Exam Part 1 Flashcards
tE = (tO + tM + tP) / 3 is the formula for Three-Point Estimating in which you estimate project duration with very little historical data to go on. In the equation, E represents the Estimate, O the Optimistic duration based on the best-case scenario and M is the Most Likely activity duration given a number of analyzed factors. What does the P represent?
- Pessimistic
- Purposeful
- Pie-in-the-sky
- Prescient
Answer: Pessimistic
Pessimistic is correct. The purpose of three-point estimation in order to determine your best activity duration is to identify the best-case (optimistic), worst-case (pessimistic) and most likely scenarios, and then essentially take the average of them by dividing the three numbers by 3. So if your best-case is 10 hours, your worst-case is 24 hours and your most likely duration is 17 hours, you add 10 + 24 + 17, which equals 51. And then 51 divided by 3 is 17 (and if you use the Excel AVERAGE formula, you’ll find you get the same answer). This method is beneficial if you are basing your activity durations on peoples’ judgments rather than known data. For example, if you know it takes 8 hours from start to finish to stand up a working server, then you don’t need three-point estimation because you already know that activity’s duration for a fact.
Of the four categories of life cycles, which has the goal “Correctness of Solution?”
- Iterative
- Agile
- Predictive
- Incremental
Answer: Iterative
Agile Practice Guide Section 3.1 p.18 Table 3-1. Characteristics of Four Categories of Life Cycles states that the goal of Predictive is Manage Cost, the goal of incremental is speed, the goal of iterative is correctness of solution and the goal of agile is customer value via frequent deliveries and feedback.
Your project sponsor asks why you’ve included a 15% contingency in your cost estimate. In which subsidiary plan would he have seen this?
- Cost Management Plan
- Project Charter
- Risk Management Plan
- Requirements Traceability Matrix
Answer: Cost Management Plan
Overall explanation
The Cost Management Plan contains cost estimates, which generally includes consideration of risk response planning, such as contingency plans. A Risk Management Plan would have defined the risk and even the mitigation strategy, but it would not have explicitly defined an associated contingency cost. The Requirements Traceability Matrix documents business requirements, while the project charter, completed in the Initiating phase, will generally not do much more with costs than provide a very high-level dollar amount, if any at all.
Electric Light Bulbery has just entered into a contract with Brite Lite Chandeliers and Lamps to supply them with 5,000 specially made conical light bulbs per week for twelve weeks, totalling 60,000 light bulbs, for $350,000. However, if Electric Light Bulbery can deliver all 60,000 bulbs in only 10 weeks, they’ll get a $20,000 bonus and whatever it might cost to do so is on them. What type of contract did these two companies sign?
- Cost plus incentive fee (CPIF)
- Fixed price incentive fee (FPIF)
- Firm fixed price (FFP)
- Fixed price with economic price adjustments (FPEPA)
Answer: Fixed price incentive fee (FPIF)
Overall explanation
Electric Light Bulbery has a fixed price contract, in that they’ll be paid a certain amount for delivering all the light bulbs within the specific timeframe, but they’ll be rewarded if they can deliver the entire amount two weeks early. This is a fixed price ($350,000) with an incentive fee ($20,000). A firm fixed price would not have included the bonus (incentive). There is no mention of any economic price adjustments, so it’s not an FPEPA and the only reason the contract is not a CPIF is because Electric Light Bulbery has set a fixed price regardless of cost. If meeting the shorter 10-week timeframe costs them additional funds, that’s not something they’re going to get reimbursed for in this particular scenario.
The defintion of project management is the application of knowledge, skills, tools, and techniques to project activities to meet the what?
- Deadlines set forth by the Board of Directors
- Project requirements
- Sponsors’ and stakeholders’ expectations
- Step by step outline of project management process found in the PMBOK
Answer: Project requirements
Overall explanation
Though expectations and deadlines are important to a project manager, first and foremost their duty is to meet project requirements, in whatever form those requirements take.
When you think about how best to tailor project integration management to your project’s needs, which of the following items is NOT a question you will want to ask?
- What is an appopriate project life cycle?
- What are the project status reporting requirements?
- What is the change management process going to be on this project?
- How important is quality management going to be on this project?
Answer: How important is quality management going to be on this project?
Overall explanation
Even if your project is very small, or delivering something seemingly simple, there are still going to be acceptance criteria that will have to be met. The question is not about the importance, as quality management is always important. Responses B, C and D are good examples of questions that you can ask yourself and the team in order to help tailor the management of a project to more realistic parameters for the depth and breadth of each individual project. Other questions you can ask include how you’re going to manage knowledge, which management process will be most effective and how best can you collect lessons learned.
Which of the following is NOT part of the PMI Talent Triangle?
