AOP-7 "Rapid Power Reduction" Flashcards
1
Q
AOP-7 entry conditions
A
- Use of AOP-7 is directed by another AOP
- CRS determines that abnormal plant conditions requires immediate power reduction at a rate > 30%/hour and < 300%/hour
2
Q
AOP-7 automatic actions
A
NONE
3
Q
AOP-7 reactor trip criteria
A
- Either S/G level < 30%
- Either S/G level > 95%
- PZR level < 30%
- PZR level > 62.8%
- Tave < 525 F
- Rack C, EK-0605 “TM/LO Pressure Channel Pre-Trip”
- Rack B, EK-0608 “Hi Pressurizer Pressure Channel Pre-Trip”
- More than 1 control rod misaligned (8” deviation) after attempted realignment
- Plant cannot be stabilized following termination of power reduction
4
Q
AOP-7 turbine trip criteria
A
NONE
5
Q
AOP-7 immediate actions
A
NONE