Questions 1 Flashcards
A directive PMO (Project Management Office) differs from a supportive PMO in that a directive PMO is responsible for providing which critical role/resource to a project, while the supportive PMO acts in consultative roles?
- Risk Manager
- Project Manager
- Software System Analyst
- Business Process Owner
Answer Project Manager
Explanation
Directive PMOs take control of the projects by directly managing the projects. Project managers are assigned by and report to the PMO. The degree of control provided by the PMO is high.
Your project has undergone two change orders and you need to gain an understand of how those together have impacted the original baselined project budget solidified during Planning. Which of the following variance analysis formulas would you use?
- SV = EV – PV
- VAC = BAC – EAC
- CPI =EV/AC
- CV = EV -AC
Answer: CV = EV -AC
Answer: CV = EV -AC
Explanation
SV = EV - PV Schedule Variance = Earned Value - Planned Value VAC = BAC - EAC Variance at Completion = Budget at Completion - Estimate at Completion CPI = EV/AC Cost Performance Index = Earned Value - Actual Cost CV = EV - AC Cost Variance = Earned Value - Actual Cost
When you are planning Quality Management for your project, there are different techniques for data representation. Which of the four following techniques includes model known as a SIPOC, an acronym which stands for: suppliers, inputs, process, outputs, and customers?
- Flowcharts
- Logical Data Model
- Mind Mapping
- Matrix Diagrams
Answer: Flowcharts
Explanation
Flowcharts are also referred to as process maps because they display the sequence of steps and the branching possibilities that exist for a process that transforms one or more inputs into one or more outputs. Flowcharts show the activities, decision points, branching loops, parallel paths, and the overall order of processing by mapping the operational details of procedures that exist within a horizontal value chain. One version of a value chain is the SIPOC. You can see a sample of this model in Figure 8-6 on page 285 of the PMBOK.
The Code of Ethics and Professional Conduct includes both aspirational standards and mandatory standards for project managers. The Code was created to instill confidence in the project management profession and to help an individual in making wise decisions, particularly when faced with difficult situations where the individual may be asked to compromise his or her ___________ or values.
- Integrity
- Beliefs
- PMP Designation
- Knowledge
Answer: Integrity
Explanation
PMI publishes the Code of Ethics and Professional Conduct [5] to instill confidence in the project management profession and to help an individual in making wise decisions, particularly when faced with difficult situations where the individual may be asked to compromise his or her integrity or values. The values that the global project management community defined as most important were responsibility, respect, fairness, and honesty. The Code of Ethics and Professional Conduct affirms these four values as its foundation.
One of the two major influences on projects is known as EEFs. What does “EEF” stand for?
- Empirical Evaluation Failures
- Enterprise Estimation Field
- Enterprise Environmental Factors
- Evaluation Elemental Factors
Answer: Enterprise Environmental Factors
Explanation
The correct answer is Enterprise Environmental Factors. EEFs originate from the environment outside of the project and often outside of the enterprise, and may have an impact at the organizational, portfolio, program, or project level.
In which of the project management processes will you find stakeholders engaging with the project for the first time?
- Identify Risks
- Develop Project Charter
- Plan Scope Management
- Develop Project Management Plan
Answer: Develop Project Charter
Explanation
While stakeholders are engaged throughout every phase of the project, and can be involved in all of the project management processes, inputs and outputs, the first time a stakeholder engages with the project is during the Initiation process of Develop Project Charter.
Methodology is a system of practices, techniques, procedures, and rules used by those who work in a discipline which project manager apply in their management. (PMBOK is NOT a methodology, but a recommended reference for what practice?
1. Tailoring
2. Program management
3. Project management
4. Product management
Answer: Tailoring
Explanation
Methodology is a system of practices, techniques, procedures, and rules used by those who work in a discipline which project manager apply in their management. (PMBOK is NOT a methodology, but a recommended reference for tailoring). Tailoring is necessary because each project is unique.
Who does the Project Management Book of Knowledge (PMBOK) say is responsible for what the project team produces?
- Project Sponsor
- Project Business Owner
- Project Manager
- Executive Sponsor
Answer: Project manager
Explanation
Project Management Institute explains the role of a project manager as being similar to that of an orchestra’s conductor, stating, “The project manager and conductor are both responsible for what their teams produce—the project outcome or the orchestra concert, respectively. The two leaders need to take a holistic view of their team’s products in order to plan, coordinate, and complete them.”
