PMP Practice test 2: PMP Practice Test Three Flashcards
Ray is a project manager in his organization and he’s leading a Scrum-based project. In this project, Ray needs to define with the project team how long each project iteration should take. What term best describes the duration of an iteration in a Scrum project?
I. iteration
2. Increment
3. Timeboxed period
4. Rolling wave planning
Answer: Timeboxed period
Explanation
When using an adaptive life cycle, the time-boxed periods for releases, waves, and iterations are specified. Time-boxed periods are durations during which the team works steadily toward completion of a goal. Time-boxing helps to minimize scope creep as it forces the teams to process essential features first, then other features when time permits.
As a project manager, you need several different skills to be effective. One skill is communication. According to some research cited in the PMBOK Guide, sixth edition, project managers spend how much of their time communicating?
- 80%
- 50%
- 90%
- 20%
Answer: 90%
Explanation
Project managers spend about 90 percent of their time communicating. Communication management is covered in detail in Chapter 10 in the PMBOK Guide and is closely related to Project Stakeholder Engagement.
June is a project manager in her organization and she’s working with the project sponsor and the immediate project team to identify the project stakeholders. The process of stakeholder identification is best described as first happening when?
- Prior to or during the project charter development and approval
- When the project planning begins by the project sponsor
- At the start of each project phase as directed by the PMBOK guide
- At the start of project execution but before the WBS creation
Answer: Prior to or during the project charter development and approval
Explanation
Stakeholder identification occurs for the first time in a project either prior to or at the same time the project charter is developed and approved. It is repeated as necessary, but should be performed at the start of each phase and when a significant change in the project or the organization occurs. Each time the identification process is repeated, the project management plan components and project documents should be consulted to identify relevant project stakeholders.
Harold is the project manager of the JKL Project for his organization and he’s meeting with the project team to identify some project risks in the next phase of the project. During the meeting, he notices that Char and Holly won’t look at each other and their body language tells Harold, and the rest of the project team members, that there is some hostility between these two individuals. Throughout the meeting, Harold observes that these two individuals won’t speak to each other and it’s causing some disruption in the conference. What component of the communication model is happening and will present a challenge for Harold to overcome?
- Anger
- Emotional intelligence
- Barrier
- Blockage
Answer: Barrier
Explanation
The only term listed that is part of the communication model is the barrier. A barrier is when two parties won’t communicate due to something blocking the flow of communication. In this instance, there appears to be some disagreement between Char and Holly, but a barrier could also be things like technology failure or different languages spoken between the parties.
Joan is the project manager of the NKQ Project, and she is trying to get the project sponsor to decide some of the project work. Joan wants the project sponsor to make a decision, but the project sponsor is encouraging Joan and the project team to make the decision. Joan suspects that the project sponsor is putting the decision on her because if the decision is wrong, it will be her fault. Beth, a project team member, says that project sponsor always wants the team to make decisions. What leadership style is happening in this scenario?
- Transactional
- Servant leadership
- Laissez-faire
- Charismatic
Answer: Laissez-faire
Explanation
Laissez-faire means the project sponsor or project manager is allowing the team to make decisions and establish their personal goals, also referred to as taking a hands-off style. Transactional is more about the focus on goals, feedback, and accomplishment to determine rewards; management by exception. Servant leadership is often in agile projects and demonstrates a commitment to serve and put other people first; focuses on other people’s growth, learning, development, autonomy, and well-being; concentrates on relationships, community, and collaboration; leadership is secondary and emerges after service. Charismatic is the ability to inspire; is high-energy, enthusiastic, self-confident; holds strong convictions.
You are working with the project team to determine the cost of an activity in the project. The project team has provided a pessimistic, optimistic, and most likely estimate of costs for the activity. What type of estimate are you likely creating with the project team in this scenario?
- Monte Carlo
- Beta
- Averaged
- Constant
Answer: Beta
Explanation
The only answer that’s applicable is the beta estimate, which is also known as PERT. Beta uses the formula of (O+(4ML)+P)/6 to create a prediction of costs. Note that triangular is the three-point estimate that generates an average of costs, but it is not called Averaged.
In project integration management the process to close the project or phase creates four outputs. Which one of the following is not one of the four outputs of closing the project or phase?