1.Strategic and Business Management
2. Leadership
3. Continuing Education
4. Technical Project Management
Answer: Continuing Education
Overall explanation
While continuing education is indeed one of the ways a project manager can increase his or her knowledge and/or effectiveness in any of the three project manager competencies, the competencies themselves are the other three answers shown here. The talent triangle focuses on three key skill sets: 1)Technical project management. The knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management. The technical aspects of performing one’s role. 2)Leadership. The knowledge, skills, and behaviors needed to guide, motivate, and direct a team, to help an organization achieve its business goals. 3)Strategic and business management. The knowledge of and expertise in the industry and organization that enhanced performance and better delivers business outcomes.
The Plan Quality Management process exists within the Planning phase of a project. In the Monitoring & Controlling phase of a project, you Control Quality. What is the missing related process you undertake during the Executing phase of a project?
- Prioritize Quality
- Manage Quality
- Define Quality
- Categorize Quality
Answer: Manage Quality
Overall explanation
Manage Quality is the missing process, and it occurs during the Executing phase of a project, when your job is to manage the quality of whatever it is that’s being executed. The other three options are not PMBOK processes.
What document should be completed before a project is consdidered, in order to assess the viability of continuing with an initiative into the project management processes?
- project charter
- Project Management Plan
- Business Case
- business requirements document
Answer: Business Case
Overall explanation
A Business Case is a documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities it lists the objectives and reasons for project initiation.
How many interpersonal and team skills techniques are there?
- 10
- 17
- 16
- 15
Answer: 17
Overall explanation
There are 17. Active listening, communication styles assessment, conflict management, cultural awareness, decision making, emotional intelligence, facilitation, influencing, leadership, meeting management, motivation, negotiation, networking, nominal group technique, observation/conversation, political awareness and team building.
Joni’s about to attend a meeting in which a very important decision on which part to use for the widget her project team is producing, will be made. She believes from what most of her team’s told her that Part A is the best choice but has no vote as it is a business and manufacturing decision. The project sponsor has agreed that he will abide by whatever the Majority Vote is at today’s meeting. If there are 18 people in attendance including Joni, how many must vote for Part A in order for it to be chosen?
- 10
- 17
- 9
- 18
Answer: 9
Overall explanation
Though there are 18 people at the meeting, one of them is Joni. But Joni is the project manager and as the problem tells us, she does not have a vote in which part is chosen since it’s a business and manufacturing decision. This leaves 17 people eligible to vote. The definition of a Majority Vote is that more than 50% of the members of the group have to vote a certain way for that to be the decision. 50% x 17 = 8.5. So if 9 people vote for Part A, then Part A will be chosen. (Of note: Had Joni also been allowed a vote, then Majority would have had to be 10 or more votes for Part A in order for it to win, as 50% x 18 = 9, and more than 50% automatically takes us to 10 votes.)
Lindsey’s project involves a lot of people who work in shifts, rather than a “9 to 5” day. It’s going to be difficult for her to remember when each of the project team members is available, and how that availability affects their assigned tasks, without something to help manage that. What’s one output of the Acquire Resources process that will provide her with a tool she can use throughout the rest of the project to keep the resources organized?
- Physical Resource Assignments
- Project Team Assignments
- Resource Calendar
- Change Requests
Answer: Resource Calendar
Overall explanation
Of the choices presented, only the Resource Calendar meets Lindsey’s needs. A resource calendar identifies the working days, shifts, start and end of normal business hours, weekends, and public holidays when each specific resource is available. Information on which resources (such as team resource, equipment, and material) are potentially available during a planned activity period is used for estimating resource utilization. Resource calendars also specify when and for how long identified team and physical resources will be available during the project. This information may be at the activity or project level. This includes consideration of attributes such as resource experience and/or skill level, as well as various geographical locations.
Kirstie’s project team is having fun designing a new coffee maker intended to easily mimic the fancy drinks made at major coffee houses around the world. As the team brainstorms what features and functions they want the coffee maker to have, Project Manager Kirstie and assigned Business Analyst Michelle are asking the Subject Matter Experts various questions to help them refine what they want the product to do and how they want it to work. This team is involved in which aspect of Define Scope?
- Decision Making
- Product Analysis
- Expert Judgment
- Data Analysis
Answer: Product Analysis
Overall explanation
While it may take bits and pieces of all four of these categories to make the best coffee maker possible, the clear winner here is Product Analysis because, as the PMBOK 6th Edition shares with us on p. 153: Product analysis can be used to define products and services. It includes asking questions about a product or service and forming answers to describe the use, characteristics, and other relevant aspects of what is going to be delivered. Each application area has one or more generally accepted methods for translating high-level product or service descriptions into meaningful deliverables. Requirements are captured at a high level and decomposed to the level of detail needed to design the final product. Examples of product analysis techniques include but are not limited to: J175Product breakdown, Requirements analysis, Systems analysis, Systems engineering, Value analysis, and Value engineering.
How many potential financial measures that a project needs to meet, could be documented in the business case?
