AUC 349 Smoke Control Using PPF Flashcards

0
Q

When using the PPF s at a high rise fire what should be given first consideration for pressurization

A

The attack stairwell is the first consideration as ordered by IC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What tools Ventiation support group report to ICP WITH?

A
Two 27 inch PPF with exhaust hoses
Eye and ear protection
Dave Clark headset
HT
CO monitor
Elevator keys 
Halligen and Heavy axe
Door chocks 
Hand lights 
SCBA and full PPE
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Proper placement of PPFS IS based on what factors

A
  1. Number of PPFS
  2. Personnel available
    3 location of fire
    4 number floors in building
    5 stage of FF ops
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What should be done if negative results are encountered when using PPFS

A
  1. Discontinue pressurization by throttling down fans to idle
  2. Close doors to the stairwell that fan is pressuring
  3. Notify IC when fans are deactivated and doors secured
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the priority use for PPFS

A
  1. Pressurization of attack stair to support fire attack by controlling smoke condition at attack stair doorway and throughout the attack stairway
  2. pressurizing the evacuation stairwell for smoke and CO control
  3. Ventilating the public hallways for smoke and CO CONTROL
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the optimum placement of the PPF

A
  1. 4-6 from attack stairway door on the ground floor directly facing the door to the stairwell angle tilt of 80 degrees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

True or false you should place the fan in the stairwell thAt you are trying to pressurize?

A

False. Fan should placed to blow fresh air into the stairwell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The pressurization of attack stair will allow up to how many doors to be open and still be effective.?

A

Up to 3 doors and will still remain effective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Members cannot move from one area to another in stairwell…true or false

A

False: members may move from one area to another as long as remember to close the stairway doors behind them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who is responsible for maintaining a proper stairwell seal

A

All members on the fire ground

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who verifies that stairway doors are closed above The fire floor?

A

The vent support superviser will request that the IC instruct 3&4 due ladder companies verify

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who surveys the floors below fire floor of attack stairway to verify doors are in closed
Position

A

Vent support supervisor instructs vent group members to survey floors below fire floor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Depending on conditions one fan can pressurize up how many stories ?

A

10 stories

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Two fans will pressurize

A

40 story building when properlypostioned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If a additional fan is needed a second fan should be placed where ?

A

3 floors below the fire floor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If your trying to clear the stairway of smoke and CO how long should you open the bulkhead door the smoke clears

A

Approximately 60 seconds

16
Q

What are the benefits of pressuring and clearing contaminated stairwells of smoke andCO

A
  1. Faciltate the rapid and efficient evacuation and searches of the stairwells
  2. Limit the contamination of other parts of structure
  3. Reduce calls form panicked resident s due to smoke
  4. It provides fresh air to operating units
17
Q

If high levels of CO are encountered while using PPFS who should be notified

A

The IC

18
Q

If using fans for sequential vent where do you place the fan?

A

On the exterior of building

19
Q

Fans will be placed on the exterior of building when used to sequential vent in this situation the exhaust fans do not need to be used because fans are on exterior of building . True or false

A

False exhaust hoses shall still be used

20
Q

Firefighters may still operate in attack stairway when sequential venting that stairway

A

No FFs or civilians .. Must be removed before vent begins

21
Q

If venting the attack stair by sing sequential vent the bulkhead of attack stair should remain closed and bulkhead to evacuation stair should remain open .

A

No the bulkhead of the attack stair remains open and the bulkhead over the evacuation stair remains closed

22
Q

Co contamination occurs on multiple floors start where to relieve co

A

Start at the lowest point of contamination and work towards the top of building

23
Q

When trying to mechanical vent a structure where should look for an exhaust opening ?

A

As a close to and as high as possible to the seat of the fire

24
Q

When should you try and vent a la rge area mechanically ?

A

After the seat of fire is determined and fire is controlled by a sprinkler or handline

25
Q

When using PPFS to pressurize a large area for the purposes of mechanical vent how far back should you set the fan form I nlet opening ?

A

Further than 4-6 feet back used to pressurize stairs …..fan at 80 degress

26
Q

How large should the exhaust opening be when using PPFS to mechanical vent a large area?

A

Double the size of the inlet area where fan is placed

27
Q

When using roll down gates as the inlet area for the fans how do you create the seal

A

By adjusting the height of the roll down door