Final Q&A Flashcards

Wrong answers

1
Q

Under what circumstances can a contractor request an extension of time for completion of a construction contract and what is the process for making such a request according to FAR part 11.5?
A contractor can request an extension of time within 10 days of the beginning of a delay caused by a variation in estimated vs actual quantity of unit-priced items.
A contractor can request an extension of time if the variation in estimated vs actual quantity of unit-priced items exceeds +/- 15%. The request must be made within 10 days of the beginning of the delay.
A contractor can request an extension of time if the variation in estimated vs actual quantity of unit-priced items is less than +/- 15%. The request must be made within 10 days of the beginning of the delay.
A contractor cannot request an extension of time for completion.
FAR 11.5

A

B. A contractor can request an extension of time if the variation in estimated vs actual quantity of unit-priced items exceeds +/- 15%. The request must be made within 10 days of the beginning of the delay.

Explanation:
FAR Part 11.5 addresses “Liquidated Damages” for construction contracts and includes provisions related to delays caused by variations in quantities. Specifically, under FAR 11.503, a contractor is allowed to request an equitable adjustment (including time extensions) if there is a substantial variation in the estimated versus actual quantities of unit-priced items. The threshold for such a request is typically a variation exceeding +/- 15%.

Additionally, the contractor is required to notify the contracting officer within 10 days of the start of the delay to ensure timely processing of the request.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following shall not be made available to a member of the public under the Freedom of Information Act?

A statement made by a contracting officer to a mediator to resolve a dispute

A complaint received by the FCC about an inappropriate television broadcast

An FBI report profiling the suspect in an unsolved crime

An agreement giving a photographer access to photograph military assets
FAR 24

A

A. A statement made by a contracting officer to a mediator to resolve a dispute

Explanation:
Under the Freedom of Information Act (FOIA), certain types of information are exempt from disclosure to the public. FAR Part 24 implements FOIA guidelines to protect sensitive information. The following exemptions under FOIA are relevant:

Exemption 4: Protects trade secrets and confidential commercial or financial information.
Exemption 5: Protects inter-agency or intra-agency communications that are privileged, such as:
Attorney-client privilege
Deliberative process privilege

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following contract modifications needs to be signed by both the contractor and the contracting officer?
A termination notice
An agreement definitizing a letter contract
A change authorized by the Options clause
An administrative change

A

An agreement definitizing a letter contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Except as authorized by law, what is the maximum term of contracts for severable services that are funded by annual appropriations?

100 days
Five years
Until the end of the fiscal year of the appropriation
There is no maximum specified by the FAR

A

Until the end of the fiscal year of the appropriation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which of the following is not a function of the General Services Administration?

Provides digital pricing tools to help federal contracting officers and others find awarded prices to use in negotiations

Management of U.S. Federal property

Allows federal agencies to acquire a wide range of commercial products, services, and software solutions from pre-approved vendors using a Multiple Award Schedule

Procurement Innovation Resource Center which provides guidance and tools to assist the GSA acquisition team with incorporating innovation into procurements

Administers foreign aid programs and humanitarian assistance to federal agencies.
FAR Part 41.203

A

E. Administers foreign aid programs and humanitarian assistance to federal agencies.

Explanation:
The General Services Administration (GSA) primarily focuses on managing federal property, procurement, and providing resources and solutions to federal agencies to streamline acquisition processes. FAR Part 41.203 pertains to energy procurement but does not address foreign aid or humanitarian assistance, which are responsibilities handled by other agencies such as the U.S. Agency for International Development (USAID) or the Department of State.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a CPSR and what is its purpose?

Contractor Pricing System Review; to ensure that a contractor is correctly and accurately applying dollar thresholds in its pricing

Contractor Purchasing System Review; to evaluate the efficiency and effectiveness with which the contractor spends Government funds

Counterfeit Part Surveillance Report; to detect and avoid the use of parts which have been misrepresented or unlawfully reproduced

Contractor Program Status Register; to record the price, quality, delivery, and technical and financial capabilities of competing vendors

A

Contractor Purchasing System Review; to evaluate the efficiency and effectiveness with which the contractor spends Government funds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which is not one of the two types of Value-Engineering approaches?
Incentive approach
Teaming approach
Mandatory program
None of the above
FAR Part 48

A

Teaming approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When a make-or-buy program is required of a contractor, how should major items be categorized?
“Can-make,” “can-buy,” or “can make or buy”
“Shall make” or “shall buy”
“Must make,” “must buy,” or “can either make or buy”
“Raw material,” “commercial item,” or “off-the-shelf item”

A

“Must make,” “must buy,” or “can either make or buy”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which statute applies to a contract for the dismantling, demolition, or removal of improvements under FAR Part 37.301, unless further construction work is intended at that location?

The Service Contract Labor Standards statute.

The Davis-Bacon Act.

The Walsh-Healey Public Contracts Act.

The Fair Labor Standards Act.
FAR Part 37.301

A

B. The Davis-Bacon Act.

Explanation:
FAR 37.301 states that the Davis-Bacon Act applies to contracts for the dismantling, demolition, or removal of improvements if further construction work is intended at the location. This is because the Davis-Bacon Act is designed to ensure that workers on federally funded or assisted construction projects are paid prevailing wages.

However, if no further construction work is planned, the contract is treated as a service contract, and the Service Contract Labor Standards statute may apply instead.

Analysis of Other Options:
The Service Contract Labor Standards statute: This applies to service contracts but not when further construction is intended at the location after demolition. The Davis-Bacon Act takes precedence in those cases.
The Davis-Bacon Act: Correct, as it applies to contracts involving construction, alteration, or repair, including those where demolition is part of a broader construction effort.
The Walsh-Healey Public Contracts Act: This applies to manufacturing or furnishing materials, supplies, articles, or equipment and is not relevant to construction or demolition contracts.
The Fair Labor Standards Act: This governs minimum wage, overtime pay, and other labor standards but does not specifically apply to federal construction or demolition contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When should the contracting officer charge interest on the balance of an advance payment?

When the contract is for research and development

For all contracts, except when interest is excluded by statute or agency procedures

Only under cost-reimbursement contracts with state or local governments

Always

A

For all contracts, except when interest is excluded by statute or agency procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A contract that is awarded using other than sealed bidding procedures is what?

A sole source contract

A negotiated contract

Always the best value for the Government

Not described in the FAR

A

A negotiated contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If the contractor does not have an approved purchasing system, and the agency awards a covered contract type, then consent to subcontract is required for…

subcontracts for advisory and assistance services.

subcontracts that exceed the micro-purchase threshold.

cost-reimbursement, time-and-materials, labor-hour subcontracts or letter contracts and unpriced actions.

all subcontracts.
FAR Part 44

A

C. cost-reimbursement, time-and-materials, labor-hour subcontracts or letter contracts and unpriced actions.

Explanation:
FAR Part 44.201-1 outlines the requirements for consent to subcontract when a contractor does not have an approved purchasing system. Specifically:

Consent to subcontract is required for certain types of subcontracts, particularly when the contract type involves greater risk to the government, such as:
Cost-reimbursement subcontracts (since costs are reimbursed directly, government oversight is critical).
Time-and-materials or labor-hour subcontracts (where payment is based on labor hours and materials, increasing risk of inefficiency).
Letter contracts and unpriced actions (where terms are not fully negotiated, and potential risks are higher).
Subcontracts for fixed-price contracts below certain thresholds generally do not require consent unless specifically outlined in the prime contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the term for the amount of money specified in a bond as the maximum payment for which the surety is obligated?
Bonded amount
Guaranteed amount
Performance amount
Penal amount

A

Penal amount

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the following scenarios requires posting an RFQ on e-Buy?

When the order consists of brand name specifications.

When using sole source procurement methods only.

When utilizing blanket purchase agreements (BPAs).

When the order is not being placed against a GSA schedule.
FAR Part 8.404-6

A

A. When the order consists of brand name specifications.

Explanation:
FAR Part 8.404-6 outlines the requirements for placing orders against General Services Administration (GSA) Federal Supply Schedules (FSS). When an agency specifies brand name products in a request for quotation (RFQ), the e-Buy system must be used to post the RFQ, unless one of the limited exceptions applies. This requirement is intended to promote competition and transparency.

Analysis of Other Options:
When the order consists of brand name specifications: Correct, as FAR 8.404-6(c) specifies that RFQs with brand name requirements must be posted on e-Buy to ensure fair opportunity for vendors to compete.
When using sole source procurement methods only: Sole source procurement generally bypasses competitive solicitation, so posting on e-Buy is not required.
When utilizing blanket purchase agreements (BPAs): BPAs established under a GSA schedule have separate procedures, and posting on e-Buy is not mandatory unless the order has brand name specifications.
When the order is not being placed against a GSA schedule: e-Buy is specifically designed for use with GSA schedule contracts, so this is not applicable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A contractor infringes on a copyright with the authorization of the Government. What remedy is available to the copyright holder?

A suit for monetary damages against the Government in the Court of Federal Claims

An injunction against the Government, prohibiting use of the copyrighted material

A suit for monetary damages against the contractor in a Federal court

No relief is available to the copyright holder

A

A suit for monetary damages against the Government in the Court of Federal Claims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A failure in estimating, accumulating, or reporting costs to comply with applicable cost accounting standards is called what?
Deviation
Nonconformity
Noncompliance
Digression

A

Noncompliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Who is authorized to sign a contract on behalf of the United States?
Only the contracting officer
The contracting officer, or a representative appointed by the contracting officer
Any representative of the procuring agency
Only the senior procurement executive of the procuring agency

A

Only the contracting officer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

If hazardous materials are expected to be used during contract performance, what must the apparent successful offeror do prior to contract award?

Make all reasonable efforts to procure nonhazardous materials instead

Make a list of the hazardous materials to be used available to the public

Furnish hazardous material data on a Material Safety Data Sheet

Require bonding and insurance during performance of the contract

A

Furnish hazardous material data on a Material Safety Data Sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A mineral required for production in performance of a contract is not mined in the United States, but can be acquired from another country. How does the Buy American statute apply in this case?

The mineral must be acquired from a domestic supplier

The mineral is considered a foreign end product

Performance of the contract must be stopped until a domestic substitute becomes available

The mineral may be acquired from a foreign source if it is in the best interest of the Government

A

The mineral may be acquired from a foreign source if it is in the best interest of the Government

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Agencies shall use simplified acquisition procedures to the maximum extent practicable…

for all purchases of supplies or services exceeding the simplified acquisition threshold.

for all purchases of supplies or services not exceeding the simplified acquisition threshold, including purchases at or below the micro-purchase threshold.

for all purchases of supplies or services not exceeding the micro-purchase threshold.

for all purchases of supplies or services between the micro-purchase threshold and the simplified acquisition threshold.

A

for all purchases of supplies or services not exceeding the simplified acquisition threshold, including purchases at or below the micro-purchase threshold.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

xcept as specifically permitted by executive agencies, the fast payment procedure may not be used for individual purchasing instruments exceeding what amount?
$15,000
$75,000
$35,000
$10,000

A

$35,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Which of the following is true about size standards?

The size standards established by the SBA are universal for all industries

NAICS codes are updated by OMB every year

A new NAICS code can be used for up to 12 months before SBA issues a size standard for it

A

Application of size standards includes specifying the size standard in the solicitation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The statutory limit when negotiating fee for a Cost-Plus-Fixed-Fee contract for maintenance services is what percent of the contract’s estimated cost, excluding fee?
10 percent
15 percent
6 percent
There is no fee limitation
FAR 15.404-4(c)(4)(i) or FAR 16.306(c)

A

A. 10 percent

Explanation:
Under FAR 15.404-4(c)(4)(i) and FAR 16.306(c), when negotiating a fee for a Cost-Plus-Fixed-Fee (CPFF) contract, statutory fee limitations are set depending on the type of work:

Research and Development Work: The fee limit is 15% of the contract’s estimated cost (excluding the fee).
Architectural and Engineering Services: The fee limit is 6%.
Other Work, including maintenance services: The fee limit is 10% of the contract’s estimated cost (excluding the fee).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Which of the following is a system whereby the contracting officer receives authorization from a fiscal and accounting officer to obligate funds on purchase documents against a specified lump sum of funds reserved for the purpose for a specified period of time rather than obtaining individual obligation authority on each purchase document?

a charge account.
long lead funding.
bulk funding.
a blanket purchase agreement (BPA).

A

C. Bulk funding.

Explanation:
Bulk funding is a method where a lump sum of funds is reserved for a specific purpose and period, allowing the contracting officer to obligate funds against that sum without needing individual obligation authority for each purchase document. This approach simplifies administrative procedures for multiple small purchases by using a pre-approved pool of funds.

Analysis of Other Options:
A charge account: This term is not relevant in the context of government contracting or funding mechanisms under the FAR.
Long lead funding: Refers to the allocation of funds for items or components that require a long lead time to produce or procure, not a system for obligating funds for multiple purchases.
Bulk funding: Correct. This method reserves a lump sum of funds for specified uses, streamlining the process for small purchases.
A blanket purchase agreement (BPA): BPAs are agreements between the government and a vendor to simplify repetitive purchases of supplies or services. They are not a funding mechanism but rather a procurement t

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Which of the following proposal analysis techniques is the process of independently reviewing and evaluating specific elements of each offeror’s proposed cost estimate to determine whether the estimated proposed cost elements are realistic for the work to be performed?
Cost Analysis
Cost Realism Analysis
Price Analysis
Price Realism Analysis

A

Cost Realism Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which of the following is NOT prohibited under the Prohibition on Contracting for Certain Telecommunications and Video Surveillance?
A contractor using a covered telecommunications system that is not used in the performance of a federal contract.

