Missed Questions 7 Flashcards
A global fashion house is planning next season’s product line and initiates a project to create media buzz before Fashion Week. The team launches a social media campaign. One team member publishes one of the top-secret designs on their personal social media feed.
The project manager speaks with the team member about the breach and the team member apologizes, explaining they had hoped to generate publicity. However, competitors pounce on the opportunity and a costly mistake is made.
Which three actions should the project manager take to safeguard the future of the project? (Choose 2)
- Revise the team charter and review organizational rules.
- Instruct the designers to create new designs immediately.
- Update the compliance requirements for the project.
- Restrict team member access to confidential material.
Revise the team charter and review organizational rules.
Explanation: Despite the potential high drama of this scenario, this is a simple case of a problem that needs to be addressed. To safeguard the future of this project, the project manager should log the issue, remind the team of organizational rules, update the compliance requirements for the project, and revise the team charter to ensure the team is mindful of the rules going forward. Even though this was a costly and embarrassing mistake, the project manager is the steward of the project and must take steps to ensure its success.
New designs are outside of the project scope and moving to restrict access to the confidential designs would probably not allow the team members to do their jobs. The project manager needs to be able to trust their team and the team members must uphold the value of honesty and exhibit ethical behavior. This is a core value of the PMI Code of Ethics and Professional Conduct.
✓ Instruct the designers to create new designs immediately.
Explanation: Despite the potential high drama of this scenario, this is a simple case of a problem that needs to be addressed. To safeguard the future of this project, the project manager should log the issue, remind the team of organizational rules, update the compliance requirements for the project, and revise the team charter to ensure the team is mindful of the rules going forward. Even though this was a costly and embarrassing mistake, the project manager is the steward of the project and must take steps to ensure its success.
New designs are outside of the project scope and moving to restrict access to the confidential designs would probably not allow the team members to do their jobs. The project manager needs to be able to trust their team and the team members must uphold the value of honesty and exhibit ethical behavior. This is a core value of the PMI Code of Ethics and Professional Conduct.
A government is ready to announce a new tax on sugary products to fund a healthcare program. The team is working on the first set of goals to secure buy-in from the industry stakeholders and launch a strong public campaign to support the mandate.
In which three ways can the project build a shared understanding of the project goals with public stakeholders? [Pick Two]
- Inform industry stakeholders that noncompliant businesses will be penalized.
- Announce the tax along with an advertising campaign to educate the country and individuals about the benefit.
- Use an incremental approach by taxing products with the highest sugar content only and explain how this will improve health results over a period of time.
- Launch a national survey program to anticipate how individuals and businesses will react.
Announce the tax along with an advertising campaign to educate the country and individuals about the benefit.
Explanation: Projects do NOT always bring popular changes. There are many ways to approach stakeholder buy-in to a controversial problem. Proving the value of the project incrementally is one, if you have the time. Explaining the benefits to the skeptical customer is an empathetic approach, which is also valid. And involving key stakeholders in the premise of the change and allowing them to share in its success is a third possibility. Because the change will be difficult for stakeholders, just listening or gathering data is NOT enough.
Use an incremental approach by taxing products with the highest sugar content only and explain how this will improve health results over a period of time.
Explanation: Projects do NOT always bring popular changes. There are many ways to approach stakeholder buy-in to a controversial problem. Proving the value of the project incrementally is one, if you have the time. Explaining the benefits to the skeptical customer is an empathetic approach, which is also valid. And involving key stakeholders in the premise of the change and allowing them to share in its success is a third possibility. Because the change will be difficult for stakeholders, just listening or gathering data is NOT enough.
A Project Manager notices that one team member seems increasingly unhappy during team meetings. The team member is not making progress on a key work package, and this lack of progress is now impacting the critical path. The team member feels that they are not in the correct role within the project team.
What should the Project Manager do?
1. Meet with the team member to discuss where they can contribute, based on their strengths.
2. Schedule weekly touchpoints with the team member to discuss barriers that may impact their work.
3. Reassure the team member about their abilities by reminding them that they were chosen for a reason.
4. Enroll the team member in targeted training to acquire the needed skills for their assigned role.
Meet with the team member to discuss where they can contribute, based on their strengths.
Explanation: Yes - This is the best response. The individual may truly be right. As a Servant Leader, you can help them find the correct role.
If the project manager decides to staff the project with team members with one or more contractors, what is the first step the project manager must take?
