Q

AOP-22 entry conditions

A
  • EK-0735 “Charging Low Flow”
  • EK-0761 “Pressurizer Level HI-LO”
  • EK-0763 “Pressurizer Level Channel “A” LO-LO”
  • EK-0764 “Pressurizer Level Channel “B” LO-LO”
  • EK-0769 “Pressurizer High Level”
  • Loss of level control program output signal causing a deviation from the calculated level control setpoint
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AOP-22 automatic actions

A
  • PZR High Level - max letdown, min charging, and PZR Backup Heaters energize (in auto position only)
  • PZR Low Level - min letdown, max charging
  • PZR Low-Low Level - all PZR Heaters trip, CV-2003, Letdown Orifice Stop Valve, closes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AOP-22 reactor trip criteria

A

PZR Level < 30%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AOP-22 immediate actions

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly