Guide - SEction 2.7 (Deck#2) - Measurement Performance Flashcards

KPIs, Effective Metrics

1
Q

What helps to ensure the right things are measured and reported to stakeholders?

(eem)

A

Establishing effective measures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What allow for tracking, evaluating, and reporting information that can communicate project status, help improve project performance, and reduce the likelihood of performance deterioration?

A

Effective measures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What allow the project team to use information to make timely decisions and take effective actions?

A

Effective measures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are quantifiable measures used to evaluate the success of a project?

A

Key performance indicators (KPIs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are 2 types of KPIs?

A

leading indicators and lagging indicators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What predict changes or trends in the project?

A

Leading indicators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does the project team do if the leading indicator is unfavorable?

A

The project team evaluates the root cause of the leading indicator measurement and takes actions to reverse the trend.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What can help identify potential performance variances before they cross the tolerance threshold?

A

leading indicators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the high level desired result of using leading indicators?

A

Reduce performance risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are some examples of non-quantifiable leading indicators that indicate project performance may be at risk?

A

The lack of a risk management process,
stakeholders who are not available or engaged,
or poorly defined project success criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What measure project deliverables or events?

A

lagging indicators

They provide information after the fact, they reflect past performance or conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What can also be used to find correlations between outcomes and environmental variables?

A

lagging indicators

For example, a lagging indicator that shows a schedule variance may show a correlation with project team member dissatisfaction. This correlation can assist the project team in addressing a root cause that may not have been obvious if the only measure was schedule status.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are 5 characteristics of effective metrics (or SMART criteria)?

A
  1. Specific
  2. Meaningful (measurable)
  3. Achievable (agreed)
  4. Relevant (realistic or reasonable)
  5. Timely (time bound)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What characteristic to metrics is defined by - Measures should be tied to the business case, baselines, or requirements. It is not efficient to measure product attributes or project performance that do not lead to meeting objectives or improving performance?

A

Meaningful

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What characteristic to metrics is defined by - the people, technology, and environment.

A

Achievable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What characteristic to metrics is defined by - what to measure?

A

Specific

17
Q

What characteristic to metrics is defined by - information provided by the measure should provide value and allow for actionable information?

A

Relevant

18
Q

What characteristic to metrics is defined by - Information that is old is not as useful as fresh information?

A

Timely

Forward-looking information, such as emerging trends, can help project teams
change direction and make better decisions