3.3.4 Critical path analysis 👣 Flashcards

1
Q

What is critical path analysis 🧐 ?

A

It is a project management tool that uses network analysis used to plan complex and time sensitive project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the four purposes of a critical path analysis

A

efficiency - shows what Tasks can be carried out at the same time -Helps a production or instalment time

decision-making - Estimating how long project will take will help meet deadlines quickly

and implications of delays are assessed

Time based management- -Minimise the length of time spent on business processes - Identify tasks that need to be done in order

working capital control - Identify what resources will be required for the project and when we need to order them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe a node

A

On the left-hand side we have number of the day

on the top is the EST early starting time

on the bottom is the LFT latest finishing time

On top of the link is the letter of the activity and on the bottom is the duration

If the link has two slashes in it that means it is a critical path and we have to take it first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do we calculate the next EST for the next node?

What happens if We have two strands at the same time?

A

We add the EST and duration up and put it where the next EST for the next day is

If you have two at the same time you use the highest duration and add that up with the previous EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the four limitations of critical path analysis and the explanation ?

A

Very lengthy projects involve large number of activities that numerous dependencies -
Maybe the specialist planning software layers of supervision required - computer 🖥 may simply this

Network analysis such as CPA relies on estimates and forecasts-Significant research is required and a close relationship between suppliers are essential

Network analysis does not guarantee success on the project - project managers have to be highly skilled - experience

Resources may not be as flexible as hoped - employees may require additional training in order to transfer to critical tasks

machinery and other capital resources may require adaptation



How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do we calculate LFT ?

A

Right to left - LFT - duration

But in next LFT

Start with last node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How We calculate float time?

A

LFT - duration - Est

How well did you know this?
1
Not at all
2
3
4
5
Perfectly