- Work with procurement to draft an RFP (or similar contracting document.)
- Identify organizations that can provide the needed resources.
- Determine if the organization has an preexsiting contracts with staffing agencies.
- Determine the types of skills needed and the required time frame.
Determine the types of skills needed and the required time frame.
Explanation: This is correct, as stated. Wysocki (2019) also indicates that the number of personnel is equally relevant to this first step.
All other steps listed are certainly relevant, but the process must start with the skills needed, the quantity needed, and the time frame needed.
A project team is completing a sprint. This team normally performs well under time pressure. But this time, something seems different. The workrooms are quiet, and people are having conversations that seem secretive. A check of the scrum board shows that work is on schedule and quality checks are met, yet the team lead feels anxious.
What should the team lead do?
- Think about any other recent changes or reasons that could be the cause of these anxious feelings.
- Assume everything is fine and let the team continue working.
- Ask everyone to give a quick report of how they think the sprint is going at the next standup.
- Tell the team you are feeling anxious about their work
Think about any other recent changes or reasons that could be the cause of these anxious feelings.
Explanation: If the data shows positive signs that work is on track and you are feeling anxious or unsure, then it’s a good idea to trust your instinct. Something could be happening outside of the project, and your awareness of it might be causing concern. Try to identify the cause of your anxiety on your own without spreading worry or alerting the team about it. Assuming everything is fine would be alright, but without some introspection to analyze the context of the project, your anxiety might affect the team.
The Project Manager receives a progress report during a demo and review meeting. The report shows that the agile project is not on track. Since all work was purposely selected and sequenced to meet higher-level objectives, the Project Manager is surprised by the report.
In the future, how can the Project Manager prevent this type of miscommunication in an agile project?
- Support self organization for the project team and help them provide buy-in for the project.
- Provide early training and ongoing mentoring about the agile approach for the project team.
- Ensure that the team is trained to use the agile process reporting system.
- Ensure that there is a contingency reserve to cover these issues.
Support self organization for the project team and help them provide buy-in for the project.
Explanation: For agile projects, rather than a project manager selecting and sequencing work, higher-level objectives are explained and the team members are empowered to self-organize specific tasks as a group to best meet those objectives. This leads to the creation of practical plans with high levels of buy-in from the team members.
PMBOK® Guide Sixth Edition (2018), Appendix 3 / X3.3.3 Executing Process Group, p670
A project team is working 24-hour days in shifts under hazardous conditions to train an operations team at an offshore plant. To ensure safety, one team member on each shift personally hands off the notes to the next shift. The system works until team member A complains that they worked more night shifts than everyone else. The project manager checks the rota for the last 3 weeks. The scheduler has made an error, and team member A has worked more night shifts than was planned.
Which two actions should the project manager take to resolve the problem? (Choose 2)
- Apply a temporary solution until the scheduler can correct the error.
- Ask the team to sit together and make their own rota.
- Discuss the challenges of the schedule with the whole team and decide on a better practice for scheduling.
4.Apologize to team member A and coach the scheduler on the criticality of the schedule. - Record the incident and solution in the lessons learned register.
Discuss the challenges of the schedule with the whole team and decide on a better practice for scheduling.
Explanation: We need an immediate response to address the issue and improve the scheduling process for the future. The team can sit together with the scheduler and decide how to create an appropriate schedule. The project manager should answer team member A’s complaint as well as coach the scheduler on the dangerous consequences of a scheduling error like this. Recording the incident in the lessons learned register will not resolve the problem, but it is a useful step for learning on future projects.
Apologize to team member A and coach the scheduler on the criticality of the schedule.
Explanation: We need an immediate response to address the issue and improve the scheduling process for the future. The team can sit together with the scheduler and decide how to create an appropriate schedule. The project manager should answer team member A’s complaint as well as coach the scheduler on the dangerous consequences of a scheduling error like this. Recording the incident in the lessons learned register will not resolve the problem, but it is a useful step for learning on future projects.
Two team members disagree about which technology should be used during the project, as each member prefers a different technology. Which of the following is the LEAST effective way to resolve this conflict?
- To maintain harmony, the project manager emphasizes to both team members that both technologies would work equally well for the project, but the charter already states the technology that will be used.
- The project manager demands they use one of the technologies.
- The project manager authorizes a test of both technologies to see which one would better fit the needs and the constraints of the project.
- The project manager agrees to use both technologies for all work on the project; all deliverables will be created, essentially twice, once for each technology.