Extending an existing contract that contains covered telecommunication equipment.

Entering into a contract that is 30 days or fewer for services that use covered telecommunications equipment.

Providing a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements.
FAR 4.2102

A

D. Providing a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements.

Explanation:
Under FAR 4.2102, the Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (as per Section 889 of the 2019 National Defense Authorization Act) outlines restrictions on federal contracting involving certain covered telecommunications equipment and services (e.g., equipment from Huawei, ZTE, and other blacklisted entities). However, there are some exceptions, including:

Backhaul, roaming, and interconnection arrangements: These are not prohibited because they are incidental third-party services that contractors cannot control directly.
Analysis of Other Options:
A contractor using a covered telecommunications system that is not used in the performance of a federal contract: Prohibited. FAR prohibits contractors from using covered equipment or services, even if not directly used for the federal contract, unless a waiver is granted.
Extending an existing contract that contains covered telecommunication equipment: Prohibited. Extending or renewing contracts involving covered equipment is not allowed under the prohibition.
Entering into a contract that is 30 days or fewer for services that use covered telecommunications equipment: Prohibited. There is no exemption based on contract duration; any contract involving covered equipment or services is prohibited unless a specific exception applies.
Providing a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements: Not prohibited. These are recognized exceptions because they are external services that contractors typically do not directly control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Which of the following is NOT required to be revealed during a post-award debriefing?
Evaluated technical score of the successful offeror.

Evaluated price of all offerors.
Evaluation of the unsuccessful offeror’s proposal.
Ranking of all offerors.
All of the above

A

B. Evaluated price of all offerors.

Explanation:
According to FAR 15.506, post-award debriefings are conducted to provide unsuccessful offerors with information about the award decision. The goal is to increase transparency while protecting sensitive information. The following details must be shared during a debriefing:

The evaluated technical score of the successful offeror and the debriefed offeror.
The evaluated price of the successful offeror.
A summary of the rationale for the award decision.
The ranking of the debriefed offeror, if a ranking was deve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

The contracting officer may only accept proposal revisions during
discussions.
fact finding.
clarifications.
communications to establish the competitive range.
FAR 15.001 and FAR 15.307

A

A. Discussions.

Explanation:
According to FAR 15.307, proposal revisions can only be submitted in response to discussions. Discussions occur after the establishment of the competitive range and are conducted to allow offerors an opportunity to revise their proposals to address weaknesses, deficiencies, or other issues identified by the contracting officer. Following discussions, the contracting officer must request final proposal revisions (FPRs) before making an award decision.

Analysis of Other Options:
Discussions: Correct. Proposal revisions are allowed during discussions, and offerors in the competitive range are given the opportunity to submit final proposal revisions afterward.
Fact finding: Fact finding is used to clarify or verify facts but does not involve the submission of proposal revisions.
Clarifications: Clarifications are limited exchanges with offerors to resolve minor or administrative issues (e.g., correcting errors or confirming compliance). Proposal revisions are not allowed during clarifications.
Communications to establish the competitive range: Communications at this stage are intended to determine which offerors should be included in the competitive range. Proposal revisions are not permitted during this phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Options for increased quantities of supplies/services may NOT be expressed in terms of

percentage of specific line items.
increase in specific line items.
additional numbered line items.
a range of quantities for various line items.
FAR 17.204(f)

A

D. A range of quantities for various line items.

Explanation:
According to FAR 17.204(f), options for increased quantities of supplies or services must be clearly defined and cannot be expressed as a range of quantities for various line items. The FAR requires that options be specific and measurable to avoid ambiguity and ensure enforceability. Options must be expressed in terms such as:

A percentage increase in specific line items.
A specified quantity increase in specific line items.
Additional numbered line items.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

The Bonds statute requires performance and payment bonds for any construction contract valued in excess of _________?
$150,000
$650,000
$1,000,000
$2000

A

$150,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

The terminating contracting officer shall recommend the release of excess funds to the contracting officer within how long after the receipt of the termination notice?
30 days
3 months
10 days
14 days
FAR 49.105-2

A

30 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What types of costs are normally segregable and accountable under the terms of the Change Order Accounting clause?
indirect costs
fringe costs
general and administrative costs
direct costs
FAR 43.203

A

direct costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

If the contractor does not have an approved purchasing system, consent to subcontract is required for all of the following except which?

Cost-reimbursement contracts
Fixed-price contracts below the simplified acquisition threshold
Time-and-materials contracts
Letter contracts
FAR 44.201-1(b)

A

Fixed-price contracts below the simplified acquisition threshold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Personnel rendering services who are not subject to the supervision and control usually prevailing in relationships between the government and its employees are performing under:

Performance-based contracts
Personal services contracts
Supply contracts
Non-personal services contracts
FAR 37.101

A

Non-personal services contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

For a supplemental agreement, when is the effective date of a contract modification?

the date agreed upon by the contracting parties
the issue date
the date received by the contractor
the date received by the government
FAR 43.101

A

the date agreed upon by the contracting parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is a payment for accepted supplies or services, including payments for accepted partial deliveries?

Delivery payments
Final/partial acceptance
Commercial payments
Progress payments
FAR 32.001

A

Delivery payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Commercial Advance Payment shall not exceed what percentage of the contract price?
10%
15%
5%
1%
FAR 32.202-1(b)(6)

A

15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is the relationship between the Economy Act and more specific statutory authority, like the statutory authorities for the Federal Supply Schedules or Governmentwide acquisition contracts?

The Economy Act applies when more specific statutory authority does not exist.

The Economy Act always applies, regardless of whether more specific statutory authority exists.

Orders using the Federal Supply Schedules or Governmentwide acquisition contracts are to be treated as Economy Act orders.

The Contracting Officer must use discretion in deciding whether to use the Economy Act or more specific statutory authority that may apply to an acquisition.
FAR 17.502-2(b)

A

The Economy Act always applies, regardless of whether more specific statutory authority exists.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

This law states laborers and mechanics must be paid time and a half for overtime work (e.g.;40 hours/week)?

Wage Rate Requirements statute
Kickbacks statute
Minimum Wage Act
Contract Work Hours and Safety Standards Act
FAR 22.403-3

A

Contract Work Hours and Safety Standards Act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

This law provides that federal contracts in excess of $2,000 to which the United States or the District of Columbia is a party for construction, alteration, or repair (including painting and decorating) of public buildings or public works within the United States, shall contain a clause that no laborer or mechanic employed directly upon the site of the work shall receive less than the prevailing wage rates as determined by the Secretary of Labor.

Wage Rate Requirements (Construction)
Contract Work Hours and Safety Standards Act
Minimum Wage Act
Kickbacks statute
FAR 22.404-1(b)

A

Wage Rate Requirements (Construction)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

A post-award debriefing should ideally occur within ____ days after receipt of the written request for a debriefing by the offeror.
7
3
5
10
FAR 15.506

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

A letter contract may be used when the schedule will provide definitization of a contract no greater than _____ days after the date of the letter contract.
180
150
120
365
FAR 16.603

A

180

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

A distinct six-position code consisting of a combination of alpha and/or numeric characters assigned to identify specific agency offices, units, activities, or organizations by the General Services Administration for civilian agencies and by the Department of Defense for defense agencies is the:

Activity Address Code (AAC)
Procurement Instrument Identification (PIID)Â
Line Item Number
CAGE Code Number
FAR 2.101

A

Activity Address Code (AAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Which of the following is correct about the FAR citation 15.506(a) ______________________.

15 is the part, 5 is the subpart, 06 is the section, and a is the paragraph.
1 is the part, 5 is the subpart, 506 is the section, and a is the paragraph.
15 is the part, 5 is the subpart, 06 is the paragraph, and a is the sentence.
15 is the part, 50 is the subpart, 6 is the section, and a is the paragraph.
FAR 1.105-2

A

15 is the part, 5 is the subpart, 06 is the section, and a is the paragraph.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

f it is in the Government’s interest, and if supplies or services required in the performance of a Government contract are available from Government supply sources, contracting officers may authorize contractors to use these sources in performing:

A contract using Federal Prison Industries.
Government-wide Acquisition Contracts (GWACS)
Federal Supply Schedules
A contract under the “AbilityOne” Program
FAR 51.101

A

C. Federal Supply Schedules

Explanation:
Under FAR 51.101, contracting officers may authorize contractors to use Government supply sources—such as Federal Supply Schedules (FSS)—if it is determined to be in the Government’s interest. This authorization allows contractors to procure supplies or services directly from these government sources to support contract performance.

Analysis of Other Options:
A contract using Federal Prison Industries: Federal Prison Industries (also known as UNICOR) provides mandatory sources of supply for certain items, but FAR 51.101 does not specifically apply to its use.
Government-wide Acquisition Contracts (GWACs): GWACs are contracts for technology and other solutions managed by specific agencies. Contractors do not “use” GWACs directly; they are used by federal agencies.
Federal Supply Schedules: Correct. FAR 51.101 explicitly allows contracting officers to authorize contractors to use Federal Supply Schedules when performing a Government contract.
A contract under the “AbilityOne” Program: The AbilityOne Program ensures that certain services and supplies are provided by organizations employing individuals with disabilities. FAR 51.101 does not apply to AbilityOne contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

When might contracting offices request exceptions to standard forms?
Overprinting forms
Computer generated forms
Special construction and printing forms
Continuation sheets
FAR 53.106

A

A. Overprinting forms

Explanation:
According to FAR 53.106, contracting offices may request exceptions to standard forms when overprinting is required. Overprinting involves preprinting additional information on a standard form to tailor it for a specific purpose, such as including agency-specific instructions or terms.

Exceptions to standard forms are requested through the General Services Administration (GSA), as outlined in FAR 53.106.

Analysis of Other Options:
Overprinting forms: Correct. Overprinting is a valid reason to request an exception to a standard form.
Computer-generated forms: These are permissible as long as they conform to the exact layout and content of the standard forms. Exceptions are generally not required for computer-generated forms.
Special construction and printing forms: This is not mentioned as a reason for requesting exceptions under FAR 53.106.
Continuation sheets: Continuation sheets are standard and commonly used to supplement standard forms; they do not require an exception.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Protests may be filed with ______________________.

either the contracting officer or the United States Court of Federal Claims

either the agency or the General Accountability Office

the agency, the GAO, or the General Services Board of Contract Appeals (ADP acquisition)

Small Claims Court for awards under the Simplified Acquisition threshold
FAR 33.102

A

B. either the agency or the General Accountability Office (GAO)

Explanation:
Under FAR 33.102, protests may be filed with:

The agency: This is referred to as an agency-level protest, where the protest is resolved internally by the contracting agency.
The Government Accountability Office (GAO): The GAO provides an independent forum for bid protests, typically involving issues like improper evaluation or failure to follow solicitation requirements.
Additionally, protests may also be filed with the United States Court of Federal Claims (COFC), although this is not explicitly stated in FAR 33.102. COFC is an alternative to GAO and agency-level protests but is not included in the correct options for this question.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

To which of the following subcontracts may a contracting officer consent?

A subcontract that makes the results of arbitration between the prime contractor and subcontractor binding on the Government

A subcontract obligating the contracting officer to deal directly with the subcontractor

A subcontract providing for payment on a ?fixed-price incentive basis

A subcontract providing for payment on a cost-plus-a-percentage-of-cost basis
FAR 44.203(b

A

C. A subcontract providing for payment on a fixed-price incentive basis

Explanation:
Under FAR 44.203(b), the contracting officer may consent to subcontracts, but certain types of subcontracts are explicitly prohibited or require specific scrutiny. Here’s how the options align with FAR guidance:

A subcontract that makes the results of arbitration between the prime contractor and subcontractor binding on the Government: Not permitted. This would improperly obligate the Government to decisions in which it has no direct participation, violating FAR principles.
A subcontract obligating the contracting officer to deal directly with the subcontractor: Not permitted. The Government maintains a relationship only with the prime contractor and does not deal directly with subcontractors.
A subcontract providing for payment on a fixed-price incentive basis: Permitted. Fixed-price incentive contracts are an acceptable contract type and may be used in subcontracts with contracting officer consent.
A subcontract providing for payment on a cost-plus-a-percentage-of-cost basis: Not permitted. This type of contract is explicitly prohibited under FAR 16.102(c) because it incentivizes increased costs without promoting cost control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Regarding the authority to use extraordinary contractual actions, agencies shall maintain complete records of all actions taken under FAR 50.1.For request for relief processed, these records shall include, as a minimum the following except:

Approval above the contracting officer.

The contractor’s request.

All relevant memorandums, correspondence, affidavits, and other pertinent documents.

