PMP Practice Test 4: PMP Practice Test Four Flashcards
Mary is the project manager for her organization and she’s been assigned a new project. Management has asked Mary to create a reliable project budget as soon as possible and Mary states she’ll need to create a definitive estimate and this will take some time. In order to create the definitive estimate for a project, what document must first be created? Choose the best answer:
- Work breakdown structure
- Product scope
- Project scope
- Project charter
Anwer: Work breakdown structure
Explanation
A definitive estimate for project costs is the most reliable estimate type, but it does require a WBS. The WBS will take time to create, so too then will the definitive estimate. The other choices don’t provide enough information to create a reliable estimate type for management.
You are the project manager of the JKL Project for your organization and you’re meeting with the project team. It’s come to your attention that the project team has padded every activity duration in the project schedule by 10-12 hours. You explain to the team that this padding isn’t acceptable and they need to identify accurate duration estimates to predict the duration of the project. What law describes the danger of padding activity duration estimates?
- Law of Diminishing Returns
- Parkinsons Law
- Moore’s Law
- Little’s Law
Answer: Parkinsons Law
Explanation
Parkinson’s Law states that work expands to fill the time allotted to it. So, if the project team says an activity will take 50 hours, even with the padding, the task will take 50 hours. Little’s Law describes the duration and length of a queue in relation to how long the queue is. Moore’s Law describes the speed of processors, which is somewhat dated now. The Law of Diminishing Returns says that you cannot continue to add labor to reduce the duration of an activity with affecting the yield of the activity and the effectiveness of the laborers added to the activity.
Consider a project to create new accounting software for an organization. In the project the team has skipped some required software testing to meet a deadline, but this has allowed several escaped defects which have now caused problems in production. What term best describes this scenario?
- Escaped defect resolution
- Poor project management
- Cost of nonconformance to quality
- Poor change control
Answer: Cost of nonconformance to quality
Explanation
The cost of nonconformance to quality are the costs that are introduced to an organization when quality control, quality assurance measures, and guidelines are not followed. By the team skipping the testing portion of the software development lifecycle they have allowed errors to be introduced to production, which can be a costly mistake. The cost of nonconformance to quality, sometimes just called poor quality, can also be costs such as loss of sales, loss of reputation, and frustration by the stakeholders.
You are the project manager for the GHB Project and you’re working with the project team to create the project schedule. Jeff, a project team member, has identified two tasks that don’t need to happen sequentially, but could happen at the same time if one task starts a day before the second task. What type of relationship could you apply to these to two tasks?
- SS
- FS
- SF
- Lead, one day
Answer: SS
Explanation
The best choice is SS, a start-to-start activity. This would allow both activities to start at the same time essentially, you could then add +1 day of lag to the second activity to shift its start day by one day. Note that lead time, one day, isn’t a valid relationship and wouldn’t be the best choice as the answer doesn’t address which task has the lead day. In addition, lead is negative time, so this would be a cumbersome scheduling approach.
Hans is the project manager for his organization and management has asked him to help choose a project. Project A is worth $450,000 and will take 18 months to complete. Project B is worth $560,000 but will take two years to complete. A third project is worth $301,000 and will take 25 months to complete. If Hans recommends Project A what is the opportunity cost in this scenario?
- $861,000
- $450,000
- $560,000
- $301,000
Answer: $861,000
Explanation
The opportunity cost is the total amount of the other projects that the organization chooses to not do in favor of Project A. In this scenario, it’s the total of Project B and Project C; this would be $560,000 and $301,000.
You are the project manager of Project GHJ, and you’re working with Jack as he manages the budget for your project. In your organization, the project team reports to Jack. Which of the following options can best describe the amount of authority you have in this organizational structure?
- Total
- High
- Low
- Moderate
Answer: Low
Explanation
When the project budget is managed by the functional manager and the team reports to the functional manager you’re likely operating in a functional, multi-divisional or weak matrix structure. The project manager’s authority in these organizational structures varies from low to little or none.
As a project manager you need to identify assumptions, constraints, risks, and other facets of the project you’re managing. Which one of the following is not an example of a constraint?
- A project requirement to use Microsoft Office
- A project deadline of December 12
- A project schedule based on predictable weather
- A project budget of $250,000
Answer: A project schedule based on predictable weather
Explanation
A constraint is anything that limits your options. An assumption is anything that you believe to be true, but can’t, or have not, proven it to be true. While you may schedule your project for good weather, such as in a construction project, you can’t always predict the weather. Weather is an assumption. The other options are constraints.
You are the project manager of the NJK Project, and your project sponsor has asked you to create a flowchart to show how vendors and customers may interact in your project. What specific type of diagram is your project sponsor asking you to create?
