How often does ODP-1 require the RO and CO must perform a thorough evaluation (Control Board walk down)?

A

Conducted at a minimum every two hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What alarms cannot be left in fast flash ?

A

Possible Inadvertent Boron Dilution (BDAS)
CEA Position Out-of-Limits (PDIL)
Containment Sumps Excess Leakage (RCS Leakage Detection)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Per ODP-1, on which of the main control boards will ALL manipulations be peer-checked?

A

RMN-B01

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which of the following activities does not require a peer check per ODP-1?
A. Lowering load on the main turbine
B. Borating 1000 gallons during Mode 3
C. Paralleling the ‘A’ DG with offsite power through PBA-S03 during Mode 5
D. Transferring NAN-S01 from the Unit Aux Transformer to NAN-S03 in preparation for plant shutdown

A

The answer used to be B, but page 33 of ODP-1 specifically calls out borating/diluting as needing Peer Checks. - Changed by Nick Hart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which of the following two-handed operations is permitted by ODP-1?
A. Override and open primary sample isolation valves
B. Throttling of LPSI injection valves
C. Operation of SBCV permissives
D. Isolation of RCP Seal Bleed-off

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who’s permission is required to perform a two handed operation not required by plant design or outlined in ODP-1?

A

Operations Director

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What evolutions require plant announcements?

A

Operation of any breaker >480V
Changing plant Modes
Pump starts during normal operations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is a control room brief required?

A
Pending reactivity manipulations
As requested by team members
High activity in the control room
After discovery of an abnormal condition in the control room
AOP/EOP implementation and transitions
Change in strategy or priority
Following plant transients
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What Operations Are Allowed To Be Performed Skill of The Craft (No Procedure In Hand)?

A
HVAC Temp Controls
CEDMCS Mode And CEA Selector Switches
Blowdown Stack M/U
Draining The SOVP
Draining The Main Gen H2/Liquid Detectors
Pressurizer Heater Operations
RPCB Sub Group Selection Check
Main Gen MVAR Adj (As Directed By ECC)
Making Up To DG Jacket Water
Surge Tank Level Adjustments (CR permission)
Resetting Alarms (CR permission)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What things are considered when considering an operation for skill of the craft?

A

No existing procedure
Low complexity such that we would not consider writing a procedure
Low risk, event not likely without written guidance
Operator is capable of success
No plant status change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Describe Principles For Clear Communication

A
Concise
Noun Names Used
Accepted Terminology
Clear/Unambiguous
Phonetic Alphabet Used For Channels/Trains
Identify Sender/Receiver
Component And Action
Single Instruction!
Needed Precautions
Be careful  when communicating cross-department (Engineers speak their own version of English)
Use Three Legged Communications!
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who can communicate to the CR Staff?

A

SM/CRS Only, guests and advisors may not, guest and advisors should communicate only to the SM/CRS. If needed the SM will communicate to the CRS. This includes during an outage all OCC and Ops 4th Floor communications go through the SM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

List required on-shift CR meetings.

A

0700/1900
11:30AM/11:30PM
0515/1715

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

List required on-shift CR meetings.

A

0700/1900
1130/2330
0515/1715

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does it say at the bottom of every page of ODP-1?

A

THINK SAFETY AT ALL TIMES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Operations top priority?

A

Safety

17
Q

What will be done for equipment suspected of abnormal behavior, potential malfunction or operation under abnormal conditions?

A

Additional Monitoring

18
Q

Modifications of Operational Standards:
A. Are never permitted.
B. Are permitted when authorized by the operations director.
C. Will be required by shift supervision to ensure safe plant operations during certain events.
D. Will only be allowed when authorized by the shift manager during performance of emergency or abnormal operating procedures.

A

C

19
Q

Which is not Correct? During all modes of operation:
A. The CRS will direct or acknowledge each activity and evolution.
B. The Shift Manager may delegate responsibilities related to performance or control of work to other supervisors.
C. The CRS will determine what level of control and verification is required.
D. The CRS will concur with the procedure section to be used for each evolution.

A

B

20
Q
Per ODP-1 section 7.0 for monitoring, operator should monitor the following to have an overall picture of the plant except:
A. Reactor Power
B. RCS Temperature
C. CEA positions
D. Pressurizer level and pressure
E. SG pressure and Levels
A

C

21
Q
Ensuring a control room environment that promotes proper plant monitoring and control is the responsibility of the:
A. All control room personnel
B. The CRS
C. The CRS and SM
D. The SM
A

B

22
Q
Prompt recognition of AOP/EOP/EAL and tech spec entries is the responsibility of:
A. The SM
B. The ROs and CRS
C. The SM and CRS
D. The CRS
A

D.

23
Q
Unit 1 is refueling the core and the reactor operator is monitoring the plant.  In this case, the RO is responsible for monitoring:
A. Boards 1-7
B. Boards 2-6
C. Boards 3, 4, and 5
D. Boards 2, 3, and 4
A

D

24
Q

A BDAS alarm comes in on board 2 multiple times throughout the shift. WHich of the following is true concerning alarm response?
A. The alarm response is always continuous use.
B. The alarm response only needs to be used on the first performance.
C. The alarm response for BDAS is reference use only.
D. The BDAS alarm needs to be addressed within 10 minutes.

A

B

25
Q
During an outage, the standard application of alarm management applies to all except:
A. The electric plant
B. RCS inventory
C. EHC controls
D. Systems required by SRA
A

C

26
Q

Conditions that present a past or current challenge to, or question the ability of, a System, Structure, or Component to perform its function (meet design requirements) will be addressed by:

A

initiating a PVAR.

27
Q

If a conditions is corrected prior to initiating a PVAR, do you still need to write a PVAR, why or why not?

A

Yes, to evaluate potential extent, cause, or reportability of the condition. If in doubt, write a PVAR.

28
Q
Teamwork is fostered through all of the following except:
A. open communications,
B. cooperation
C. trust
D. respect
E. value
A

E

29
Q
Who's permission must be granted to approach the control boards?
A. CRS
B. SM
C.RO/CO
D. UDL
A

C.

Can be found under section 7.1

30
Q

What is the primary entry point of the control room?
A. Side Doors
B. Door by SM’s office
C. STSC

A

C.

31
Q

Who can communicate to the CR Staff?

A

SM/CRS Only, guests and advisors may not, guest and advisors should communicate only to the SM/CRS. If needed the SM will communicate to the CRS. This includes during an outage all OCC and Ops 4th Floor communication go through the SM.