PMP Practice test 2: PMP Practice Test Two Part Two Flashcards
You are a project manager for your company and you are coaching your project team on quality. The team has a desire to work quickly and catch mistakes during product testing. Based on this analysis, complete this statement: Quality is _____________, never _____________.
- Quality is planned, never inspected in
- Quality is expensive, defects are more expensive
- Quality is mandatory, never optional items
- Quality is optional, never forgotten
Answer: Quality is planned, never inspected in
Explanation
Quality is always planned into a project and never inspected into a project. Prevention is preferred over inspection. It is better to design quality into deliverables, rather than to find quality issues during inspection. The cost of preventing mistakes is generally much less than the cost of correcting mistakes when they are found by inspection or during usage. The other options are not valid statements about quality and inspection.
Robert is the project manager for his company and he’s leading a large, international project. In this project, he’ll be purchasing from vendors in different countries for resources needed on the project. In his contracts with the international vendors, what must be clearly defined to alleviate any claims or litigation concerns later in the project?
- Contract attorneys
- Monetary unit
- Legal jurisdictions
- Purchasing officer for each country
Answer: Legal jurisdictions
Explanation
In international contracting, the legal jurisdictions under which the contracts will be administered are clearly spelled out in the contract. In most cases, the seller is an external contractor who is bound by a formal contractual relationship. Note that monetary units is often defined in the contract, but in consideration of litigation, the legal jurisdiction is the better choice for the scenario.
You are a project manager for the HJG Project, and you’re working with your project team and several key stakeholders to identify the project requirements. As part of this activity, you need to reference a specific project management plan that will define how requirements will be planned, tracked, and reported. What project management plan should you reference?
- Requirements management plan
- Scope management plan
- Project management
- Communicaitons management plan
Answer: Requirements management plan
Explanation
The requirements management plan defines how the requirements activities will be planned, tracked, and reported for the project. This answer is from the PMBOK Guide, 5.1.3.2.
You are the project manager of a new construction project for your organization. The project has just recently been chartered, and you’re working with the project team to define the project management plan, scope statement, and cost budget and other project details. Your customer has contacted you and informed you that they have several changes to the project, such as different flooring selection, larger windows, and an outdoor seating area. What should you do next?
- Refuse the changes as the project charter has already been created
- Complete a change request and pass the change through integrated change control
- Ask the team to explore the changes in costs, scope, schedule, risk, and quality concerns before approving the changes for the project
- Accept the changes and continue with project planning
Answer: Accept the changes and continue with project planning
Explanation
The project management plan should be baselined; that is, it is necessary to define at least the project references for scope, time, and cost, so that the project execution can be measured and compared to those references and performance can be managed. Before the baselines are defined, the project management plan may be updated as many times as necessary. No formal process is required at that time. However, once it is baselined, it may only be changed through the Perform Integrated Change Control process.
Martha is a project manager in her organization and she is working with the project team to create a data representation of the stakeholders’ authority and interest in the project. She wants to create a salience model for the key stakeholders. In this model, all of the following attributes are used except for which one?
- Urgency
- Power
- Influence
- Legitimacy
Answer: Influence
Explanation
Influence is not a component of the salience model. A salience model describes classes of stakeholders based on assessments of their power (level of authority or ability to influence the outcomes of the project), urgency (need for immediate attention, either time-constrained or relating to the stakeholders’ high stake in the outcome), and legitimacy (their involvement is appropriate).
Kelly is the project manager of the GHY Project for her organization. Management has asked Kelly to take the project scope baseline, the project cost baseline, and the project schedule baseline and create a hybrid baseline to reflect overall project performance. What should Kelly do next?
- Inform her manager that these are three separate items that are distinct and cannot be merged to show project performance
- Create a performance measurement baseline to show all three baselines and how the project is performing
- Create an information radiator of all the performance requirements management has requested
Answer: Create a performance measurement baseline to show all three baselines and how the project is performing
Explanation
Management has asked Kelly to create a performance measurement baseline. A performance measurement baseline is an integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance.
You are a project manager for your company, a startup technology company. Your project needs to purchase 30 laptops from a vendor and management has authorized you to manage the entire procurement decision and transaction as there is no procurement officer in your company. In this scenario, what type of purchasing are you participating in?
- Direct purchasing
- Project purchasing
- Vendor-based purchasing
- Decentralized purchasing
Answer: Decentralized purchasing
Explanation
For smaller organizations or startup companies and those without a purchasing, contracting, or procurement department, the project manager may assume the purchasing authority role to negotiate and sign contracts directly (decentralized purchasing). For more mature organizations, the actual procurement and contracting functions will be carried out by a separate department with the specific role to purchase, negotiate, and sign contracts (centralized purchasing).
Ned is a project manager in his organization and you are serving as a project management consultant on Ned’s project. Ned insists that his project needs a high-quality grade of material for the project work to be successful. You advise that quality and grade are often misunderstood. What’s the difference between quality and grade?