- 20
- 10
- 15
- 5
Answer: 15
Overall explanation
One of the project success criteria is meeting the agreed-upon financial measures documented in the business case. These financial measures may include but are not limited to: Net present value (NPV), Return on investment (ROI), Internal rate of return (IRR), Payback period (PBP), and Benefit-cost ratio (BCR). Meeting business case nonfinancial objectives; Completing movement of an organization from its current state to the desired future state; Fulfilling contract terms and conditions; Meeting organizational strategy, goals, and objectives; Achieving stakeholder satisfaction; Acceptable customer/end-user adoption; Integration of deliverables into the organization’s operating environment; Achieving agreed-upon quality of delivery; Meeting governance criteria; and Achieving other agreed-upon success measures or criteria (e.g., process throughput).
How many personality characteristic does the PMBOK indicate an effective project needs to have some level of ability within, in order to be successful?
- 8
- 11
- 10
- 15
Answer: 11
Overall explanation
The correct answer is 11. Personality refers to the individual differences in characteristic patterns of thinking, feeling, and behaving. Personality characteristics or traits include but are not limited to: Authentic (e.g., accepts others for what and who they are, show open concern); Courteous (e.g., ability to apply appropriate behavior and etiquette); Creative (e.g., ability to think abstractly, to see things differently, to innovate); Cultural (e.g., measure of sensitivity to other cultures including values, norms, and beliefs); Emotional (e.g., ability to perceive emotions and the information they present and to manage them; measure of interpersonal skills); Intellectual (e.g., measure of human intelligence over multiple aptitudes); Managerial (e.g., measure of management practice and potential); Political (e.g., measure of political intelligence and making things happen); Service-oriented (e.g., evidence of willingness to serve other people); Social (e.g., ability to understand and manage people); and Systemic (e.g., drive to understand and build systems). An effective project manager will have some level of ability with each of these characteristics in order to be successful. Each project, organization, and situation requires that the project manager emphasize different aspects of personality.
A few of the managers who were identified as Interested Stakeholders, have come to Lily, the project manager for a project to revamp a company’s Marketing website, and asked her to give them an updated project budget. Lily tells them it will take a little time, as she’ll have to evaluate the relationship between the consumption of project funds and the work being accomplished by those expenditures. The managers protest that she doesn’t need to do all that to control project costs; that all she needs to do is tell them how much of the budget has been spent. Lily stands her ground, arguing that only by monitoring work completed vs. money spent can she give them an accurate picture of where things stand. Which Project Cost Management process is Lily pulling these principles from?
- Plan Cost Management
- Determine Budget
- Estimate Costs
- Control Costs
Answer: Control Costs
Overall explanation
Updating the budget requires knowledge of the actual costs spent to date. Any increase to the authorized budget can only be approved through the Perform Integrated Change Control process. Monitoring the expenditure of funds without regard to the value of work being accomplished for such expenditures has little value to the project, other than to track the outflow of funds. Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control is the management of the approved cost baseline
The “Develop the project management plan” process achieves which of these goals?
- It formally sets in stone an entire set of detailed business requirements, technical requirements and vendor requirements.
- Copying and pasting what’s in the charter (output of Initiating) into a Planning phase document.
- Defines, prepares and coordinates all subsidiary plans and integrates them into a comprehensive plan.
- Defines an iterative and agile approach to the project to promote engagement of team members.
Answer: Defines, prepares and coordinates all subsidiary plans and integrates them into a comprehensive plan.
Overall explanation
The Project Management Plan integrates - sometimes at a high level - the components of the other plans developed during the Planning phase. From the Risk Management Plan to the Project Schedule to the Quality Management Plan and the project budget, the Project Management Plan becomes the “one-stop shop” outlining how the project will proceed to meet the its objectives. It doesn’t contain details down to the nth degree; it contains enough information to be the roadmap, and the subsidiary documents contain further detail for those times when it’s required.
What are the two deliverables expected to be completed by the end of the Initiating phase of a project?
- Business Requirements Document and Project Charter
- Risk Management Plan and Procurement Plan
- Stakeholder Registesr and Communication Plan
- Stakeholder Register and Project Charter
Answer: Stakeholder Register and Project Charter
Overall explanation
When you’re initiating a project, you are making identifications and gathering data at a high level in order to obtain approval to proceed to the Planning phase. All of the other documents listed within the multiple choice answers besides Stakeholder Register and Project Charter, are deliverables developed during the Planning phase.
Which of the following is not considered a decision-making technique when performing integrated change control?
- Voting
- Autocratic Decision-Making
- Multicriteria Decision Analysis
- Influencing Outcomes
Answer: Influencing Outcomes
Overall explanation
Influencing outcomes is not a decision-making technique. Rather, it’s a technique that anyone can use in an attempt to influence the outcome of a decision being made using one of the other three techniques listed here.
What is the Closing process used to close out?
- One project phase
- All of these
- The whole project
- Contract
Answer: All of these
Overall explanation
The closing process group consists of the processes performed to formally complete or close a project, phase, or contract. This process group verifies that the defined processes are completed within all of the Process Groups to close the project or phase, as appropriate, and formally establishes that the project or project phase is complete.