AOP-7 "Rapid Power Reduction" Flashcards

1
Q

AOP-7 entry conditions

A
  • Use of AOP-7 is directed by another AOP

- CRS determines that abnormal plant conditions requires immediate power reduction at a rate > 30%/hour and < 300%/hour

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AOP-7 automatic actions

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AOP-7 reactor trip criteria

A
  • Either S/G level < 30%
  • Either S/G level > 95%
  • PZR level < 30%
  • PZR level > 62.8%
  • Tave < 525 F
  • Rack C, EK-0605 “TM/LO Pressure Channel Pre-Trip”
  • Rack B, EK-0608 “Hi Pressurizer Pressure Channel Pre-Trip”
  • More than 1 control rod misaligned (8” deviation) after attempted realignment
  • Plant cannot be stabilized following termination of power reduction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AOP-7 turbine trip criteria

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

AOP-7 immediate actions

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly