project management Flashcards

1
Q

what is critical path analysis?

A

a network diagram that helps organise a businesses tasks in level of importance and allocates time needed to achieve each task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is total float?

A

how long can one task go over without impacting the finishing time of the next task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

how do u calculate total float?

A

earliest finishing time of task A - duration - Earliest finishing time of task B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is free float?

A

how much one task can go over without impacting the end time of the entire project. q

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

how do you calculate free float?

A

earliest start time - duration - latest finish time of task before

How well did you know this?
1
Not at all
2
3
4
5
Perfectly