Exam Part 2 Flashcards
Which type of Project Management Office provides a consultative role to projects by supplying templates, best practices, training, access to information, and lessons learned from other projects?
- External Consultant
- Supportive
- Controlling
- Directive
Answer: Supportive
Overall explanation
Supportive PMOs provide a consultative role to projects by supplying templates, best practices, training, access to information, and lessons learned from other projects. This type of PMO serves as a project repository. The degree of control provided by the PMO is low. In contrast, Controlling PMOs provide support and require compliance through various means. The degree of control provided by the PMO is moderate. Compliance may include (Adoption of project management frameworks or methodologies, use of specific templates, forms, and tools, conformance to governance frameworks). And finally, Directive PMOs take control of the projects by directly managing the projects. Project managers are assigned by and report to the PMO. The degree of control provided by the PMO is high. Whether or not the PMI is an external consultant is irrelevant to this question.
One of the two major influences on projects is known as EEFs. What does “EEF” stand for?
- Evaluation Elemental Factors
- Enterprise Estimation Field
- Empirical Evaluation Failures
- Enterprise Environmental Factors
Answer: Enterprise Environmental Factors
Overall explanation
The correct answer is Enterprise Environmental Factors. EEFs originate from the environment outside of the project and often outside of the enterprise, and may have an impact at the organizational, portfolio, program, or project level.
The Communication Model for Cross-Cultural Communication begins with the Sender being the one to Encode a message. He or she then transmits it, and it is received by the Receiver and decoded. The Receiver then returns some form of acknowledgement to the sender confirming receipt. But what is the thing called which can and does disrupt both the sender transmitting their message and the receiver transmitting their feedback.
- Culture
- Feedback Message
- Noise
- Not having a Communication Plan
Answer: Noise
Overall explanation
In and of itself, not having a communication plan will not be a contributing factor in disrupting the communication between a sender and a receiver. A cultural difference may cause - but is not in and of itself the thing disrupting) the correct answer, which is Noise. And finally, the Feedback Message - if any is provided by the Receiver - can also be disrupted by Noise. Noise can be anything from personal biases, to cultural differences to actual noise such as loud music or language barriers inhibiting clarity.
Which of the following is not considered a data gathering technique for developing a project charter?
- Responsibility Assignment Matrix
- Interviews
- Focus Groups
- Brainstorming
Answer: Responsibility Assignment Matrix
Overall explanation
While the Responsibility Assignment Matrix, or RAM, may help you identify who is responsible for helping with various parts of the charter, the three main techniques for gathering data to put into a project charter are conducting focus groups, interviews or brainstorming sessions with Subject Matter Experts (SMEs).
It’s time for Emma to do her weekly status report again. It’s a very important tool she’s found is effective at letting all of her stakeholders know where things stand at the end of each week, regardless of what level of engagement the stakeholder is at. What input to “Manage Communications” is this status report an example of?
- Project Management Plan
- EEFs and OPAs
- Project Documents
- Work Performance Reports
Answer: Work Performance Reports
Overall explanation
Work Performance Reports -Reports are circulated to the project stakeholders through this process -Can include status and progress reports -Work performance reports can contain earned value graphs and information, trend lines and forecasts, defect histograms, contract performance information, and risk summaries -They can be presented as dashboards, heat reports, stop light charts, or other representations useful for creating awareness and generating decisions and actions
How many data representation techniques are there?
- 8
- 10
- 15
- 5
Answer: 15
Overall explanation
There are 15. Affinity diagrams, cause-and-effect diagrams, control charts, flowcharts, hierarchical charts, histograms, logical data model, matrix diagrams, matrix-based charts, mind mapping, probability and impact matrix, scatter diagrams, stakeholder engagement assessment matrix, stakeholder mapping/representation and text-oriented formats.
There’s a set of technical guidelines known as DfX (Design for X) which can be used to manage quality. Using the DfX that’s decided upon within your project may result in cost reduction, quality improvement, better performance, and what?