A copy of the contractual document implementing an approved request.
FAR 50.101-3

A

A. Approval above the contracting officer.

Explanation:
According to FAR 50.101-3, agencies must maintain complete records of all extraordinary contractual actions, but approval above the contracting officer is not explicitly required to be included in the records. The records must include:

The contractor’s request: Documentation of the relief or modification requested by the contractor.
All relevant memorandums, correspondence, affidavits, and other pertinent documents: Supporting documents to justify the request and the decision-making process.
A copy of the contractual document implementing an approved request: This ensures that the final action is properly documented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Contract items are technically classified as-

complex and non-complex
critical and non-critical
commercial and military-federal
supply or service
FAR 46.203

A

B. critical and non-critical

Explanation:
Under FAR 46.203, contract items are technically classified as either critical or non-critical for the purpose of determining the appropriate level of inspection and quality assurance. The classifications are based on the item’s importance to the mission and the consequences of failure:

Critical Items: Items that require special attention and inspection because their failure could result in mission failure, injury, or significant loss.
Non-Critical Items: Items that do not have as significant an impact on mission success or safety, requiring less stringent inspection and oversight.
This classification helps determine the type and level of quality assurance procedures that are applied.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

GSA is authorized by 40 U.S.C.501 to contract for utility services for periods not exceeding ___ years.
10
5
15
25
FAR 41.103(a

A

D. 25

Explanation:
According to FAR 41.103(a), the General Services Administration (GSA) is authorized under 40 U.S.C. 501 to contract for utility services for periods not exceeding 25 years. This extended contract term is allowed to support long-term planning and stable relationships with utility providers, which is essential for the efficient management of government facilities and resources.

Key Takeaway:
GSA is authorized to enter into utility service contracts for up to 25 years under 40 U.S.C. 501 and FAR 41.103(a), ensuring flexibility and stability in utility procurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Who can authorize continued performance in the face of a protest after award?

The head of the contracting activity.
The commanding officer.
The chief of the contracting office.
The contracting officer provided his findings are documented in the file.
FAR 33.1

A

A. The head of the contracting activity.

Explanation:
According to FAR 33.104(c)(2), after a protest is filed, the head of the contracting activity (HCA) is the official authorized to permit continued performance of a contract in the face of a protest after award. This authority is contingent upon a determination that:

Performance of the contract is in the best interest of the United States, or
Urgent and compelling circumstances significantly affecting the interests of the United States will not allow for waiting for the protest decision.
This decision must be documented with a detailed rationale and added to the contract file.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Under the Buy American statute, a domestic end product that does not consist wholly or predominantly of iron or steel or a combination of both means all the following, except:

An end product manufactured in the United States if the product has undergone substantial transformation.
An unmanufactured end product mined or produced in the United States.
An end product manufactured in the United States if the product meets the domestic content test.
An end product manufactured in the United States if the product is a commercially available off-the-shelf item.
FAR 25.001(c) and FAR 25.003.

A

D. An end product manufactured in the United States if the product is a commercially available off-the-shelf item.

Explanation:
Under the Buy American statute and its implementing regulations in FAR 25.001(c) and FAR 25.003, a domestic end product that does not consist wholly or predominantly of iron or steel must meet specific criteria:

Substantial transformation: An end product is considered domestic if it is manufactured in the United States and has undergone a substantial transformation.
Unmanufactured end product: If the product is unmanufactured, it must be mined or produced in the United States.
Domestic content test: The end product must be manufactured in the United States and meet the domestic content test, which requires that a certain percentage of the cost of its components is mined, produced, or manufactured in the United States.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

When applying an alternate to FAR 52.215-2 or FAR 52.215-5 the determination and findings in Foreign Acquisitions must identify the contract and its purpose, and identify if the contract is with a foreign contractor or with a foreign government or an agency of a foreign government; describe the efforts to include the basic clause; describe the price and availability of the supplies or services from the United States and other sources; and determine that it will best serve the interest of the United States to use the appropriate alternate clause.
True
False
FAR 25.1001

A

True

Explanation:
According to FAR 25.1001, when applying an alternate to FAR 52.215-2 (Audit and Records—Negotiation) or FAR 52.215-5 (Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Products and Commercial Services) in the context of foreign acquisitions, the contracting officer must prepare a Determination and Findings (D&F).

The D&F must include the following:

Identification of the contract and its purpose.
Identification of whether the contract is with a foreign contractor, foreign government, or an agency of a foreign government.
Description of efforts to include the basic clause.
Price and availability analysis of supplies or services from the United States and other sources.
Determination that using the alternate clause will best serve the interest of the United States.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

What does FEMP stand for?

Federal Energy Management Program
Federal Energy Management Products
Federal Environment Management Program
Federal Environment Management Products
FAR 23.103

A

Federal Energy Management Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Some acceptable contents of a subcontracting plan include the following.

A description of the method used to develop the subcontracting goals.

The description of the method used to identify potential sources for solicitation purposes.

A statement of the total dollars planned to be subcontracted.

Assurances that the offeror will include the clause at 52.219-6.
FAR 19.704

A

D. Assurances that the offeror will include the clause at 52.219-6.

Explanation:
Under FAR 19.704, a subcontracting plan must include specific elements aimed at ensuring compliance with small business subcontracting goals. Some of the acceptable contents include:

A description of the method used to develop the subcontracting goals (e.g., how the contractor determined realistic goals for small business participation).
A description of the method used to identify potential sources for solicitation purposes (e.g., outreach efforts or databases used to find small business subcontractors).
A statement of the total dollars planned to be subcontracted, with a breakdown for small businesses, including small disadvantaged, women-owned, HUBZone, and veteran-owned businesses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Assume that the CO has rejected the SBA’s recommendation to set aside an acquisition.

proceed with full and open competition.

suspend action on the acquisition.

complete a fair and reasonable price determination.

complete an SBA override signed by the next higher person in the CO’s chain of command.
FAR 19.502-8

A

B. Suspend action on the acquisition.

Explanation:
According to FAR 19.502-8, if a contracting officer (CO) rejects the Small Business Administration’s (SBA) recommendation to set aside an acquisition for small business, the SBA can appeal the decision to the head of the contracting activity (HCA). During the appeal process, the contracting officer must suspend action on the acquisition until the appeal is resolved, unless:

The HCA makes a written determination that proceeding with the acquisition is in the best interest of the Government.
Urgent and compelling circumstances exist that require the acquisition to proceed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

___________ are written instruments of understanding that contain terms and conditions that apply to future orders, a description of supplies and services to be provided, and methods for pricing, issuing, and delivering future orders.

Indefinite-Delivery Arrangements

Blanket Purchase Agreements

Basic Ordering Agreements

Fixed-Price Contracts
FAR 16.703

A

C. Basic Ordering Agreements

Explanation:
According to FAR 16.703, a Basic Ordering Agreement (BOA) is a written instrument of understanding between a government agency and a contractor. It outlines:

Terms and conditions that apply to future orders.
A general description of the supplies or services to be provided.
Methods for pricing, issuing, and delivering future orders.
A BOA is not a contract by itself but provides a framework for issuing orders efficiently when specific requirements arise.

Analysis of Other Options:
Indefinite-Delivery Arrangements: Incorrect. This is not a defined term under the FAR. Instead, the FAR discusses Indefinite-Delivery Contracts (IDCs) in FAR Subpart 16.5.
Blanket Purchase Agreements (BPAs): Incorrect. While BPAs (covered under FAR 13.303) are also agreements for streamlined purchasing, they are typically used under simplified acquisition procedures and are not as formal as BOAs.
Basic Ordering Agreements: Correct. BOAs provide the structure for future orders, as described in FAR 16.703.
Fixed-Price Contracts: Incorrect. Fixed-price contracts are fully executed contracts with fixed terms, not agreements for fut

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

A ______________ is the review and evaluation of any separate cost elements and profit or fee in an offeror’s or contractor’s proposal, as needed to determine a fair and reasonable price or to determine cost realism, and the application of judgment to determine how well the proposed costs represent what the cost of the contract should be, assuming reasonable economy and efficiency.
Price analysis
Cost Analysis
Technical Analysis
Cost Realism Analysis
FAR 15.404

A

B. Cost Analysis

Explanation:
According to FAR 15.404-1(c), cost analysis is the review and evaluation of:

Separate cost elements (e.g., labor, materials, overhead).
Profit or fee in a contractor’s proposal.
The application of judgment to assess whether the proposed costs are fair and reasonable or realistic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Which of the following statements is true in regard to contracting officers tailoring the clause at FAR 52.212-4, Contract Terms and Conditions-Commercial Products and Commercial Services?

Contracting officers may not tailor this clause.
Contracting officers may tailor any paragraph of this clause
Contracting officers may tailor any paragraph of this clause if a waiver is approved.
Contracting officers shall tailor this clause by addenda to the solicitation and contract.
FAR 12.302.

A

D. Contracting officers shall tailor this clause by addenda to the solicitation and contract.

Explanation:
According to FAR 12.302, contracting officers may tailor the clause at FAR 52.212-4 to accommodate the specific needs of a particular acquisition, provided the tailoring is consistent with commercial practices and does not contradict statutory requirements. Tailoring is done by addenda to the solicitation and contract. The process ensures the clause aligns with both the commercial nature of the acquisition and the Government’s requirements.

Analysis of Other Options:
Contracting officers may not tailor this clause: Incorrect. FAR 12.302 explicitly permits tailoring of the clause when necessary, as long as it aligns with commercial practices.
Contracting officers may tailor any paragraph of this clause: Incorrect. While tailoring is permitted, certain paragraphs of FAR 52.212-4 cannot be tailored because they are required by statute or regulation.
Contracting officers may tailor any paragraph of this clause if a waiver is approved: Incorrect. Tailoring does not require a waiver but must adhere to the guidelines in FAR 12.302.
Contracting officers shall tailor this clause by addenda to the solicitation and contract: Correct. Tailoring is explicitly done by addenda, as stated in FAR 12.302, ensuring it is clear and consistent with the solicitation and contract requirements.
Key Takeaway:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

When must contracting officers synopsize contract awards?

When contract awards exceed $25,000
When contract awards exceed $15,000
When contract awards exceed $30,000
When contract awards exceed $20,000
FAR 5.3

A

C. When contract awards exceed $30,000

Explanation:
According to FAR 5.301(a), contracting officers must synopsize contract awards in the System for Award Management (SAM) via the Contract Opportunities portal when the contract award exceeds $30,000, unless an exception applies.

This synopsis provides public notice of the contract award and promotes transparency and accountability in federal procurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

What criteria is not a valid consideration to make an award based on other than full and open competition?

Demonstration of unique capability specific to the services proposed.
Resembles the substance of a competitive acquisition.
Substantial duplication of cost unrecoverable through competition.
Schedule impact causing unacceptable delays.
FAR 6.3

A

B. Resembles the substance of a competitive acquisition.

Explanation:
Under FAR 6.3, contracting officers may award contracts using other than full and open competition in specific circumstances, as outlined in FAR 6.302. These justifications must be based on valid criteria such as unique capabilities, substantial cost duplication, or schedule impacts. However, the criterion that a procurement “resembles the substance of a competitive acquisition” is not a valid justification for using other than full and open competition.

Analysis of Other Options:
Demonstration of unique capability specific to the services proposed: Valid. FAR 6.302-1 allows for sole-source contracts if only one source can meet the requirements due to unique capabilities.
Resembles the substance of a competitive acquisition: Not valid. This is not a recognized criterion for other than full and open competition.
Substantial duplication of cost unrecoverable through competition: Valid. FAR 6.302-1(a)(2)(ii) allows for exceptions if competition would cause substantial duplication of costs that are not expected to be recovered.
Schedule impact causing unacceptable delays: Valid. FAR 6.302-2 permits the use of other than full and open competition in cases of urgency where delays would significantly harm the Government.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

The National Industrial Security Program Operating Manual (NISPOM) is implemented in which two publications? The National Industrial Security Program Operating Manual (NISPOM) (32 CFR part 117) and the _________:
DoD Manual 5220.22, Volume 2, National Industrial Security Program: Industrial Security Procedures for Government Activities.
DoD Manual 5220.20, Volume 5, National Industrial Security Program: Industrial Security Procedures for Government Activities.
DoD Manual 5220.22, Volume 5, National Industrial Security Program: Industrial Security Procedures for Civilian Activities.
DoD Manual 5220.20, Volume 2, National Industrial Security Program: Industrial Security Procedures for Civilian Activities.
FAR 4.402(b)

A

A. DoD Manual 5220.22, Volume 2, National Industrial Security Program: Industrial Security Procedures for Government Activities.

Explanation:
According to FAR 4.402(b), the National Industrial Security Program Operating Manual (NISPOM), codified at 32 CFR Part 117, is implemented through:

The NISPOM itself, which provides guidance for safeguarding classified information by contractors, licensees, and grantees of the U.S. government.
DoD Manual 5220.22, Volume 2, which outlines industrial security procedures specific to government activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

An agency must transmit a notice of proposed contract action to the governmentwide point of entry at least 15 days before issuance of a solicitation, or a proposed contract action the Government intends to solicit and negotiate with only one source under the authority of FAR 6.302, except that, for acquisitions of commercial products or commercial services:

The Contracting Officer must transmit the notice at least 40 days before issuance of a solicitation if the acquisition is covered by the World Trade Organization Government Procurement Agreement or a Free Trade Agreement.

The Contracting Officer may establish a shorter period for issuance of the solicitation if the estimated amount of the contract action is less than the simplified acquisition threshold

The Contracting Officer transmits the notice only if subcontracting opportunities exist.

The Contracting Officer may use the combined synopsis and solicitation procedure.
FAR 5.203.

A

The Contracting Officer may use the combined synopsis and solicitation procedure.
FAR 5.203.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

A written acquisition plan must include the following EXCEPT:

Applicable conditions
Risk and Risk Mitigation
Statement of Need
Source Selection Evaluation Board Report
FAR 7.105

A

Source Selection Evaluation Board Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Which authority permitting other than full and open competition may be used when none of the other authorities in FAR 6.302 apply?

International agreement.
National security
Public interest.
Unusual and compelling urgency.
FAR 6.302-7(b).

A

C. Public interest.

Explanation:
Under FAR 6.302-7(b), the authority to use “other than full and open competition” in the interest of the public may be invoked when none of the other authorities in FAR 6.302 apply. This authority is considered a “last resort” and is rarely used because it requires a high level of approval and justification. Specifically:

It must be determined by the agency head that the use of this authority is necessary.
A written determination must explain how it serves the public interest.
This determination must be approved by a higher authority and published in the Federal Register.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

The following are exceptions to the requirement for contracting officers to make notices of proposed contract actions available through the governmentwide point of entry, except:

Competitive acquisitions under the Section 8(a) program.

Acquisitions for utility services (other than telecommunications services) and only one source is available.

Acquisitions required by a statute to be made from a specific source, such as a workshop for the blind under the rules of the Committee for Purchase from People Who Are Blind or Severely Disabled.

An order placed under FAR Subpart 16.5.
FAR 5.202 and FAR 5.205(f).

A

A. Competitive acquisitions under the Section 8(a) program.

Explanation:
Under FAR 5.202, there are specific exceptions to the requirement for contracting officers to make notices of proposed contract actions available through the governmentwide point of entry (GPE), such as SAM.gov. However, competitive acquisitions under the Section 8(a) program are not exempt and must still be publicized unless another specific exception applies.

Analysis of the Options:
Competitive acquisitions under the Section 8(a) program: Incorrect (Not an exception). While sole-source acquisitions under Section 8(a) may qualify for exceptions under certain conditions, competitive 8(a) acquisitions do not automatically fall under these exceptions and must be publicized unless another FAR 5.202 exception applies.
Acquisitions for utility services (other than telecommunications services) and only one source is available: Correct (Exception). Per FAR 5.202(a)(7), acquisitions for utility services where only one source is available are exempt from the notice requirement.
Acquisitions required by a statute to be made from a specific source, such as a workshop for the blind under the rules of the Committee for Purchase from People Who Are Blind or Severely Disabled: Correct (Exception). Per FAR 5.202(a)(4), these acquisitions are exempt because the source is mandated by statute.
An order placed under FAR Subpart 16.5: Correct (Exception). Orders under FAR Subpart 16.5 for Indefinite-Delivery Contracts are exempt from the requirement, as stated in FAR 5.202(a)(11).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Governmentwide point of entry (GPE)Â means the single point where Government business opportunities greater than ___________, including synopses of proposed contract actions, solicitations, and associated information, can be accessed electronically by the public.
35000
20000
35000
25000
FAR 2.101

A

25000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

What is a covered employee?

Covered employee means an individual who performs an acquisition function and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; and subcontractors that are self-employed individuals treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor employee of the contractor who performs an acquisition function closely associated with inherently governmental functions .
FAR 3.11

A

C. Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Explanation:
According to FAR 3.1101, a covered employee refers to an individual who performs acquisition functions closely associated with inherently governmental functions and is:

An employee of the contractor, or
A self-employed individual subcontractor who is treated as a covered employee because there is no employer to whom the individual could submit the required disclosures.
This definition ensures that individuals performing these sensitive functions are subject to the same disclosure and compliance requirements as employees of the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Who can authorize continued performance in the face of a protest after award?

The head of the contracting activity.

The commanding officer.

The chief of the contracting office.

The contracting officer provided his findings are documented in the file.
FAR 33.1

A

The head of the contracting activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

A foreign end product may be purchased under the Buy American Act if___________.

the price of the lowest domestic offer is determined to be unreasonable by the CO.

the article is manufactured in South America.

the cost of the domestic components equals at least 25 percent of the total cost of all components.

the head of the agency approves the purchase.
FAR 25.103

A

the price of the lowest domestic offer is determined to be unreasonable by the CO.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

The Bonds statute requires performance and payment bonds for any construction contract valued in excess of _________?
$150,000
$650,000
$1,000,000
$2000
FAR 28.102-1(a)

A

$150,000

73
Q

Who is responsible for performing CAS administration for all contracts and subcontracts in a business unit?

Cognizant Federal Agency Official
Contracting Officer
Head of Contracting Agency
Head of Agency
FAR 30.601

A

Cognizant Federal Agency Official

74
Q

What is the relationship between the Economy Act and more specific statutory authority, like the statutory authorities for the Federal Supply Schedules or Governmentwide acquisition contracts?

The Economy Act applies when more specific statutory authority does not exist.

The Economy Act always applies, regardless of whether more specific statutory authority exists.

Orders using the Federal Supply Schedules or Governmentwide acquisition contracts are to be treated as Economy Act orders.

The Contracting Officer must use discretion in deciding whether to use the Economy Act or more specific statutory authority that may apply to an acquisition.
FAR 17.502-2(b)

A

The Economy Act applies when more specific statutory authority does not exist.

75
Q

his law provides that federal contracts in excess of $2,000 to which the United States or the District of Columbia is a party for construction, alteration, or repair (including painting and decorating) of public buildings or public works within the United States, shall contain a clause that no laborer or mechanic employed directly upon the site of the work shall receive less than the prevailing wage rates as determined by the Secretary of Labor.

Wage Rate Requirements (Construction)
Contract Work Hours and Safety Standards Act
Minimum Wage Act
Kickbacks statute
FAR 22.404-1(b)

A

Wage Rate Requirements (Construction)

76
Q

What does FEMP stand for?
Federal Energy Management Program

Federal Energy Management Products
Federal Environment Management Program
Federal Environment Management Products
FAR 23.103

A

Federal Energy Management Products

77
Q

What is the minimum amount of information that a request for proposals for competitive acquisitions shall contain?

The government’s requirement, the anticipated terms and conditions that will apply to the contract, the information required to be in the offeror’s proposal, and factors that will be used to evaluate the proposal

The anticipated size of the proposal, the government’s requirement, the urgency of the requirement, the information required to be in the offeror’s proposal, and the factors that will be used to evaluate the proposal

The government’s requirement and the information required to be in the offeror’s proposal

The type of contract contemplated, the government’s requirement, the information required to be in the offeror’s proposal, and the proposal due date and time
FAR 15.2

A

The government’s requirement, the anticipated terms and conditions that will apply to the contract, the information required to be in the offeror’s proposal, and factors that will be used to evaluate the proposal

78
Q

An offeror may request a post-award debriefing by submitting a written request for debriefing to the Contracting officer to be received within _____ days after receipt of a notice of contract award.
3
7
5
10
FAR 15.506

A

3

79
Q

A post-award debriefing should ideally occur within ____ days after receipt of the written request for a debriefing by the offeror.
7
3
5
10
FAR 15.506

A

5

80
Q

Which instrument is indicated by the letter designation A, in position 9 of the PIID?

Basic ordering agreements.
Basic purchasing agreements
Blanket ordering agreements
Blanket purchase agreements
FAR 4.1603(3)

A

Blanket purchase agreements

81
Q

When should a Contracting Officer publicize a requirement in the GPE though a synopsis?

The Contracting Officer should publicize 1 week prior to solicitation.

The Contracting Officer should publicize 30 days prior to solicitation.

The Contracting Officer should publicize 1 month prior to solicitation.

The Contracting Officer should publicize 15 days prior to solicitation.
FAR 5.203

A

The Contracting Officer should publicize 15 days prior to solicitation.

82
Q

When must contracting officers synopsize contract awards?

When contract awards exceed $25,000
When contract awards exceed $15,000
When contract awards exceed $30,000
When contract awards exceed $20,000
FAR 5.3

A

When contract awards exceed $25,000

83
Q

______________ products or services that have a lesser or reduced effect on human health and the environment when compared with competing products or services that serve the same purpose. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product or service.

Environmentally Friendly
Environmentally Conscientious
Environmentally Preferable
Environmentally Advantageous
FAR 2.101

A

Environmentally Preferable

84
Q

Contract items are technically classified as-
complex and non-complex
critical and non-critical
commercial and military-federal
supply or service
FAR 46.203

A

B. Critical and non-critical

Explanation:
Under FAR 46.203, contract items are classified as critical or non-critical based on the item’s significance to the mission and the consequences of its failure. This classification guides the type and level of inspection and quality assurance required during contract performance.

Critical items: These items require special attention and stringent quality controls because their failure could result in mission failure, injury, or significant loss.
Non-critical items: These items do not have the same potential for severe consequences in case of failure and therefore require less stringent inspection and oversight.
This technical classification ensures the appropriate allocation of resources for quality assurance based on the item’s importance and risk.

85
Q

Which of the following is an example of a contract under which contractors could be authorized to use government supply sources?

Government firm-fixed price contract
Contract under the Javits-Wagner-O’Day Act (known as AbilityOne)
A negotiated contract with a contractor that has no other government cost reimbursement type contracts
Time-and-materials contracts for repair of commercial equipment
FAR 51.101

A

A. Government firm-fixed price contract

Explanation:
Under FAR 51.101, contractors may be authorized to use government supply sources, such as GSA schedules, when performing work under certain contracts. Authorization is determined by the contracting officer when it is in the Government’s interest. Government firm-fixed-price contracts are an example of contracts where contractors can be granted such authorization if it benefits the government.

Analysis of Other Options:
Government firm-fixed price contract: Correct. Contractors working under firm-fixed-price contracts can be authorized to use government supply sources when it aligns with the Government’s best interest.
Contract under the Javits-Wagner-O’Day Act (known as AbilityOne): Incorrect. AbilityOne contracts are designed for organizations employing individuals with disabilities, and they operate under separate statutory requirements. These contracts do not typically involve authorization for contractors to use government supply sources.
A negotiated contract with a contractor that has no other government cost reimbursement type contracts: Incorrect. The type of negotiation or the absence of other contracts is not a criterion for authorization under FAR 51.101.
Time-and-materials contracts for repair of commercial equipment: Incorrect. While time-and-materials contracts may involve material purchases, using government supply sources is

86
Q

To which of the following subcontracts may a contracting officer consent?

A subcontract that makes the results of arbitration between the prime contractor and subcontractor binding on the Government

A subcontract obligating the contracting officer to deal directly with the subcontractor

A subcontract providing for payment on a ?fixed-price incentive basis

A subcontract providing for payment on a cost-plus-a-percentage-of-cost basis
FAR 44.203(b)

A

C. A subcontract providing for payment on a fixed-price incentive basis

Explanation:
Under FAR 44.203(b), contracting officers may consent to certain types of subcontracts but are prohibited from consenting to others, particularly those that impose obligations on the Government or violate regulations. Here’s how the options align with FAR guidance:

A subcontract that makes the results of arbitration between the prime contractor and subcontractor binding on the Government: Not permitted. This would improperly obligate the Government to arbitration outcomes in which it has no direct role, violating FAR principles.
A subcontract obligating the contracting officer to deal directly with the subcontractor: Not permitted. The Government maintains a contractual relationship only with the prime contractor and does not directly engage with subcontractors.
A subcontract providing for payment on a fixed-price incentive basis: Permitted. Fixed-price incentive contracts are an acceptable contract type and may be used in subcontracts with contracting officer consent.
A subcontract providing for payment on a cost-plus-a-percentage-of-cost basis: Not permitted. This type of payment structure is explicitly prohibited under FAR 16.102(c) because it incentivizes increased costs without promoting efficiency or cost control.

87
Q

GSA is authorized by 40 U.S.C.501 to contract for utility services for periods not exceeding ___ years.
10
5
15
25
FAR 41.103(a)

A

D. 25

Explanation:
Under FAR 41.103(a) and 40 U.S.C. 501, the General Services Administration (GSA) is authorized to contract for utility services for periods not exceeding 25 years. This extended contract period allows for stability and long-term planning in managing government utility needs, such as electricity, water, and natural gas.

88
Q

When applying an alternate to FAR 52.215-2 or FAR 52.215-5 the determination and findings in Foreign Acquisitions must identify the contract and its purpose, and identify if the contract is with a foreign contractor or with a foreign government or an agency of a foreign government; describe the efforts to include the basic clause; describe the price and availability of the supplies or services from the United States and other sources; and determine that it will best serve the interest of the United States to use the appropriate alternate clause.
True
False
FAR 25.1001

A

True

Explanation:
Under FAR 25.1001, when applying an alternate to FAR 52.215-2 (Audit and Records—Negotiation) or FAR 52.215-5 (Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Products and Commercial Services) in the context of foreign acquisitions, the contracting officer must prepare a Determination and Findings (D&F).

89
Q

Assume that the CO has rejected the SBA’s recommendation to set aside an acquisition.

proceed with full and open competition.

suspend action on the acquisition.

complete a fair and reasonable price determination.

complete an SBA override signed by the next higher person in the CO’s chain of command.
FAR 19.502-8

A

B. Suspend action on the acquisition.

Explanation:
Under FAR 19.502-8, if a contracting officer (CO) rejects the Small Business Administration’s (SBA) recommendation to set aside an acquisition for small business, the SBA may appeal the decision to the head of the contracting activity (HCA). During the appeal process, the CO must suspend action on the acquisition until the appeal is resolved, unless:

The HCA determines in writing that the acquisition must proceed to protect the Government’s interests.
Urgent and compelling circumstances exist that require continuing with the acquisition.

90
Q

he contracting officer must, to the extent practicable, provide maximum participation opportunity to all of the following EXCEPT:

Veteran-owned small business
HUBZone small business
Disabled-minority-owned small business
Service-disabled veteran-owned small business
FAR 19.2

A

C. Disabled-minority-owned small business

Explanation:
Under FAR 19.2, the contracting officer must provide maximum practicable opportunities for participation in federal contracts to the following categories of small businesses:

Veteran-owned small business (VOSB)
HUBZone small business
Service-disabled veteran-owned small business (SDVOSB)
Small disadvantaged businesses (SDB), including those owned by minorities.

91
Q

Which Section of the Uniform Contract Format includes the “Evaluation factors for award?”
A
J
K
M
FAR 15.204-1

A

D. M

Explanation:
Under FAR 15.204-1, Section M of the Uniform Contract Format (UCF) is designated for “Evaluation Factors for Award”. This section outlines the criteria that will be used to evaluate proposals and make the award decision. It is critical for ensuring transparency and fairness in the procurement process.

Breakdown of Relevant Sections:
Section A: Information such as the solicitation cover page and basic details.
Section J: Attachments such as exhibits or other supporting documentation.
Section K: Representations, certifications, and other statements of offerors.
Section M: Evaluation factors for award, including technical, cost, and past performance criteria.
Key Takeaway:
The evaluation factors for award are detailed in Section M of the Uniform Contract Format (UCF), as specified in FAR 15.204-1.

92
Q

Which of the following should not be considered in deciding what information to obtain through an oral presentation?

The impact on the efficiency of the acquisition.
The impact (including cost) on small business.
The government’s ability to adequately evaluate the information.
The need to revise the offeror’s proposal.
FAR 15.102(c)

A

The need to revise the offeror’s proposal.

93
Q

The Federal Supply Schedule Program is also known as the:
Central Contractor Registry (CCR)
E-Buy Program
Source-Supply List (SSL)
Multiple Award Schedule Program
FAR 8.402

A

D. Multiple Award Schedule Program

Explanation:
The Federal Supply Schedule (FSS) Program, as referenced in FAR 8.402, is also known as the Multiple Award Schedule (MAS) Program. This program allows federal agencies to purchase commercial products and services from pre-approved vendors at negotiated prices, streamlining the procurement process and promoting efficiency.

94
Q

A Department of Commerce regulation in support of approved national defense, emergency preparedness, and energy programs is known as the_____________________.

Defense Priorities and Allocation System.
DOC Emergency Authorization System.
Approved program.
Defense Authorization Act.
FAR 11.600

A

A. Defense Priorities and Allocation System (DPAS).

Explanation:
Under FAR 11.600, the Defense Priorities and Allocation System (DPAS) is a Department of Commerce regulation that supports approved national defense, emergency preparedness, and energy programs. It allows the prioritization of contracts and orders necessary to meet national defense requirements, ensuring timely delivery of critical goods and services.

DPAS is implemented under the authority of the Defense Production Act and is designed to support federal priorities in times of emergency or national defense needs.

95
Q

o meet the implied warranty of merchantability, the commercial items acquired by the government must be ______________.
manufactured to the highest commercial standards.

of at least average, fair, or medium-grade quality.
factory seconds if they are available.
of at least AAA+ or very high quality.
FAR 12.404

A

of at least average, fair, or medium-grade quality.

96
Q

Prohibition on a ByteDance Covered Application includes the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited. This prohibition applies to the presence or use of a covered application on any information technology owned or managed by______, or on any information technology used or provided by the _______ under a contract, unless an exception is granted.

the Government, Contractor
the Contractor, Vendor
the Vendor, Government
the Government, Government
FAR 4.2202 (b)

A

A. the Government, Contractor

Explanation:
According to FAR 4.2202(b), the prohibition on a ByteDance Covered Application, such as TikTok, applies to:

Any information technology owned or managed by the Government.
Any information technology used or provided by the contractor under a federal contract, unless an exception is granted.
This prohibition ensures that no covered application is present on IT systems connected to federal operations, safeguarding against potential cybersecurity risks.

Key Takeaway:
The prohibition applies to information technology owned or managed by the Government and IT used or provided by the Contractor under a federal contract, as stated in FAR 4.2202(b).

97
Q

An agency must transmit a notice of proposed contract action to the governmentwide point of entry at least 15 days before issuance of a solicitation, or a proposed contract action the Government intends to solicit and negotiate with only one source under the authority of FAR 6.302, except that, for acquisitions of commercial products or commercial services:

The Contracting Officer must transmit the notice at least 40 days before issuance of a solicitation if the acquisition is covered by the World Trade Organization Government Procurement Agreement or a Free Trade Agreement.

The Contracting Officer may establish a shorter period for issuance of the solicitation if the estimated amount of the contract action is less than the simplified acquisition threshold

The Contracting Officer transmits the notice only if subcontracting opportunities exist.

The Contracting Officer may use the combined synopsis and solicitation procedure.
FAR 5.203.

A

D. The Contracting Officer may use the combined synopsis and solicitation procedure.

Explanation:
Under FAR 5.203, contracting officers are generally required to transmit a notice of proposed contract actions to the governmentwide point of entry (GPE) at least 15 days before issuing a solicitation or negotiating with only one source. However, for acquisitions of commercial products or commercial services, contracting officers may streamline the process by using the combined synopsis and solicitation procedure described in FAR 12.603. This allows the contracting officer to issue a single document for both the synopsis and the solicitation.

98
Q

The justification for other than full and open competition for a proposed contract over $750,000 but not exceeding $15 million shall be approved in writing by:

The head of contracting activity.
The advocate for competition for the procuring activity.
The contracting officer.
One level above the contracting officer.
FAR 6.304(a)(2).

A

. One level above the contracting officer.

Explanation:
Under FAR 6.304(a)(2), the justification for other than full and open competition for a proposed contract exceeding $750,000 but not exceeding $15 million must be approved in writing by an official one level above the contracting officer. This requirement ensures additional oversight and accountability for justifications at this dollar range.

Analysis of Other Options:
The head of contracting activity: Incorrect. This official approves justifications for proposed contracts exceeding $15 million but not exceeding $75 million, as stated in FAR 6.304(a)(3).
The advocate for competition for the procuring activity: Incorrect. The advocate for competition is responsible for promoting competition but does not approve justifications.
The contracting officer: Incorrect. The contracting officer may only approve justifications for contracts not exceeding $750,000, as per FAR 6.304(a)(1).
One level above the contracting officer: Correct. This is the approval authority for justifications for contracts over $750,000 but not exceeding $15 million, per FAR 6.304(a)

99
Q

What is a covered employee?

Covered employee means an individual who performs an acquisition function and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; and subcontractors that are self-employed individuals treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor employee of the contractor who performs an acquisition function closely associated with inherently governmental functions .
FAR 3.11

A

C. Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Explanation:
According to FAR 3.1101, a covered employee is defined as:

An individual who performs an acquisition function closely associated with inherently governmental functions, and
Is:
An employee of the contractor, or
A self-employed subcontractor treated as a covered employee because there is no employer to whom such an individual could submit required disclosures.
This definition ensures that individuals who perform acquisition-related tasks, which are critical to the government’s functions, comply with ethical standards and reporting requirements.

100
Q

An Independent Government Estimate of construction costs shall be prepared and furnished to the Contracting officer for each proposed contract and contract modification anticipated to exceed:
$100,000
$1,000,000
$150,000
$500,000
FAR 36.203(a)

A

$150,000

101
Q

Which of the following is not true in the acquisition of information technology?

“Modular contracting” means use of one or more contracts to acquire information technology systems in successive, interoperable increments

“National security system” means any telecommunications or information system operated by the United States Government

rior to entering into a contract for information technology, an agency should analyze risks, benefits, and costs.

When acquiring information technology services, solicitations must describe any minimum experience or educational requirement for proposed contractor personnel.
FAR 39.104

A

When acquiring information technology services, solicitations must describe any minimum experience or educational requirement for proposed contractor personnel.

102
Q

Who can authorize continued performance in the face of a protest after award?

The head of the contracting activity.
The commanding officer.
The chief of the contracting office.
The contracting officer provided his findings are documented in the file.
FAR 33.1

A

The head of the contracting activity.

103
Q

A contractor may assign monies due or to become due under a government order/contract only when the contract value totals _________ or more.
$25,000
$1,000
$100
$500
FAR 32.802

A

$1,000

104
Q

Rights of the government to use, disclose, reproduce, prepare derivative works, distribute copies to the public, and perform publicly and display publicly, in any manner and for any purpose, and to have or permit others to do so.

Unrestricted rights
Restricted rights
Unlimited rights
Limited rights
FAR 27.401

A

Unlimited rights

105
Q

Factors for determining whether a cost is allowable include all of the following except:

Terms of the contract
Allocability
Reasonableness
Total price
FAR 31.201-2

A

Total price

106
Q

he Contracting Officer shall not award a CAS-covered contract until the _____________ has made a written determination that the required disclosure statement is adequate.

Program Manager
Agency Head
Cognizant Federal Agency Official
Contracting Activity
FAR 30.202-6

A

Cognizant Federal Agency Official

107
Q

Who is responsible for performing CAS administration for all contracts and subcontracts in a business unit?

Cognizant Federal Agency Official
Contracting Officer
Head of Contracting Agency
Head of Agency
FAR 30.601

A

Cognizant Federal Agency Official

108
Q

Solicitations to perform contracts or contract modifications that are expected to exceed ___________ ($1M for construction) for which subcontracting possibilities exist, require the apparent successful offeror/bidder to submit an acceptable subcontracting plan prior to award.
$700,000
$500,000
$750,000
$600,000
FAR 19.702

A

$750,000

109
Q

The Service Contract Labor Standards includes which of the following statutory exceptions where it does not apply.

Any contract for janitorial services.
Any contract for nonseverable services.
Any contract for severable services.
Any contract for public utility services.
FAR 22.1003-3 and 22.604

A

Any contract for public utility services.

110
Q

mprest Funds are used for cash purchases below what level?
$1,000
$500
$2,500
$750
FAR 13.305

A

$500

111
Q

A post-award debriefing should ideally occur within ____ days after receipt of the written request for a debriefing by the offeror.
7
3
5
10
FAR 15.506

A

5

112
Q

_______________ is an online shopping service through which ordering activities may search specific information (national stock number, part number, common name), review delivery options and place orders directly with schedule contractors.

E-Buy
SAM.gov
GSA Advantage!
Federal Supply Schedule (FSS)
FAR 8.402

A

GSA Advantage!

113
Q

Which authority permitting other than full and open competition may be used when none of the other authorities in FAR 6.302 apply?

International agreement.
National security
Public interest.
Unusual and compelling urgency.
FAR 6.302-7(b).

A

Public interest.

114
Q

Which instrument is indicated by the letter designation A, in position 9 of the PIID?
Basic ordering agreements.
Basic purchasing agreements
Blanket ordering agreements
Blanket purchase agreements
FAR 4.1603(3)

A

Blanket purchase agreements

115
Q

Prohibition on a ByteDance Covered Application includes the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited. This prohibition applies to the presence or use of a covered application on any information technology owned or managed by______, or on any information technology used or provided by the _______ under a contract, unless an exception is granted.

the Government, Contractor
the Contractor, Vendor
the Vendor, Government
the Government, Government
FAR 4.2202 (b)

A

the Government, Contractor

116
Q

Governmentwide point of entry (GPE)Â means the single point where Government business opportunities greater than ___________, including synopses of proposed contract actions, solicitations, and associated information, can be accessed electronically by the public.
35000
20000
35000
25000
FAR 2.101

A

25000

117
Q

Which of the following is correct about the FAR citation 15.506(a) ______________________.

15 is the part, 5 is the subpart, 06 is the section, and a is the paragraph.
1 is the part, 5 is the subpart, 506 is the section, and a is the paragraph.
15 is the part, 5 is the subpart, 06 is the paragraph, and a is the sentence.
15 is the part, 50 is the subpart, 6 is the section, and a is the paragraph.
FAR 1.105-2

A

15 is the part, 5 is the subpart, 06 is the section, and a is the paragraph.

118
Q

The FAR is prepared, issued, and maintained by:

The Executive Office of the President.

The Office of Management and Budget and the General Services Administration.

The National Contract Management Association.

The Secretary of Defense, the Administrator of General Services, and the Administrator of the National Aeronautics and Space Administration.
FAR 1.103

A

The Secretary of Defense, the Administrator of General Services, and the Administrator of the National Aeronautics and Space Administration.

