AOP-27 "Tave/Tref Controller Failure" Flashcards

1
Q

AOP-27 entry conditions

A

EK-0967 “Loop 1-Loop 2 Tave Deviation” (5 F difference) in conjunction with:
-EK-0968 “Loop 1 Tave/Tref Gross Deviation” (5 F difference)
AND/OR
-EK-0969 “Loop 2 Tave/Tref Gross Deviation” (5 F difference)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AOP-27 automatic actions

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AOP-27 reactor trip criteria

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AOP-27 immediate actions

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly