Non Class 125V DC Flashcards

1
Q

What is the capacity of the ‘E’ and ‘F’ batteries?

A

Each battery has sufficient capacity to independently supply the required loads for 2 hours following the loss of the battery charger connected to the 125 VDC control center at a minimum temperature of 60F in the battery room.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the major loads on NKN-D43?

A

Oscillograph
Turbine Protection
Transformer annunciators
Plant annunciators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the normal source of power to the Plant Computer?

A

NKN-M45 (125V DC control center ‘E’) through a 45kVA inverter to NQ which supplies the plant computer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List the significant loads on NKN-M46

A
Main Turbine Emergency Oil Pump
Emergency Seal Oil Pump
Feedwater Pump A Emergency Oil Pump
Feedwater Pump B Emergency Oil Pump
NAN-S06 Control Power (Norm)
NAN-S05 Control Power (Alt)
Normal Access Personnel Air Lock
Emergency Access Personnel Air Lock
NKN-D44
NKN-D45
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List the major loads on NKN-M45

A
Plant Computer (NQ system)
NKN-D41
NKN-D42
NKN-D43
NAN-S05 (Norm)
NAN-S06 (Alt)
Main Generator Primary protection ckts
Main Generator Backup protection ckts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A ‘hard ground’ on NKN-M45 (or M46) will give the following indications …

A

Two yellow lights on the ground detection assembly are LIT, a white light at the NKN-M45 (M46) Control Center is LIT, and the Control Room receives an alarm.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the locations of all six 125 VDC distribution panels?

A
D41 - Turbine Building 100'
D42 - Aux Building 100'
D43 - Turbine Building 100'
D44 - In NKN-M46
D45 - In SSR Room
D19 - Chlorinator Building
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the major loads on NKN-D41?

A

Switchgear control power
Main Generator auxiliaries
Turbine Building HVAC control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

RCP bkr control receives power from …

A

NKN-D44 (located in NKN-M46)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The ____ Battery connects to NKN-M46 and is nominally rated for _____ Amp-Hours.

A

‘F’ (NKN-F18)

3460

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The SSO cabinet receives power from …

A

NKN-D45 (in SSR Room)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Control Power to the Cooling Towers has been lost, where and what DC distribution panel would you expect to send an AO to check?

A

Chlorinator Building, NKN-D19

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does the Turbine Building HVAC system support the NK system?

A
Two 100% capacity explosion proof exhaust fans provide adequate air flow to the NK system batteries and components for control of temperature and to prevent buildup of potentially explosive H2 concentration levels during normal plant operation.
Cooling for the non-class switchgear room and DC equipment on top of battery room is provided by HTN-A02C Air handling unit.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the purpose of the mechanical interlock on the ‘EF’ battery charger?

A

A mechanical interlock is provided between the ‘EF’ output bkrs, which prevents possible closing of both of the bkrs simultaneously and accidentally paralleling both of the 125 VDC control centers NKN-M45 and NKN-M46

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is accumulation of moisture prevented in NKN-M45 and M46?

A

Thermostatically controlled space heaters (rated at 240V) are provided in the control center, which are located in the bottom of each section and are supplied from 120 VAC sources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The ____ Battery connects to NKN-M45 and is nominally rated for _____ Amp-Hours.

A

‘E’ (NKN-F17)

2380

17
Q

What indications would you expect to receive for a ‘soft ground’ on NKN-M45 (or M46)?

A

Yellow light on the ground detection assembly
White light at the NKN-M45 Control Center
NO Control Room alarm

18
Q
(ANNUNCIATOR)
125VDC
CC M45
CHGR E/E1
TRBL
A

Causes for this annunciator include:
NKN-M45 Bus UV, ground or bkr trip
Batt Charger E/E1 overvoltage, UV, reverse current, AC supply UV or charger failure

19
Q
(ANNUNCIATOR)
125VDC
CC M46
CHGR F/EF
TRBL
A

Causes for this annunciator include:
NKN-M46 Bus UV, ground or bkr trip
Batt Charger F/EF overvoltage, UV, reverse current, AC supply UV or charger failure

20
Q
(ANNUNCIATOR)
125VDC
PNL
D41/42/43
TRBL
A

Causes for this annunciator include:

NKN-D41/42/43 Bus UV, ground or bkr trip

21
Q
(ANNUNCIATOR)
125VDC
PNL D19
CHGR G
TRBL
A

Causes for this annunciator include:
NKN-D19 Bus UV, ground or bkr trip
Batt Charger G overvoltage, UV, reverse current, AC supply UV or charger failure

22
Q

What is normal operating voltage for NKN-M45 when powered by the ‘E’ battery charger?

A

135VDC

23
Q

List the major loads on NKN-D42

A

Switchgear control power
Radwaste annunciators
Motor Operated Disconnects
Plant Annunciators