Start Project Flashcards
What does it mean if an “R” is next to your name in a RACI chart?
A. You are accountable for the result.
B. You should be engaged to provide required inputs.
C. You should be kept up to date on the status.
D. You are responsible for the activity’s execution.
D. You are responsible for the activity’s execution.
Which is a good practice for the use of collaboration Technology?
A. Select tools with the best features.
B. Select tools that the team lead has experience using.
C. Define team goals and practices before selecting tools.
D. Use the tools that the previous project used.
Define team goals and practices before selecting tools.
Which of the following is not a stakeholder in a financial project?
A. Someone opposed to the project
B. Project manager
C. Someone who is not interested in the project
D. Project sponsor
Someone who is not interested in the project
Which of the following is an artifact that outlines how the team will operate and work together?
A. Team charter
B. Resource management plan
C. Project charter
D. Team acquisition plan
Team charter
Which of the following would be least likely to be included in a stakeholder engagement plan?
A. List of identified project stakeholders
B. Documentation of the relationships between project stakeholders
C. Amount of money invested by the project stakeholders
D. Actions to be used interacting with project stakeholders
C. Amount of money invested by the project stakeholders
Your company has entered into a contract to develop a new and improved website for another company. The contract specifies the major deliverables, with details about what the website will contain, the completion date, and budget. The appendix contains the change control procedures that will be used. What project life cycle should be used to deliver this project?
A. Predictive
B. Agile
C. Hybrid
D. Scrum
An organization is exploring a new project with many unknowns, and most of the work to be done is designing software to build the best solution in collaboration with the customer. Which project management approach is best suited for this project?
A. Agile
B. Plan-Driven
C. Phased
D. Predictive
A. Agile
The business determines that the project you are managing must be based on a plan-driven project management approach. This is partially due to the SMART objectives the steering committee has set for the project. In the acronym SMART, what does the T stand for?
A. Technical
B. Tentative
C. Timely
D. Testable
C. Timely
A meeting that is held at frequent intervals in an agile project is referred to as which of the following?
A. Lessons learning meeting
B. End-of-phase meeting
C. Retrospective meeting
D. Status meeting
C. Retrospective meeting
Every timeboxed iteration in the project has a demo scheduled at the end during the iteration review session. What is the goal of this demo?
A. To groom the iteration backlog
B. To revise the product roadmap
C. To solicit feedback from the product owner and other stakeholders
D. To establish the features to be included in the project backlog
C. To solicit feedback from the product owner and other stakeholders
What is the typical length of a sprint/iteration?
A. 1 Week
B. 2 Weeks
C. 1-4 weeks
D. Up to 12 Weeks
C. 1-4 weeks
In which of the following artifacts will a list of stakeholders who will receive communications about the project appear?
A. Communications requirements analysis
B. Communications management plan
C. Stakeholder register
D. Communications requirements analysis and communications management plan
B. Communications management plan
Which of the following is not a component of the communications management plan?
A. Initiator and receiver of project information
B. Stakeholder register
C. Collection and transfer of institutional knowledge
D. Frequence of each communication
Stakeholder register
After integrating the communications management plan into the overall project plan, what would be the next logical step?
A. Determining whether there will be changes to the proposed technology before the project is over
B. Creating a schedule for the production of each type of communication
C. Creating a description of stakeholder communication requirements
D. Distributing the plan to all the stakeholders
D. Distributing the plan to all the stakeholders
Which of the following is not a benefit of planning for a minimum viable product?
A. Risk reduction
B. Early feedback
C. Early value from the service
D. Project team disbands early
D. Project team disbands early