Construction Projects Flashcards

1
Q

Define a Manday

A

A MD is a unit of work performed by one person in eight hours. It is a set standard and does not change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is project scope sheet?

A

A project scope sheet includes general site information, preconstruction description, and photos for the environmental protection plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is direct labor?

A

All labor expended directly on an assigned construction task, either in the field or in the shop, which contributes directly to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is indirect labor?

A

All labor required to support construction but does not usually produce an end product itself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the Availability Factor?

A

Amount of time the worker is actually on the job (percentage)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Level I Gantt Chart?

A

Used as a primary tool to manage overall unit tasking. Shows weeks vs individual projects and reflects total MDs planned or expended.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Level II Gantt Chart?

A

Used as an individual project plan as well as to control and evaluate progress. Shows weeks vs master activities. Reflects allocated manpower resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Level III Gantt Chart?

A

Used to plan, schedule, and monitor/control the day-to-day operations of the project. Shows days vs construction activities for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is WIP?

A

Work in Place: The completed quantity of work divided by the total quantity of work yet to be performed (percentage)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the importance of generating and maintaining a CAS Sheet?

A

Construction Activity Summary Sheet:

  • Resource management support as determined in the detailed planning phase in the project schedule
  • Official documentation of actual project execution as part of the project package
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Field Adjustment Request?

A

FAR is a formal procedure to record, track, and monitor requests by the engineering unit for an alteration to the original project plans or specifications because of changed conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Design Change Directive?

A

DCD is a formal procedure to record changes to the project plans or specifications and become part of the project package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a Request for Information?

A

RFIs are a convenient, formal procedure to record, track, and monitor questions concerning a construction project’s plans and specifications. Recorded in a RFI submittal log.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who can approve a FAR?

A

The contracting officer or authorized representative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What approves the DCD?

A

The contracting officer as directed by the design agent, customer, or HHQ.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the 3-Phases of control for the execution of project quality control (QC)?

A
  1. Preparatory
  2. Initial
  3. Follow-Up
17
Q

What is a Definable Feature of Work?

A

DFOW is a task that is separate and distinct from other tasks and has separate control requirements.

18
Q

What sections are in a Project Package?

A
  1. General Information and Correspondence
  2. Activities and Networks
  3. Resources
  4. Plans
  5. Drawings and Specifications