and unpredictable
Describe the three types of bonding required for a construction project.
1)Bid bond for entering into a contract
2)labor & material bond payment bond for covering payment to contractors & suppliers
3) Performance bond to make sure the job is completed.
How can contractors protect themselves since they purchase materials in a job?
Contractors request payment for materials in advance as a down payment or once the materials have been delivered to the job site.
What is the 10% holdback at the end of the project for?
A 55-day holdback at the end of the contract is to give the owner time to confirm that all suppliers and subcontractors have been paid.
Small claims court can be used for claims less than:
25,000
What are allowances often used for in a contract?
Flooring, cabinets, and light fixtures. Contract allowances do not include taxes.
If the actual cost of the work equals or is less than the allowance:
no overhead or profit is added to the cost of the work. If the cost of work exceeds the allowance, then the contractor can add on overhead and profit to the amount that exceeds the allowance.
During the project, when actual costs become known for each allowance, the price of the contract is amended with:
Change order
It is very important to define the scope of work for each allowance why?
No overlap occurs between the allowance and the rest of the contract.
What is a contingency used for
To pad a contract bid price to cover missed items.
A contingency allowance is built into contracts for larger projects to cover work that is unforeseen and unpredictable.