- Final report
- Final project team assessment
- Final product
- Project documents updates
Answer: Final project team assessment
Explanation
The close project or phase process does not create the final project team assessment. The four items are the product documents updates, the final product, service, or result transition, final report, and the organizational process assets updates.
As a project manager, you should recognize the communication model not only for your exam but also to be a more effective project manager. Which one of the following is the correct ordering of a message through the communications model?
- Sender, Transmitter, Medium, Receiver, Decoder, Acknowledgement
- Sender, Encoder, Transmitter, Decoder, Receiver
- Sender, Encoder, Medium, Decoder, Receiver, Acknowledgement
- Encoder, Decoder, Acknowledgement
Answer; Sender, Encoder, Medium, Decoder, Receiver, Acknowledgement
Explanation
The communications model is Sender, Encoder, Medium, Decoder, Receiver, and Acknowledgement.
A project manager is running late on his project implementation and he has decided to add 15 workers to some effort-driven activities. This addition of workers will reduce the duration of the work but will drive costs. What term best describes this addition of labor to the effort-driven activities?
- Crashing
- Slack
- Compounding
- Float
Answer: Crashing
Explanation
Crashing adds labor to effort-driven activities but increases the overall costs of the project for the additional labor.
Beth is a project manager in her organization, and she is working with her project team to create the project management plan for her project. The purpose of the project management plan is best described as which one of the following choices?
1, Define when the work will be completed and how much the work will cost
2. Define all processes the project team must utilize
3. Define how the project will achieve its objectives
4. Manage phase transitions within the project timeline
Answer: Define how the project will achieve its objectives
Explanation
The best answer is that the project management plan defines how the project will achieve its objectives. The project plan defines all processes that the project, not just the project team, will utilize and to what depth each selected process will be implemented. The project plan can also address how phase transitions will be managed, but this is not the best choice for achieving the project objectives. The project plan also addresses more than just the timeline and project costs.
As a project manager participating in the PMI certification program, you should be familiar with the PMI Talent Triangle and its components. Which one of the following is not part of the PMI Talent Triangle?
- Quality management
- Leadership
- Technical project management
- Strategic and business management
Answer: Quality management
Explanation
Quality management is not part of the PMI Talent Triangle. The three components are Technical Project Management, Leadership, and Strategic and Business Management.
You are a project manager for your organization and management has asked you to present a chart that will show the planned project performance on one axis and the actual project performance on a second axis to see the correlation of what was expected and what was experienced. What type of quality management chart is being requested?
- Pareto chart
- Scatter diagram
- Fishbone chart
- Histogram
Answer: Scatter diagram
Explanation
Scatter diagrams can show the planned performance on one axis and the actual performance on the second axis.
Consider an activity that is not on the critical path that has four days of float available. The duration of the activity is four days. What’s the total amount of time this activity can take without affecting the project completion date?
- Four days
- Eight days
- Four days plus four days of slack time
- Seven days
Answer: Eight days
Explanation
The correct answer is simply eight days as the task will take four days to complete, and there are four days of float for a total of eight possible days of duration.
Victor is the project sponsor of the HK Project and he has cautioned Mary of overworking the project team to meet deadlines in the project. Mary is eager to meet the deadlines and feels that the time should work a little extra throughout the project to deliver as promised. What’s one of the key drawbacks of overworking the project team?
- Duration estimates will be bloated to reduce actual work hours
- The project will likely experience rework
- Mary will need improved communication and emotional intelligence
- The team will enjoy bonuses, but wont enjoy the project work
Answer: The project will likely experience rework
Explanation
Meeting customer requirements by overworking the project team may result in decreased profits and increased levels of overall project risks, employee attrition, errors, or rework.
Projects are often complex and require analytical skills by the project manager and the project team. There are three specific dimensions to the complexity of project management. Which one of the following is not one of the three dimensions of complexity?
- Team behavior
- Human behavior
- Ambiguity
- System behavior
Answer: Team behavior
Explanation
Team behavior is not one of the three dimensions of complexity. Complexity within projects is a result of the organization’s system behavior, human behavior, and the uncertainty at work in the organization or its environment. In Navigating Complexity: A Practice Guide, these three dimensions of complexity are defined as System behavior: the interdependencies of components and systems. Human behavior: the interplay between diverse individuals and groups. Ambiguity: uncertainty of emerging issues and lack of understanding or confusion.