Guide - Section 2.7 (Deck#4) - Measurement Performance Flashcards

WHAT TO MEASURE: Baseline Performance, Resources

1
Q

The most common baselines are?

A

Cost and Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What baselines can use information in hte deliverable measures?

A

Scope or Technical baselines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Most schedule measures track actual performance to planned performance related to:

A
  1. Start and finish dates
  2. Effort and duration
  3. Schedule variance (SV)
  4. Schedule performance index (SPI)
  5. Feature completion rates

(SFD, ED, SV, SPI FCR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can measure the extent to which work is accomplished as planned (or not performing to plan)?

SFDV

A

Comparing the actual start dates to the planned start dates

and the actual finish dates to the planned finish dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What indicates whether estimates for the amount of work and the time the work takes are valid?
EDV

A

Actual effort and duration compared to planned effort and duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The measure of the efficiency of a process or system - in terms of the amount of work produced per unit of time or per unit of resources.

A

Productivity = output / input

Higher productivity ratios indicate a more efficient process, while lower ratios indicate a less efficient process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

refers to the amount of work required to complete a task or activity

A

effort

Effort is typically measured in terms of labor units, such as hours or days, and is based on the scope of the activity and influenced by factors such as complexity, repetition, and risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

refers to the amount of time it takes to complete the task or activity

A

duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Higher ratios of effort to duration indicate?

A

a less efficient process,
while lower ratios indicate a more efficient process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is determined by looking at performance on the critical path?

A

Schedule variance (SV) = earned value - planned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

An earned value management measure that indicates how efficiently the scheduled work is being performed?

A

Schedule performance index (SPI) = earned value / planned value

value of 1 indicates that the project is on schedule,
a value greater than 1 indicates that the project is ahead of schedule
a value less than 1 indicates that the project is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What can help assess progress and estimate completion dates and costs?

A

Feature Completion Rates

Examining the rate of feature acceptance during frequent reviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Common cost measures include:

A
  1. Burn rate ($ spent / time passed)
  2. Cost variance (CV)
  3. Cost performance index (CPI)

(BR, CV, CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In earned value management, what is determined by comparing the actual cost of a deliverable to the estimated cost?

A

Cost Variance (CV) = estimated cost - actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

An earned value management measure that indicates how efficiently the work is being performed with regard to the budgeted cost of the work?

A

Cost performance index (CPI) = earned value / actual cost

value of 1 indicates that the project is on budget,
a value greater than 1 indicates that the project is under budget
a value less than 1 indicates that the project is over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

a measure used to evaluate the difference between the planned (estimated) resource utilization and the actual resource utilization

A

Usage variance = planned usage - actual usage

17
Q

compares the actual cost of resources to the estimated cost

A

Price variance = planned cost - actual cost

18
Q

What evaluates the efficiency of resource utilization?

A

Usage variance

19
Q

By measuring what, project managers can identify areas where resources are being overused or underused and take corrective action?

A

Usage variance

20
Q

What is often used in conjunction with other metrics, such as cost variance and schedule variance, to provide a comprehensive view of project performance?

A

Usage variance

21
Q

Where is usage variance calculated?

A

at any level of the project, from individual tasks to the entire project.

22
Q

This measurement compares the actual cost of resources to the estimated cost?

A

Price variance = estimated cost - actual cost