- Grade is the level of satisfaction the workers require from materials, while quality is the ability of the materials to deliver upon their satisfaction
- Quality is about having the best product, while grade is about having the correct products
- Quality is how well the materials fulfill requirements. grade is ranking or categorization of the materials
- Actually, Ned is correct. Quality and grade are now considered to be the same term in the PMBOK guide, sixth edition
Answer: Quality is how well the materials fulfill requirements. grade is ranking or categorization of the materials
Explanation
Quality and grade are not the same concepts. Quality as a delivered performance or result is “the degree to which a set of inherent characteristics fulfill requirements” (ISO 9000 [18].). Grade as a design intent is a category assigned to deliverables having the same functional use but different technical characteristics. The project manager and the project management team are responsible for managing the trade-offs associated with delivering the required levels of both quality and grade. While a quality level that fails to meet quality requirements is always a problem, a low-grade product may not be a problem.
Beth is a project manager in her organization and she’s working with her project sponsor to define the levels of risk in a new project. Beth wants to discuss the project resilience and the unknowable-unknowns in the project. These risk events can only be recognized after they have occurred in the project. What term is best assigned to these type of risk events that attack project resilience?
- Uncertain risk
- Negative risk
- Emergent risk
- Apparent risk
Answer: Emergent risk
Explanation
The existence of emergent risk is becoming clear, with a growing awareness of so-called unknowable-unknowns. These are risks that can only be recognized after they have occurred. Emergent risks can be tackled through developing project resilience. Apparent risks and uncertain risks are not valid risk management terms. Negative risk isn’t technically a risk management term, but it’s often used to describe risks that threaten project objectives.
Charles is the project manager of a large construction project for his city. He has been asked to provide a method for public scrutiny into the working and progress of the project. Which one of the following is the best example of transparency into the progress of the project work for communications and public relations with the city residents?
- Webcams on the job site
- Status reports and information on a project website
- Financial reports and data updated weekly
- Status reports mailed to the city residents
Answer: Webcams on the job site
Explanation
A trend in infrastructure and commercial construction projects is the use of technology including web cameras (webcams) to improve stakeholder communications and relations. During construction, one or more webcams are installed on the site, with periodic updates to a publicly available website. The progress on the project can be viewed on the Internet by all stakeholders. Video data can also be stored, allowing analysis if a claim arises. Some projects have discovered that the use of webcams minimizes disputes relating to the construction work on site, as the webcam has recorded the events, so there should be no disagreement about the facts of the matter.
Joan is a project manager in her organization and she is working with the project team to create the risk management plan. Joan wants to create a structure to show the decomposition of project risks in a hierarchical approach for the potential sources of risks in the project. What type of chart should Joan create with her project team?
- Risk burnup chart
- Risk decomposition map
- Risk burndown chart
- Risk breakdown structure
Answer: Risk breakdown structure
Explanation
A common way to structure risk categories is with a risk breakdown structure (RBS), which is a hierarchical representation of potential sources of risk. An RBS helps the project team consider the full range of sources from which individual project risks may arise. This can be useful when identifying risks or when categorizing the identified risks. The organization may have a generic RBS to be used for all projects, or there may be several RBS frameworks for different types of projects, or the project may develop a tailored RBS. Where an RBS is not used, an organization may use a custom risk categorization framework, which may take the form of a simple list of categories or a structure based on project objectives.
Ken is a project manager in his organization and he working with the project team to create the project network diagram for an IT implementation project. His team has identified the tasks of launching the new web server and shutting down the old web server. The team wants to make sure that the new web server is up and running before turning off the older web server. If the new server is the successor activity and the older web server is the predecessor what’s the relationship type between these two tasks in the scenario?
- FF
- LC
- SF
- SS
Answer: SF
Explanation
Start-to-finish (SF) is a logical relationship in which a successor activity cannot finish until a predecessor activity has started. The new web server (successor) has to start before the old web server can be shut down (predecessor).
You are a project manager for the JHK Project for your organization, and you’re working with the project team to build the project network diagram. Your project team has identified a series of tasks that must happen in a specific order, but this order will cause the project duration to increase. What’s the best description on the ordering of these tasks in this scenario?
- Work logic
- Constrained logic
- Hard logic
- Soft logic
Answer: Hard logic
Explanation
This is an example of hard logic, also called mandatory dependencies. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work.
Your organization has asked you, a project manager, to work with a business analyst to create a business case for a proposed project. All of the following items are reasons why a business case may be created except for which one?
- Market demand
- Legal requirement
- Profit and loss
- Organizational need
Answer: Profit and loss
Explanation
Profit and loss is not a reason why a business case may be created. Business cases are created as a cause of market demand, organizational need, customer request, technological advance, legal requirement, ecological impact, and social needs.
Mike is the project manager of the AQA Project for his company. His BAC is $2,345,000, and he is currently 25 percent complete with the project, though he is supposed to be 30 percent complete. In the project so far, Mike has spent $612,000. Some changes have been added to the project will cost an additional $125,000 and now reflect Mike as being 20 percent complete. What is the CPI of the project considering these new changes?
- 0.67
- 0.81
- No change
- 0.75
Answer: 0.81
Explanation
The CPI is now .81 because the added funds to the BAC and the reduction in total project completion cause the CPI to change.