119
Q

The Contracts Dispute Act of 1978 states contractors shall provide certification as specified in FAR 33.
$100,000
$15,000
$65,000
$150,000
FAR 33.207(a)

A

D. $150,000

Explanation:
Under the Contract Disputes Act of 1978, as implemented in FAR 33.207(a), contractors are required to certify claims when the total amount of the claim exceeds $100,000. However, this threshold has been adjusted for inflation, and the current certification requirement applies to claims exceeding $150,000.

Certification Requirements:
The certification must state that:

The claim is made in good faith.
The supporting data are accurate and complete to the best of the contractor’s knowledge.
The amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.
The certifier is authorized to certify the claim on behalf of the contractor.

120
Q

To which of the following subcontracts may a contracting officer consent?

A subcontract that makes the results of arbitration between the prime contractor and subcontractor binding on the Government
A subcontract obligating the contracting officer to deal directly with the subcontractor
A subcontract providing for payment on a ?fixed-price incentive basis
A subcontract providing for payment on a cost-plus-a-percentage-of-cost basis
FAR 44.203(b)

A

The correct answer is:

C. A subcontract providing for payment on a fixed-price incentive basis

Explanation:
Under FAR 44.203(b), a contracting officer may consent to certain types of subcontracts while adhering to the policies and standards for subcontracting. However, the following subcontracts are prohibited or would create unacceptable risks:

A subcontract that makes the results of arbitration between the prime contractor and subcontractor binding on the Government: Not permitted. This type of subcontract improperly binds the Government to arbitration outcomes in which it has no participation.
A subcontract obligating the contracting officer to deal directly with the subcontractor: Not permitted. The Government’s contractual relationship is solely with the prime contractor, not with subcontractors.
A subcontract providing for payment on a fixed-price incentive basis: Permitted. Fixed-price incentive contracts are an acceptable contract type under FAR and may be used in subcontracts, provided the contracting officer consents if required.
A subcontract providing for payment on a cost-plus-a-percentage-of-cost basis: Not permitted. This type of payment arrangement is explicitly prohibited under FAR 16.102(c) because it incentivizes increased costs without promoting efficiency.

121
Q

Which Act provides for minimum wages and fringe benefits as well as other conditions of work?
Davis-Bacon Act
Walsh-Healy Act
Equal Opportunity Act
Service Contract Act
FAR 37.107

A

D. Service Contract Act

Explanation:
The Service Contract Act (SCA), formally known as the McNamara-O’Hara Service Contract Act, requires contractors performing service contracts for the federal government to pay their employees:

Minimum wages determined by prevailing wage rates in the locality.
Fringe benefits, such as health insurance, retirement benefits, and vacation pay.
The SCA applies to contracts exceeding $2,500 and ensures fair compensation and working conditions for employees providing services under government contracts.

Analysis of Other Options:
Davis-Bacon Act: Incorrect. The Davis-Bacon Act applies to construction contracts and establishes prevailing wage rates for laborers and mechanics working on federal or federally assisted construction projects.
Walsh-Healy Act: Incorrect. The Walsh-Healy Public Contracts Act applies to supply contracts exceeding $15,000 and requires contractors to pay prevailing wages, maintain safe working conditions, and prohibit child and convict labor.
Equal Opportunity Act: Incorrect. This act prohibits discrimination in employment but does not specifically address wages or fringe benefits.
Service Contract Act: Correct. The SCA ensures minimum wages, fringe benefits, and other fair working conditions for employees performing services on federal contracts.

122
Q

The policies and procedures for trade agreements, including the World Trade Organization Government Procurement Agreement (WTO GPA), Free Trade Agreements, least developed country designation, the Caribbean Basin Trade Initiative, the Israeli Trade Act, and the Agreement on Trade in Civil Aircraft, do not apply to all the following, except:

Acquisitions set aside for small businesses.
Acquisitions under simplified acquisition procedures.
Acquisitions from the AbilityOne program.
Acquisitions of end products for resale.
FAR 25.400(a) and FAR 25.401(a).

A

. Acquisitions under simplified acquisition procedures.

Explanation:
The policies and procedures for trade agreements under FAR 25.400(a) and FAR 25.401(a) generally apply to acquisitions above specific thresholds outlined in the trade agreements. However, exceptions include:

Acquisitions set aside for small businesses: Exempt because trade agreements do not apply to set-aside acquisitions.
Acquisitions from the AbilityOne program: Exempt because AbilityOne is a mandatory source of supply under FAR 8.7, and trade agreements do not apply.
Acquisitions of end products for resale: Exempt because resale products are excluded from trade agreement requirements.

123
Q

The following are examples when special-fuels excise taxes are NOT imposed in many contracting situations when the supplies are for any of the following except:

The exclusive use of any State or political subdivision, including the District of Columbia (26 U.S.C.4041 and 4221).
A nonprofit educational organization (26 U.S.C.4041 and 4 221).
Purchases under the Ability One program. (41 U.S.C. chapter 85).
Emergency vehicles (26 U.S.C.4053 and 4 064(b)(1)(c)).
FAR 29.202

A

C. Purchases under the AbilityOne program (41 U.S.C. chapter 85).

Explanation:
According to FAR 29.202 and the referenced sections of the U.S. Tax Code, certain situations exempt contracts from special-fuels excise taxes. Examples include:

The exclusive use of any State or political subdivision, including the District of Columbia (26 U.S.C. 4041 and 4221): Exempt from excise taxes.
A nonprofit educational organization (26 U.S.C. 4041 and 4221): Exempt from excise taxes.
Emergency vehicles (26 U.S.C. 4053 and 4064(b)(1)(C)): Exempt from excise taxes.
However, purchases under the AbilityOne program are not specifically mentioned as exempt from excise taxes under FAR 29.202 or the related tax codes. While the AbilityOne program involves mandatory source requirements for certain supplies and services, it does not inherently qualify for excise tax exemptions.

124
Q

This law states laborers and mechanics must be paid time and a half for overtime work (e.g.;40 hours/week)?

Wage Rate Requirements statute
Kickbacks statute
Minimum Wage Act
Contract Work Hours and Safety Standards Act
FAR 22.403-3

A

D. Contract Work Hours and Safety Standards Act

Explanation:
The Contract Work Hours and Safety Standards Act (CWHSSA), referenced in FAR 22.403-3, requires that laborers and mechanics employed on federal contracts be paid time and a half for overtime work, defined as work exceeding 40 hours in a week. This act applies to contracts exceeding $150,000 that involve the employment of laborers and mechanics.

Analysis of Other Options:
Wage Rate Requirements statute: Incorrect. This refers to the Davis-Bacon Act, which establishes prevailing wage rates for laborers and mechanics but does not address overtime pay.
Kickbacks statute: Incorrect. The Anti-Kickback Act prohibits kickbacks from subcontractors to prime contractors or contracting officers but is unrelated to overtime or wage requirements.
Minimum Wage Act: Incorrect. While minimum wage laws establish baseline pay requirements, they do not specifically mandate overtime pay.
Contract Work Hours and Safety Standards Act: Correct. This act mandates overtime pay for laborers and mechanics on applicable federal contracts, as stated in FAR 22.403-3.

125
Q

Assume that the CO has rejected the SBA’s recommendation to set aside an acquisition.
proceed with full and open competition.

suspend action on the acquisition.
complete a fair and reasonable price determination.
complete an SBA override signed by the next higher person in the CO’s chain of command.
FAR 19.502-8

A

B. Suspend action on the acquisition.

Explanation:
Under FAR 19.502-8, if a contracting officer (CO) rejects the Small Business Administration’s (SBA) recommendation to set aside an acquisition for small business, the SBA may appeal the CO’s decision to the head of the contracting activity (HCA). During this appeal process, the CO must suspend action on the acquisition, unless:

The HCA determines in writing that proceeding with the acquisition is necessary to protect the Government’s interests.
Urgent and compelling circumstances exist that justify continuing with the acquisition.
This ensures that the SBA’s appeal is given proper consideration before moving forward.

126
Q

Agencies shall, at a minimum, acquire EPEAT® ____-registered electronic products.

platinum
gold
silver
bronze
FAR 23.704

A

C. Silver

Explanation:
Under FAR 23.704, agencies are required to acquire EPEAT® Silver-registered electronic products at a minimum. The Electronic Product Environmental Assessment Tool (EPEAT®) is a global ecolabel that certifies the environmental performance of electronic products. The Silver registration level represents a baseline standard for environmental attributes, ensuring compliance with federal sustainability goals.

Agencies are encouraged to procure higher-level (e.g., Gold or Platinum) registered products when feasible, but Silver is the mandatory minimum requirement.

Key Takeaway:
Agencies must acquire EPEAT® Silver-registered electronic products at a minimum, as required by FAR 23.704, while striving to purchase products with higher environmental performance when possible.

127
Q

___________ are written instruments of understanding that contain terms and conditions that apply to future orders, a description of supplies and services to be provided, and methods for pricing, issuing, and delivering future orders.

Indefinite-Delivery Arrangements
Blanket Purchase Agreements
Basic Ordering Agreements
Fixed-Price Contracts
FAR 16.703

A

C. Basic Ordering Agreements

Explanation:
According to FAR 16.703, a Basic Ordering Agreement (BOA) is a written instrument of understanding between a government agency and a contractor. A BOA:

Contains terms and conditions that apply to future orders.
Describes the supplies or services to be provided.
Specifies methods for pricing, issuing, and delivering future orders.
A BOA is not a contract by itself but provides a framework for issuing contracts more efficiently when specific requirements arise.

Analysis of Other Options:
Indefinite-Delivery Arrangements: Incorrect. This is not a recognized term in the FAR. Instead, the FAR discusses Indefinite-Delivery Contracts (IDCs) in Subpart 16.5.
Blanket Purchase Agreements: Incorrect. A Blanket Purchase Agreement (BPA) is similar but applies to simplified acquisition procedures under FAR Part 13. BPAs are not the same as BOAs and are used for repetitive needs for supplies or services.
Basic Ordering Agreements: Correct. BOAs are agreements defined under FAR 16.703 to streamline future orders.
Fixed-Price Contracts: Incorrect. A fixed-price contract is a fully executed contract type with fixed terms and pricing, not an instrument for future orders.

128
Q

Which of the following should not be considered in deciding what information to obtain through an oral presentation?

The impact on the efficiency of the acquisition.
The impact (including cost) on small business.
The government’s ability to adequately evaluate the information.
The need to revise the offeror’s proposal.
FAR 15.102(c)

A

D. The need to revise the offeror’s proposal.

Explanation:
Under FAR 15.102(c), the purpose of oral presentations is to streamline the evaluation process by providing the government with an efficient method to assess an offeror’s understanding of the requirements, technical approach, or other key aspects of their proposal. Factors to consider include:

The impact on the efficiency of the acquisition: Oral presentations should enhance the efficiency of the procurement process.
The impact (including cost) on small business: Consideration must be given to the resources required for small businesses to prepare and participate.
The government’s ability to adequately evaluate the information: The government must be able to effectively evaluate the information provided during the presentation.
However, oral presentations are not intended to revise or modify an offeror’s proposal. The purpose is to provide clarity, elaboration, or supplementary details—not to change the content of the submitted proposal.

129
Q

The following are exceptions to the requirement for contracting officers to make notices of proposed contract actions available through the governmentwide point of entry, except:

Competitive acquisitions under the Section 8(a) program.
Acquisitions for utility services (other than telecommunications services) and only one source is available.
Acquisitions required by a statute to be made from a specific source, such as a workshop for the blind under the rules of the Committee for Purchase from People Who Are Blind or Severely Disabled.
An order placed under FAR Subpart 16.5.
FAR 5.202 and FAR 5.205(f).

A

A. Competitive acquisitions under the Section 8(a) program.

Explanation:
Under FAR 5.202, contracting officers are generally required to make notices of proposed contract actions available through the Governmentwide Point of Entry (GPE), such as SAM.gov, unless a specific exception applies. The listed exceptions include:

Acquisitions for utility services (other than telecommunications services) and only one source is available: Exempt under FAR 5.202(a)(7) because only one source exists for the service.
Acquisitions required by a statute to be made from a specific source, such as a workshop for the blind under the rules of the Committee for Purchase from People Who Are Blind or Severely Disabled: Exempt under FAR 5.202(a)(4) because the source is mandated by law.
An order placed under FAR Subpart 16.5: Exempt under FAR 5.202(a)(11) for orders under indefinite-delivery contracts.
However, competitive acquisitions under the Section 8(a) program are not exempt from the GPE notification requirement. While sole-source awards under Section 8(a) may qualify for exceptions in some cases, competitive 8(a) acquisitions must be publicized.

130
Q

Which of the following duties is NOT a responsibility for competition advocates?

Recommend to the Contracting Officer a system of personal accountability for competition, which may include the use of recognition and awards to motivate the procurement staff.
Review the contracting operations of the agency and identify and report to the agency senior procurement executive and the chief acquisition officer.
Prepare and submit an annual report to the agency senior procurement executive and the chief acquisition officer in accordance with agency procedures.
Recommend goals and plans for increasing competition on a fiscal year basis to the agency senior procurement executive and the chief acquisition officer.
FAR 6.502

A

A. Recommend to the Contracting Officer a system of personal accountability for competition, which may include the use of recognition and awards to motivate the procurement staff.

Explanation:
Under FAR 6.502, competition advocates are responsible for promoting and increasing competition in federal contracting. Their duties include:

Reviewing the contracting operations of the agency to identify and report barriers to competition to the agency senior procurement executive and the chief acquisition officer.
Preparing and submitting annual reports on competition efforts to the agency senior procurement executive and the chief acquisition officer.
Recommending goals and plans for increasing competition on a fiscal year basis.
However, recommending a system of personal accountability or awards to the Contracting Officer is not listed as a responsibility of competition advocates in FAR 6.502.

131
Q

Who can authorize continued performance in the face of a protest after award?
The head of the contracting activity.
The commanding officer.
The chief of the contracting office.
The contracting officer provided his findings are documented in the file.
FAR 33.1

A

The head of the contracting activity.

132
Q

For a supplemental agreement, when is the effective date of a contract modification?
the date agreed upon by the contracting parties
the issue date
the date received by the contractor
the date received by the government
FAR 43.101

A

the date agreed upon by the contracting parties

133
Q

Unless more time is needed for evaluation, how many days does a contracting officer have to accept or reject a VECP proposal?

within 30 days from its receipt by the Government
within 45 days from its receipt by the Government
within 15 days from its receipt by the Government
within 25 days from its receipt by the Government
FAR 48.103

A

within 45 days from its receipt by the Government

134
Q

To which of the following subcontracts may a contracting officer consent?

A subcontract that makes the results of arbitration between the prime contractor and subcontractor binding on the Government
A subcontract obligating the contracting officer to deal directly with the subcontractor
A subcontract providing for payment on a ?fixed-price incentive basis
A subcontract providing for payment on a cost-plus-a-percentage-of-cost basis
FAR 44.203(b)

A

A subcontract providing for payment on a ?fixed-price incentive basis

135
Q

An Independent Government Estimate of construction costs shall be prepared and furnished to the Contracting officer for each proposed contract and contract modification anticipated to exceed:
$100,000
$1,000,000
$150,000
$500,000
FAR 36.203(a

A

$150,000

136
Q

Which Act provides for minimum wages and fringe benefits as well as other conditions of work?
Davis-Bacon Act
Walsh-Healy Act
Equal Opportunity Act
Service Contract Act
FAR 37.107

A

Service Contract Act

137
Q

The Contracts Dispute Act of 1978 states contractors shall provide certification as specified in FAR 33.
$100,000
$15,000
$65,000
$150,000
FAR 33.207(a)

A

$100,000

138
Q

Which of the following is not a type of surety?
Co-surety
Individual
Corporate
Multiple
FAR 28.001

A

Multiple

139
Q

Service Contracts valued in excess of ___________ must contain mandatory provisions regarding minimum wage and fringe benefits, safe and sanitary working conditions, notification to employees of the minimum allowable compensation, and equivalent Federal employee classifications and wage rates.
$2,000
$1,000
$1,500
$2,500
FAR 22.1002-1

A

$2,500

140
Q

A post-award debriefing should ideally occur within ____ days after receipt of the written request for a debriefing by the offeror.
7
3
5
10
FAR 15.506

A

5

141
Q

Imprest Funds are used for cash purchases below what level?
$1,000
$500
$2,500
$750
FAR 13.305

A

$500

142
Q

In the elements of a PIID, positions 7 through 8 are the last two digits of the fiscal year in which the procurement instrument is issued or awarded. What do these digits refer to?

The date the action is signed, rather than the effective date
The date the effective date was awarded, rather than signed
The date the action was drafted, rather than the effective date
The date the effective date was signed, rather than the date the action was signed
FAR 4.1603(2)

A

The date the action is signed, rather than the effective date

143
Q

Unless otherwise excepted, the Contracting Officer must transmit a notice of proposed contract action to the governmentwide point of entry for each of the following situations, except:

Proposed contract action in an estimated amount of $30,000.

Proposed modification to an existing contract for additional supplies or services outside the existing contract scope in an estimated amount of $30,000.

Proposed contract termination for the convenience of the Government in an estimated amount of $30,000.

Proposed contract action in an estimated amount of $20,000, if the notice is advantageous to the Government.
FAR 5.201

A

Proposed contract termination for the convenience of the Government in an estimated amount of $30,000.

144
Q

When might contracting offices request exceptions to standard forms?
Overprinting forms
Computer generated forms
Special construction and printing forms
Continuation sheets
FAR 53.106

A

pecial construction and printing forms

Explanation:
According to FAR 53.106, contracting offices may request exceptions to standard forms for special construction and printing, where the standard forms do not meet the unique needs of the office. Other scenarios such as overprinting, computer-generated forms, and continuation sheets are more likely adaptations or modifications allowed for existing forms rather than reasons for requesting exceptions.

145
Q

Where can you make a recommendation for a new form if you are not affiliated with an executive agency?
Government Accountability Office
General Services Administration
the FAR Secretariat
Recommendations are not permitted
FAR 53.108

A

he FAR Secretariat

Explanation:
According to FAR 53.108, individuals or organizations not affiliated with an executive agency can submit recommendations for new forms to the FAR Secretariat. The FAR Secretariat is responsible for managing the Federal Acquisition Regulation and serves as the appropriate entity to receive suggestions for new forms or changes to existing ones.

146
Q

Contract items are technically classified as-

complex and non-complex
critical and non-critical
commercial and military-federal
supply or service
FAR 46.203

A

ritical and non-critical

Explanation:
According to FAR 46.203, contract items are technically classified as critical or non-critical. This classification is based on the significance of the item to the mission or end-use, as well as the consequences of a failure. Critical items are those that could cause serious consequences if they fail, while non-critical items are less significant in terms of potential failure impacts.

The other options do not reflect the technical classification as stated in the FAR:

Complex and non-complex: This is not a FAR classification.
Commercial and military-federal: These terms relate to procurement categories, not technical classifications.
Supply or service: This refers to types of contracts, not item classification.

147
Q

he ___________________ is responsible for conducting reviews of Disclosure Statements to ascertain whether it is current, accurate, and complete.
Acquiring Agency
Cognizant Federal Agency Official
Cognizant Auditor
Cognizant Officer
FAR 30.202-7

A

Cognizant Auditor

Explanation:
According to FAR 30.202-7, the Cognizant Auditor is responsible for conducting reviews of Disclosure Statements to determine whether they are current, accurate, and complete. The Cognizant Auditor plays a key role in ensuring compliance with cost accounting standards and verifying the adequacy of the Disclosure Statements.

Why not the other options?
Acquiring Agency: While the acquiring agency is involved in procurement, it does not perform the detailed review of Disclosure Statements.
Cognizant Federal Agency Official: This role involves oversight and coordination but does not include the technical responsibility of reviewing Disclosure Statements.
Cognizant Officer: This is not a specific r

148
Q

All contracts subject to 41 U
$250,000
$2,500
$10,000
$15,000
FAR 22.6

A

$2,500

Explanation:
According to FAR 22.6, which addresses the Service Contract Labor Standards (formerly the Service Contract Act), the Act applies to contracts over $2,500 for services performed in the United States using service employees. Contracts below this threshold are not subject to the provisions of the Service Contract Labor Standards.

149
Q

____________ are written instruments of understanding that contain terms and conditions that apply to future orders, a description of supplies and services to be provided, and methods for pricing, issuing, and delivering future orders.
Indefinite-Delivery Arrangements
Blanket Purchase Agreements
Basic Ordering Agreements
Fixed-Price Contracts
FAR 16.703

A

asic Ordering Agreements

Explanation:
According to FAR 16.703, Basic Ordering Agreements (BOAs) are written instruments of understanding that include terms and conditions applicable to future orders. They describe the supplies or services to be provided and methods for pricing, issuing, and delivering future orders. However, a BOA itself is not a contract; it requires the issuance of orders for any binding agreement.

Why not the other options?
Indefinite-Delivery Arrangements: This is a general category for contract types like indefinite-quantity contracts, but it is not the specific instrument described in FAR 16.703.
Blanket Purchase Agreements: While BPAs also facilitate simplified acquisitions, they are governed under FAR 13.303, not FAR 16.703, and do not include all the specific details outlined in a BOA.
Fixed-Price Contracts: These are a type of contract where pricing terms are established but do not inherently describe mechanisms for future orders.

150
Q

Which of the following contract types puts the most risk on the buyer?
Cost Plus Fixed Fee
Time & Material
Firm Fixed Price
Fixed-Price with Incentive Fee
FAR 16.101

A

Time & Material

Explanation:
Among the listed options, Time & Material (T&M) contracts put the most risk on the buyer. In a T&M contract, the buyer agrees to pay for the contractor’s actual labor hours at predetermined rates, as well as the cost of materials. This structure places significant risk on the buyer because the total cost is not fixed and depends on the time and materials required, which can lead to cost overruns.

Why not the other options?
Cost Plus Fixed Fee (CPFF): The buyer assumes substantial risk because they reimburse all allowable costs, plus a fixed fee. However, this type of contract is less risky for the buyer than T&M because costs are controlled through limitations and close monitoring.
Firm Fixed Price (FFP): This type puts the least risk on the buyer, as the contractor agrees to deliver the required work for a fixed price. Any cost overruns are borne by the contractor.
Fixed-Price with Incentive Fee (FPIF): The buyer assumes some risk, but it is shared with the contractor through incentives to control costs and meet performance goals. The risk is still lower than in a T&M contract.

151
Q

The Federal Supply Schedule Program is also known as the:
Central Contractor Registry (CCR)
E-Buy Program
Source-Supply List (SSL)
Multiple Award Schedule Program
FAR 8.402

A

Multiple Award Schedule Program

Explanation:
According to FAR 8.402, the Federal Supply Schedule Program is commonly referred to as the Multiple Award Schedule (MAS) Program. This program provides federal agencies with a simplified process for acquiring commercial products and services at pre-negotiated prices and terms.

Why not the other options?
Central Contractor Registry (CCR): The CCR was a system for contractor registration, but it is now part of the System for Award Management (SAM) and unrelated to the Federal Supply Schedule Program.
E-Buy Program: E-Buy is an online procurement tool associated with the Federal Supply Schedule, but it is not the name of the program itself.
Source-Supply List (SSL): This is not a recognized term in the FAR related to the Federal Supply Schedule Program.

152
Q

The justification for other than full and open competition for a proposed contract over $750,000 but not exceeding $15 million shall be approved in writing by:
The head of contracting activity.
The advocate for competition for the procuring activity.
The contracting officer.
One level above the contracting officer.
FAR 6.304(a)(2).

A

he advocate for competition for the procuring activity.

Explanation:
According to FAR 6.304(a)(2), the justification for other than full and open competition for a proposed contract over $750,000 but not exceeding $15 million must be approved in writing by the advocate for competition for the procuring activity or a similar designated official.

Why not the other options?
The head of contracting activity: This official is required for contracts exceeding $15 million but not exceeding $75 million.
The contracting officer: The contracting officer approves justifications for contracts up to $750,000, not above this threshold.
One level above the contracting officer: This is not specified as the approving authority in the context of justifications for other than full and open competition.

153
Q

Which of the following is not true in the acquisition of information technology?

“Modular contracting” means use of one or more contracts to acquire information technology systems in successive, interoperable increments
“National security system” means any telecommunications or information system operated by the United States Government
Prior to entering into a contract for information technology, an agency should analyze risks, benefits, and costs.
When acquiring information technology services, solicitations must describe any minimum experience or educational requirement for proposed contractor personnel.
FAR 39.104

A

When acquiring information technology services, solicitations must describe any minimum experience or educational requirement for proposed contractor personnel.

154
Q

When there is a contract dispute, the __________ __________ ________ refers to any procedure or combination of procedures voluntarily used to resolve issues in controversy.

Alternative Dispute Resolution
Allowance Dispute Resolution
Allowance Deduction Refund
Alternative Discourse Reflection
FAR 33.201

A

Alternative Dispute Resolution

155
Q

What is a payment for accepted supplies or services, including payments for accepted partial deliveries?

Delivery payments
Final/partial acceptance
Commercial payments
Progress payments
FAR 32.001

A

Delivery payments

156
Q

The Contracts Dispute Act of 1978 states contractors shall provide certification as specified in FAR 33.
$100,000
$15,000
$65,000
$150,000
FAR 33.207(a)

A

$100,000

157
Q

Which of the following is not a type of surety?
Co-surety
Individual
Corporate
Multiple
FAR 28.001

A

Multiple

158
Q

The Bonds statute requires performance and payment bonds for any construction contract valued in excess of _________?
$150,000
$650,000
$1,000,000
$2000
FAR 28.102-1(a)

A

$150,000

159
Q

What does FEMP stand for?

Federal Energy Management Program
Federal Energy Management Products
Federal Environment Management Program
Federal Environment Management Products
FAR 23.103

A

Federal Energy Management Program

160
Q

mprest Funds are used for cash purchases below what level?
$1,000
$500
$2,500
$750
FAR 13.305

A

$500

161
Q

The Federal Supply Schedule Program is also known as the:

Central Contractor Registry (CCR)
E-Buy Program
Source-Supply List (SSL)
Multiple Award Schedule Program
FAR 8.402

A

Multiple Award Schedule Program

162
Q

When must contracting officers synopsize contract awards?
When contract awards exceed $25,000
When contract awards exceed $15,000
When contract awards exceed $30,000
When contract awards exceed $20,000
FAR 5.3

A

When contract awards exceed $25,000

163
Q

rohibition on a ByteDance Covered Application includes the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited. This prohibition applies to the presence or use of a covered application on any information technology owned or managed by______, or on any information technology used or provided by the _______ under a contract, unless an exception is granted.

the Government, Contractor
the Contractor, Vendor
the Vendor, Government
the Government, Government
FAR 4.2202 (b)

A

the Government, Contractor

164
Q

Which instrument is indicated by the letter designation A, in position 9 of the PIID?
Basic ordering agreements.
Basic purchasing agreements
Blanket ordering agreements
Blanket purchase agreements
FAR 4.1603(3)

A

Blanket purchase agreements

165
Q

he justification for other than full and open competition for a proposed contract over $750,000 but not exceeding $15 million shall be approved in writing by:
The head of contracting activity.
The advocate for competition for the procuring activity.
The contracting officer.
One level above the contracting officer.
FAR 6.304(a)(2).

A

One level above the contracting officer.

Explanation:
According to FAR 6.304(a)(2), the justification for other than full and open competition for a proposed contract over $750,000 but not exceeding $15 million must be approved in writing by one level above the contracting officer. This ensures a higher level of oversight for such justifications.

Why not the other options?
The head of contracting activity: This official is required for contracts exceeding $15 million but not exceeding $75 million (FAR 6.304(a)(3)).
The advocate for competition for the procuring activity: This role is not specified for approving justifications within the $750,000 to $15 million range.
The contracting officer: This official approves justifications for contracts not exceeding $750,000 (FAR 6.304(a)(1)).

166
Q

What criteria is not a valid consideration to make an award based on other than full and open competition?
Demonstration of unique capability specific to the services proposed.
Resembles the substance of a competitive acquisition.
Substantial duplication of cost unrecoverable through competition.
Schedule impact causing unacceptable delays.
FAR 6.3

A

Resembles the substance of a competitive acquisition.

Explanation:
According to FAR 6.3, justifications for using other than full and open competition must meet specific criteria outlined in FAR 6.302. Valid considerations include:

Demonstration of unique capability specific to the services proposed (FAR 6.302-1): This applies when only one responsible source can provide the services due to unique capabilities.
Substantial duplication of cost unrecoverable through competition (FAR 6.302-2): This criterion applies if competition would result in unrecoverable and significant duplication of costs.
Schedule impact causing unacceptable delays (FAR 6.302-2): This criterion applies when urgency or schedule delays would severely affect the agency.

167
Q

A prospective contractor would be obligated to register in the System for Award Management database prior to contract award in which of the following cases?
A contract awarded by a deployed contracting officer in the course of military operations
A micropurchase using the electronic funds transfer method for payment
A contract with an individual for performance outside the United States and its outlying areas
A contract for emergency operations in response to a natural disaster
FAR 4.1102

A

A micropurchase using the electronic funds transfer method for payment

Explanation:
According to FAR 4.1102, prospective contractors are generally required to be registered in the System for Award Management (SAM) database prior to award, with some exceptions. For a micropurchase using the electronic funds transfer (EFT) method, registration in SAM is required because EFT payment details are typically recorded in SAM.

Why not the other options?
A contract awarded by a deployed contracting officer in the course of military operations: This is an exception where SAM registration is not required, as provided under FAR 4.1102(a)(4).
A contract with an individual for performance outside the United States and its outlying areas: FAR 4.1102(a)(3) exempts contracts performed outside the United States and its outlying areas if SAM registration is impractical.
A contract for emergency operations in response to a natural disaster: FAR 4.1102(a)(5) provides an exemption for contracts supporting emergency operations, including those responding to natural disasters.

168
Q

What is a covered employee?
Covered employee means an individual who performs an acquisition function and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.
Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; and subcontractors that are self-employed individuals treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.
Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.
Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor employee of the contractor who performs an acquisition function closely associated with inherently governmental functions .
FAR 3.11

A

Covered employee means an individual who performs an acquisition function closely associated with inherently governmental functions and is an employee of the contractor; or a subcontractor that is a self-employed individual treated as a covered employee of the contractor because there is no employer to whom such an individual could submit the required disclosures.

Explanation:
According to FAR 3.11, a “covered employee” is defined as an individual who performs acquisition functions closely associated with inherently governmental functions. This includes employees of contractors and self-employed subcontractors when there is no other employer to whom such an individual could submit the required disclosures.

This definition emphasizes the relationship between the individual’s role (performing acquisition functions) and their employment status, ensuring they are subject to disclosure and oversight requirements.

169
Q

If it is in the Government’s interest, and if supplies or services required in the performance of a Government contract are available from Government supply sources, contracting officers may authorize contractors to use these sources in performing:
A contract using Federal Prison Industries.
Government-wide Acquisition Contracts (GWACS)
Federal Supply Schedules
A contract under the “AbilityOne” Program
FAR 51.101

A

Federal Supply Schedules

Explanation:
According to FAR 51.101, contracting officers may authorize contractors to use Federal Supply Schedules (also referred to as the General Services Administration (GSA) schedules) when it is in the Government’s interest and the supplies or services are required to perform a government contract. Federal Supply Schedules provide contractors access to pre-negotiated pricing and terms for commercial products and services.

Why not the other options?
A contract using Federal Prison Industries: Federal Prison Industries (FPI) provides products and services to the government, but contractors are not typically authorized to use FPI supply sources.
Government-wide Acquisition Contracts (GWACs): GWACs are contracts for acquiring IT services and solutions, but this is not what FAR 51.101 addresses.
A contract under the “AbilityOne” Program: The AbilityOne Program is designed to provide employment for people with disabilities through nonprofit agencies, and it does not typically authorize contractors to use government supply sources.

170
Q

Contract items are technically classified as-
complex and non-complex
critical and non-critical
commercial and military-federal
supply or service
FAR 46.203

A

Critical and non-critical

Explanation:
According to FAR 46.203, contract items are technically classified as critical or non-critical. This classification is based on the item’s importance to the mission or end-use and the potential consequences of failure. Critical items are those where a failure could result in severe consequences, while non-critical items are less significant in terms of their impact.

Why not the other options?
Complex and non-complex: While items might be described this way informally, it is not a classification used in FAR 46.203.
Commercial and military-federal: These terms relate more to procurement categories and are not the technical classifications referenced in FAR 46.203.
Supply or service: This refers to the type of contract, not the technical classification of items.

171
Q

GSA is authorized by 40 U.S.C.501 to contract for utility services for periods not exceeding ___ years.
10
5
15
25
FAR 41.103(a)

A

10

Explanation:
According to FAR 41.103(a), the General Services Administration (GSA) is authorized under 40 U.S.C. 501 to contract for utility services for periods not exceeding 10 years. This authority is specific to utility services and allows for long-term planning and cost management in government utility contracts.

Let me know if you need further clarificati

172
Q

This law provides that federal contracts in excess of $2,000 to which the United States or the District of Columbia is a party for construction, alteration, or repair (including painting and decorating) of public buildings or public works within the United States, shall contain a clause that no laborer or mechanic employed directly upon the site of the work shall receive less than the prevailing wage rates as determined by the Secretary of Labor.
Wage Rate Requirements (Construction)
Contract Work Hours and Safety Standards Act
Minimum Wage Act
Kickbacks statute
FAR 22.404-1(b)

A

Wage Rate Requirements (Construction)

Explanation:
The Wage Rate Requirements (Construction), commonly referred to as the Davis-Bacon Act, stipulates that federal contracts in excess of $2,000 for the construction, alteration, or repair of public buildings or public works must include a clause requiring contractors to pay laborers and mechanics no less than the prevailing wage rates as determined by the Secretary of Labor. This requirement ensures fair wages based on local standards.

Why not the other options?
Contract Work Hours and Safety Standards Act: This act addresses overtime pay and safety standards, not prevailing wage rates.
Minimum Wage Act: While this act mandates minimum wages, it does not specifically apply to prevailing wages on federally funded construction contracts.
Kickbacks statute: This statute relates to prohibiting kickbacks and does not address wage requirements.

173
Q

Assume that the CO has rejected the SBA’s recommendation to set aside an acquisition.
proceed with full and open competition.
suspend action on the acquisition.
complete a fair and reasonable price determination.
complete an SBA override signed by the next higher person in the CO’s chain of command.
FAR 19.502-8

A

Suspend action on the acquisition.

Explanation:
According to FAR 19.502-8, if a contracting officer (CO) rejects the Small Business Administration (SBA)’s recommendation to set aside an acquisition, the CO must notify the SBA of the rejection in writing. At that point, the SBA can appeal the decision to the head of the contracting activity (HCA). During this appeal process, the contracting officer is required to suspend action on the acquisition until the issue is resolved or the appeal is denied.

Why not the other options?
Proceed with full and open competition: This cannot occur until the SBA’s appeal process is complete.
Complete a fair and reasonable price determination: While important, this is unrelated to the process of handling the SBA’s recommendations and appeals.
Complete an SBA override signed by the next higher person in the CO’s chain of command: This is not a recognized step in FAR 19.502-8.

174
Q

Some acceptable contents of a subcontracting plan include the following.
A description of the method used to develop the subcontracting goals.
The description of the method used to identify potential sources for solicitation purposes.
A statement of the total dollars planned to be subcontracted.
Assurances that the offeror will include the clause at 52.219-6.
FAR 19.704

A

Assurances that the offeror will include the clause at 52.219-6.

Explanation:
According to FAR 19.704, an acceptable subcontracting plan must include various elements, and one of them is assurances that the offeror will include the clause at 52.219-6 (Notice of Total Small Business Set-Aside) in all subcontracts that offer further subcontracting opportunities. This ensures that small businesses have opportunities to participate in subcontracting.

Why are the other options correct but less complete for this question?
A description of the method used to develop the subcontracting goals: This is a valid part of a subcontracting plan under FAR 19.704(a)(3).
The description of the method used to identify potential sources for solicitation purposes: This is also a valid requirement under FAR 19.704(a)(4).
A statement of the total dollars planned to be subcontracted: This is part of the subcontracting plan under FAR 19.704(a)(1).

175
Q

This law states laborers and mechanics must be paid time and a half for overtime work (e.g.;40 hours/week)?
Wage Rate Requirements statute
Kickbacks statute
Minimum Wage Act
Contract Work Hours and Safety Standards Act
FAR 22.403-3

A

Contract Work Hours and Safety Standards Act

Explanation:
The Contract Work Hours and Safety Standards Act (CWHSSA) requires that laborers and mechanics employed on federal contracts must be paid time and a half for overtime work, defined as hours worked in excess of 40 hours in a workweek. This law applies to certain federal contracts exceeding $100,000 and ensures fair compensation for overtime.

Why not the other options?
Wage Rate Requirements statute: This (Davis-Bacon Act) pertains to prevailing wage rates for construction projects, not overtime pay.
Kickbacks statute: This addresses prohibiting kickbacks on public contracts, not labor hours or overtime.
Minimum Wage Act: This ensures a minimum wage is paid but does not address overtime specifically.

176
Q

___________ are written instruments of understanding that contain terms and conditions that apply to future orders, a description of supplies and services to be provided, and methods for pricing, issuing, and delivering future orders.
Indefinite-Delivery Arrangements
Blanket Purchase Agreements
Basic Ordering Agreements
Fixed-Price Contracts
FAR 16.703

A

Basic Ordering Agreements

Explanation:
According to FAR 16.703, Basic Ordering Agreements (BOAs) are written instruments of understanding that contain terms and conditions applicable to future orders. BOAs outline the supplies or services to be provided and establish methods for pricing, issuing, and delivering future orders. However, a BOA itself is not a contract; it becomes binding only when specific orders are issued under it.

Why not the other options?
Indefinite-Delivery Arrangements: While these contracts are used for ongoing needs, they are not specifically defined as instruments of understanding under FAR 16.703.
Blanket Purchase Agreements (BPAs): BPAs, covered under FAR 13.303, are similar but used for simplified acquisitions and governed by different rules than BOAs.
Fixed-Price Contracts: These are binding contracts with fixed pricing terms and are not designed for establishing future orders.

177
Q

__________ is an online shopping service through which ordering activities may search specific information (national stock number, part number, common name), review delivery options and place orders directly with schedule contractors.
E-Buy
SAM.gov
GSA Advantage!
Federal Supply Schedule (FSS)
FAR 8.402

A

GSA Advantage!

Explanation:
GSA Advantage! is an online shopping service provided by the General Services Administration (GSA) that allows federal ordering activities to search for specific items (e.g., national stock numbers, part numbers, or common names), review delivery options, and place orders directly with schedule contractors. It is a key tool for purchasing items available under the Federal Supply Schedule.

Why not the other options?
E-Buy: This is a separate online procurement tool for requesting and submitting quotes for services and products under the Federal Supply Schedule but is not primarily a shopping service.
SAM.gov: This is a centralized system for managing government procurement data and contractor registrations but does not serve as an online shopping platform.
Federal Supply Schedule (FSS): This refers to the overarching program that provides access to pre-negotiated contracts but does not describe the online shopping service itself.

178
Q
A