- SIPOC
- HUSTL
- PESTLE
- GERT
Answer: SIPOC
Explanation
The project sponsor is asking for a SIPOC flowchart. SIPOC shows the interactions between customers and vendors using the acronym Suppliers, Inputs, Processes, Outputs, and Customers.
John is the project manager of JHG Project and he’s working with his project team. Karen, a senior developer on the team, is explaining to the team how the software your project is developing will work. It’s a sophisticated piece of software, so Karen is using analogies and drawing diagrams on the whiteboard to coach the team. What type of knowledge is Karen utilizing in this scenario?
- Direct
- Explicit
- Tacit
- Encumbered
Answer: Tacit
Explanation
Karen is utilizing tacit knowledge. Tacit knowledge is more difficult to share, requires analogies, drawings, and more time to absorb. Explicit knowledge, the only other knowledge type you’ll need to know for your exam, is more direct and easily expressed.
You are the project manager for the RGR Project and you’ve worked with the project team to create the WBS. Many of the components of the WBS in your project are identical, such as the television screens that will be installed throughout the complex. You need a method to identify each component and work package to track the requirements through the project and to help with planning the project work. Which one of the following is the best answer for identifying and tracking these items throughout the project?
- WBS dictionary
- Requirements tracking matrix
- Code of accounts
- WBS
Answer: Code of accounts
Explanation
The best answer is the code of accounts, which is a numbering system to identify each element of the WBS in a sequential pattern, such as 10.9.3 and then lower components could be numbered as 10.9.3.1, 10.9.3.2, and so on. The PMBOK Guide uses a numbering sequence like this to identify each heading in the guide. Note that the requirements tracking matrix is not a valid term, but a requirements traceability matrix is and would be a correct answer if that choice were present.
Gary is the project manager of the JKP Project, and he believes in McClelland’s Theory of Needs. As part of his belief, he has the project team complete a thematic apperception test. All of the following are part of this theory except for which one?
- Need for power
- Need for achievement
- Need for affiliation
- Need for ambition
Answer: Need for ambition
Explanation
The need for ambition is not part of the McClelland’s Theory of Needs, sometimes called the Three Needs Theory. The need for achievement, affiliation, and power are the three needs of this theory.
Jen is the project manager of an adaptive project in her organization. She wants to create a chart that will show how much work is remaining in the product backlog. What chart should Jen create?
- Forecast chart
- Scrum chart
- Iteration burndown chart
- Agile chart
Answer: Iteration burndown chart
Explanation
This chart tracks the work that remains to be completed in the iteration backlog. It is used to analyze the variance with respect to an ideal burndown based on the work committed from iteration planning (see PMBOK Guide, section 6.4.2.8). A forecast trend line can be used to predict the likely variance at iteration completion and take appropriate actions during the course of the iteration. A diagonal line representing the ideal burndown and daily actual remaining work is then plotted. A trend line is then calculated to forecast completion based on remaining work.
Ernesto is the project manager of a new project his company has just launched. The project sponsor, Julieanne, has asked Ernesto to create a quick estimate of the project should cost. Ernesto’s current project is similar, but larger in scope, to a project he recently finished. The older project cost $250,000, so he estimates the new project will cost $275,000. What type of estimate has Ernesto created?
- Direct
- Analogous
- Parametric
- Comparable
Answer: Analogous
Explanation
Ernesto has created an analogous estimate. Analogous estimates are based on similar projects to predict the cost of the current project. Analogous estimates are analogies between similar projects and while not always reliable, they are quick and based on proven project information. Note that analogous estimates should have a range of variance, such as +/- 10 percent based on the size of the project, the differences between the projects, and other factors.
You are the ScrumMaster of a large software development project. Your manager has asked that you take a moment and create a chart to show the causal factors and effect of a bottleneck your project is experiencing. You gather the project team to create this chart and do root cause analysis. What type of chart are you creating in this project?
- Pareto
- Risk burndown
- Five-Whys Charts
- Ishikawa
Answer: Ishikawa
Explanation
You are creating an Ishikawa chart. An Ishikawa chart is the same as a fishbone or cause-and-effect chart and helps to facilitate root cause analysis. Note that there is not a Five-Whys chart, this is a fictional term.
You are the project manager for a marketing project to mail out 1,000,000 postcards to prospective customers. Rather than mail out all 1,000,000 postcards at once, you and the team design three cards of different designs that you’ll mail in batches of 100,000. Whichever card gets the best response will be the selected card for the balance of the 1,000,000. What quality tool are you using in this scenario?
- Design of experiments
- Rule of seven
- Quality assurance
- Design for X
Answer: Design of experiments
Explanation
This is the design of experiments, which means you’ll do experiments on a smaller pool of the project before making decisions for the entire project. You can do this with materials – such as paint, software, and other resources before making project decisions. It helps to ensure that the project will use the best solution of all the possible alternatives identified.