- Customer Satisfaction
- Improved Engagement
- Better Communication
- Shortened Project Schedule
Answer: Customer Satisfaction
Overall explanation
Design for X (DfX) is a set of technical guidelines that may be applied during the design of a product for the optimization of a specific aspect of the design. DfX can control or even improve the product’s final characteristics. The X in DfX can be different aspects of product development, such as reliability, deployment, assembly, manufacturing, cost, service, usability, safety, and quality. Using the DfX may result in cost reduction, quality improvement, better performance, and customer satisfaction. The other three choices here have nothing to do with product design.
Which of the following measures is considered the most critical EVA (Earned Value Analysis) metric and measures the cost efficiency for the work completed?
- CPI (Cost Performance Index)
- AC (Actual Cost)
- VAC (Variance at Completion)
- CV (Cost Variance)
Answer: CPI (Cost Performance Index)
Overall explanation
The cost performance index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost. It is considered the most critical EVA metric and measures the cost efficiency for the work completed. Equation: CPI = EV (Earned Value)/AC (Actual Cost).
How do you manage a project’s core objectives during the Executing phase?
- Managing Budget
- Managing Quality
- Managing Expectations
- Managing Time
Answer: Managing Quality
Overall explanation
Thougth managing expectations, the budget and time are all important qualities of an effective Project Manager, a project’s core objectives are specifically managed by ensuring what’s being produced during the Executing phase is of acceptable quality. Specifically, Quality Management is the process of translating the Quality Management Plan into executable quality activities that incorporate the organization’s quality policies into the project.
Which project roles are responsible for identifying both individual and overall project risks?
- All project roles
- Project Manager
- Business Analyst
- Project Sponsor
Answer: All project roles
Overall explanation
The Project Management Book of Knowledge (PMBOK) makes it clear that “all project stakeholders should be encouraged to identify individual project risks. It is particularly important to involve the project team so they can develop and maintain a sense of ownership and responsibility for identified individual project risks, the level of overall project risk, and associated risk response actions.”
Fill in the blank: A portfolio is a collection of projects, programs, subsidiary portfolios, and ____________ managed as a group to achieve strategic objectives.
- Requirements
- Operations
- Budgets
- Resources
Answer: Operations
Overall explanation
This defintion of a portfolio comes straight from the Project Management Book of Knowledge. It is Operations which rounds out that definition, as Operations within the context of organizational structure support a company’s strategic objectives at the same level as projects do…the hierarchy is: Strategic Objectives –> Portfolio –> Programs –> Projects & Operations –> Shared Resources and Stakeholders.
There are three types of project management charts to help display schedules and timelines in more visual ways. If you have a stakeholder who only wants to see the start and end dates of major milestones, which type of chart is best-suited to her needs?
- Project Schedule Network Diagrams
- Milestone Charts
- Pivot Tables
- Bar Charts (aka Gantt Charts)
Answer: Milestone Charts
Overall explanation
A Bar Chart is a graphical display of project elements, dates and durations, typically used by project teams. A Milestone Chart is a graphical display of significant events in the project, usually completion of major deliverables. This type of display is often used for Executive Management. Project Schedule Network Diagrams are a graphical way to view tasks, dependencies, and the critical path of a project. These often resemble Visio diagrams (flowcharts) and provide a clear “sequence of events” that has to take place from now through project completion. Pivot Tables are an Excel feature that hasn’t much to do with displaying a project schedule. A Milestone Chart will give your stakeholder what she’s looking for.
If you work in a hospital’s Information Technology department, and you are in charge of managing only network and server changes because you’re IT, while the neuroscience managers are responsible for implementing a remote stroke assessment network, the billing department manager is responsible for implementing new billing codes hospital-wide and the Facilities manager is responsible for the project to modernize all hospital elevators, what structural type of organization is your employer?