Integration is a critical skill for project managers. Which of the following is NOT one of the levels that performing integration takes place at?
- Integration at the Cognitive Level
- Integration at the System Level
- Integration at the Context Level
- Integration at the Process level
Answer: Integration at the System Level
Explanation
The correct answer is “Integration at the System Level” because “System Level’ is made up. Project management may be seen as a set of processes and activities that are undertaken to achieve the project objectives. Although there is no stated definition on how to integrate the project processes, it is clear that a project has a small chance of meeting its objective when the project manager fails to integrate the project processes where they interact. The project manager should strive to become proficient in all of the Project Management Knowledge Areas. In concert with proficiency in these Knowledge Areas, the project manager applies experience, insight, leadership, and technical and business management skills to the project. Finally, it is through the project manager’s ability to integrate the processes in these Knowledge Areas that makes it possible to achieve the desired project results. Project managers need to be cognizant of the project context and these new aspects when managing the integration. Then project managers can decide how to best use these new elements of the environment in their projects to achieve success.
The definition of project management is the application of knowledge, skills, tools, and techniques to project activities to meet the what?
- Step by step outline of project management process found in the PMBOK
- Sponsors and stakeholders expectations
- Project requirements
- Deadlines set forth by the Board of Directors
Answer: Project requirements
Explanation
Though expectations and deadlines are important to a project manager, first and foremost their duty is to meet project requirements, in whatever form those requirements take.
Directing and Managing Project Work and Managing Project Knowledge are the two components of which part of which of the following:
- Facilitation Mangement
- Project Integration Management
- Core Objectives Management
- Executing Process
Answer: Project Integration Management
Explanation
Directing and managing project work is he process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the projects objectives. Managing project knowledge is the process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning. These two components define Project Integration Management.
Amber and Aurora are both performing software development tasks on a project to develop a new medical software to help doctors tune hearing aids more accurately for an individual patient. As Amber continues her work, Aurora sees her code degrading right in front of her eyes and realizes that one of the risks she had voiced earlier on in the project is coming true: the more Aurora tells the software to fine-tune the higher decibel ranges, the less capable it becomes of accurately identifying the lower decibels. She brings it to Aurora’s attention and after a short discussion they decide they need to report it to the Project Manager, Nishan, who pulls out the Risk Management Plan and sees that the team had developed a risk response should this occur. What should Nishan do now that the risk has now come to pass?
- Tell Amber and Aurora not to worry about it
- Update the Risk Management Plan to say the risk happened
- Execute the previously defined risk response.
- Check with the project sponsor
Answer: Execute the previously defined risk response.
Explanation
Proper attention to the Implement Risk Responses process will ensure that agreed-upon risk responses are actually executed. A common problem with Project Risk Management is that project teams spend effort in identifying and analyzing risks and developing risk responses, then risk responses are agreed upon and documented in the risk register and risk report, but no action is taken to manage the risk. Only if risk owners give the required level of effort to implementing the agreed-upon responses will the overall risk exposure of the project and individual threats and opportunities be managed proactively.
When she was assigned to a project to add one more flight between Honolulu and Tokyo to her airline’s daily scheduled flights, Xia was told by the portfolio steering committee exactly how many passengers they expected to be traveling this route by 3 months, 6 months, 9 months and 12 months after implementation. Into which project document did Xia record this information?
- Project Charter
- Benefits Management Plan
- Marketing Plan
- Business Case
Answer: Benefits Management Plan
Explanation
The benefits management plan is used to measure whether the benefits of the project were achieved as planned. And while Xia is a project manager, she was actually assigned the project prior to its official initiation, by helming the effort to do the research that led up to the formation of a business case and benefits management plan, which is how she and her team were able to get the steering committee to agree to initiate the project.
The Plan Quality Management process exists within the Planning phase of a project. In the Monitoring & Controlling phase of a project, you Control Quality. What is the missing related process you undertake during the Executing phase of a project?
- Prioritize Quality
- Define Quality
- Categorize Quality
- Manage Quality
Answer: Manage Quality
Explanation
Manage Quality is the missing process, and it occurs during the Executing phase of a project, when your job is to manage the quality of whatever it is that’s being executed. The other three options are not PMBOK processes.
How many Knowledge Areas are encompassed within the Closing process group?
- 10
- 4
- 6
- 1
Answer: 1
Explanation
Only Knowledge Area 4, Project Integration Management, has a component within the Closing process group, and that is: Close Project or Phase.