The project manager demands they use one of the technologies.
Explanation: Demanding the team uses one of the technologies is an example of forcing/directing, and it is the least effective approach. It is a win-lose approach enforced through power.
A project manager realizes that sponsor expectations are NOT being met, specifically regarding project deliverables.
To address this issue, which action should the project manager take?
- Develop a stakeholder engagement plan.
- Update the risk register.
- Develop a communications management plan.
- Create a work breakdown structure (WBS).
Update the risk register.
Explanation: The Risk Register may have existing entries about the potential for the sponsors expectations not being met that need updating. If there were no existing entries, then there will be new risks associated with any plan of action.
An important team member and a key employee of a vendor that provides products to the project have both left their organizations. New individuals have been assigned to both positions. These new individuals know little about the project. Which are the most likely documents the project manager will need to review and revise related to the area of project stakeholder management?
- Communications plan and team charter
- Project charter and stakeholder engagement plan
- Stakeholder register and stakeholder engagement plan
- Procurement management plan and stakeholder engagement plan
Stakeholder register and stakeholder engagement plan
Explanation: Realistically, changing stakeholders could affect almost any aspect of the project. However, the key documents associated with the Project Stakeholder Management Knowledge Area that project manager would have to revisit would include the stakeholder register (for details such as name, contact information, and major expectations, among others) and the stakeholder register (to determine appropriate strategies to ensure this new person’s commitment to the project goals.)
Which of the following is the least likely tool and technique used to analyze, categorize, or visually display stakeholder information? [Pick Two]
- A fishbone (Ishikawa) diagram
- A salience grid
- An influence and impact grid
- A Classification, Identification, and Analysis (CIA) diagram
- Upwards, downwards, outwards, sideways
✓ A fishbone (Ishikawa) diagram
Explanation: A fishbone diagram is typically associated with quality management.
A salience grid
Explanation: This is a tool and technique to visually display stakeholder information for the process Identify Stakeholders.
An influence and impact grid
Explanation: This is a tool and technique to visually display stakeholder information for the process Identify Stakeholders.
✓ A Classification, Identification, and Analysis (CIA) diagram
Explanation:This term was invented for this question, though it sounds particularly impressive.
Upwards, downwards, outwards, sideways
Explanation: This method classifies stakeholders on their relationship to the project. Methods used to influence stakeholders can vary greatly based on the project manager’s relationship (e.g., upward to the sponsor or downward to a team member) to a project stakeholder.
A planned task in a sprint does not get completed due to an issue that appeared three days ago but did not get resolved. The Project Manager wants to prevent this type of situation in the future.
What should the Project Manager do?
- During the retrospective, examine the issue.
- During the next iteration planning meeting, discuss the issue.
3.In the next daily standup meeting, review the issue. - In the demo, address the issue.
During the retrospective, examine the issue.
Explanation: A retrospective is a great opportunity to talk about what went right, what went wrong, lessons learned and what to improve for next time.
A company executive who is not a key project stakeholder of a project has expressed continued interest and opinions directly to the project team. The key stakeholders are becoming annoyed and perceive the executive to be interfering and causing unwanted noise, but the project team finds the executive’s inputs helpful.
What should the team do first?
1. Discuss what should happen at the next retrospective.
2. Ask the product owner to intervene in the conflict.
3. Use Speed B Leas conflict management techniques.
4. Add this executive to the team as a key stakeholder.
Discuss what should happen at the next retrospective.
Explanation: There is a lot happening here that could be beneficial to the project but could also be harmful—the existing stakeholders could feel threatened, or the scope could be changing from what the stakeholders envisioned with the executive’s inputs. The team needs to decide what to do, but with a clear consensus and expert judgment before taking action. A retrospective is about gaining insights for team improvement. All of the options could likely happen as well, but the first thing to do is discuss with the team. If the team agrees that further engagement is desirable, then the team could move on to reclassification of the stakeholder and any resulting conflict management.
A project has an SV of $3,000. What is known about this project?
- It’s behind schedule
- Human resources are more talented than expected
3.There is scope creep - It’s ahead of schedule
It’s ahead of schedule
Explanation: A positive SV indicates that the project is ahead of schedule.
A project has a CPI of .98. What is known about this project?
- It’s behind schedule and over budget.
- It’s behind schedule
- It’s ahead of schedule.
- It’s over budget.
It’s over budget.
Explanation: A CPI less than 1 indicates the project is over budget.