- Weak matrix organization
- Balanced matrix organization
- Projectized organization
- Functional organization
Answer: Functional organization
Overall explanation
Each department in a functional organization will do its project work independently of other departments. That’s not to say that other departments don’t get called upon for tasks, such as the neuroscience manager requiring IT to open up network ports or firewalls for their software to work, but the actual project management happens within each functional silo rather than from a centralized Project Management Office.
During which project phase does Monitoring and Controlling project work really ramp up?
- Planning
- Closing
- Initiating
- Executing
Answer: Executing
Overall explanation
Monitoring and Controlling project work ramps up once the project is in execution.
Directing and Managing Project Work and Managing Project Knowledge are the two components of which part of which of the following:
- Core Objectives Management
- Facilitation Management
- Executing Process
- Project Integration Management
Answer: Project Integration Management
Overall explanation
Directing and managing project work is he process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the projects objectives. Managing project knowledge is the process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning. These two components define Project Integration Management.
An input to identifying project stakeholders is:
- Project Management Plan
- Statement of Work (SOW)
- Business Case
- Enterprise Environmental Factors (EEF)
Answer: Enterprise Environmental Factors (EEF)
Overall explanation
The only one of these four that is a true input to the Stakeholder Register is the EEF. Both the Business Case and SOW are prequisites to the project Initiating phase, and the Project Management Plan is a deliverable that comes out of the next phase, Planning.
Which of the following areas are least likely to fall under the Initiating process group?
- Obtaining approval to proceed to the next phase of the project
- Engaging project stakeholders
- Developing a business case that can be used to inform the creation of a project charter.
- Understanding a project’s purpose and objectives
Answer: Developing a business case that can be used to inform the creation of a project charter.
Overall explanation
A project manager must engage stakeholders to obtain the information necessary to complete a stakeholder register. The project manager must also understand a project’s purpose and objectives well enough to articulate them in a project charter, and may be the person engaging decision-makers after the charter’s written, in order to obtain approval to proceed. The development of a business case does not happen within the project management life cycle at all, but is a pre-cursor to something becoming a project, and thus while a project manager may have involvement at that stage, it occurs before the Initiating process begins.
There are four generic phases of a project life cycle and though not all five of the process groups match those four phases exactly, the Closing process group - while also being able to apply to individual project phases - most closely aligns itself to which generic project phase?
- Carrying out the work
- Starting the project
- Organizing and Preparing
- Ending the project
Answer: Ending the project
Overall explanation
Ending the project is where you will be able to apply all of the Closing process groups though you can also use some of them if you are closing out contracts or project phases independent of the full and complete end of a project.
A project charter is not considered to be a ___________ because there is no consideration or money promised or exchanged in its creation.
- Project Output
- Contract
- Project Artifact
- Deliverable
Answer: Contract
Overall explanation
An approved project charter formally initiates a project, but contractual agreements are handled separately, often with the Procurement Management arena.
Elena’s project to implement a new cost accounting system within a sub-division of her company’s Finance department has to be implemented three months before the end of the organization’s fiscal year so the old system can be decommissioned prior to the new system taking on all the information required for year-end reporting. Which of the four PDM logical relationships exists between the old cost accounting system and the new one Elena’s implementing?
- Finish-to-start (FS)
- Start-to-start (SS)
- Start-to-finish (SF)
- Finish-to-finish (FF)
Answer: Start-to-finish (SF)
Overall explanation
The correct answer is Start-to-finish (SF). PDM includes four types of dependencies or logical relationships. A predecessor activity is an activity that logically comes before a dependent activity in a schedule. A successor activity is a dependent activity that logically comes after another activity in a schedule. -Finish-to-start (FS). A logical relationship in which a successor activity cannot start until a predecessor activity has finished. -Finish-to-finish (FF). A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. -Start-to-start (SS). A logical relationship in which a successor activity cannot start until a predecessor activity has started. -Start-to-finish (SF). A logical relationship in which a successor activity cannot finish until a predecessor activity has started.