Contract Practice Flashcards
Dangers of inaccurate damages
May be construed as a penalty.
They are not enforceable.
Employer will have to sue for any actual direct loss that can be proven.
What are benefits of Liquidated Damages inclusion to the contract?
Contractor knows the consequences for delay from the outset.
What are time periods for assessment relating to an Extension of Time?
12 Weeks from receipt from notification to decide.
If less than 12 weeks prior to PC CA should endeavor to decide before PC.
What are relevant events?
Events that allow a contractor to seek an extension of time.
How many relevant events in the JCT?
There are 13. Set out in clause 2.29
Who owns programme float
No clear rule, generally it belongs to the contractor.
What is the purpose of a valuation?
Provide advice to the certifier on value to allow issue of the interim certificate.
Payment provisions under JCT
First interim certificate issued within one month from possession.
Contractor can apply for payment no later than 7 days before end of period.
Interim certificate issued 7 days after application. Payment becomes due.
Employer has 14 days before final date to pay.
Needs to be in place for payments for materials on site?
Materials must be for works, adequately protected, delivered to programme.
Needs to be in place for payements for materials off site?
Proof that ownership will transfer to employer on payment (vesting certificate)
Insurance until materials are on site
Clearly labelled, stored seperately.
Advance payments - What are they?
May be used where contractor incurs high cost at a start of project.
Dealt with under clause 4.8.
JCT provides an advance payment bond to cover Employer financially.
Payments values and dates should be set out in contract particulars.
Disadvantages of advance payments?
May reduce incentive of contractor.
Bad for Employers cashflow.
Concerns over why Contractor cannot fund - Insolvency worries.
What is retention?
A percentage of each interim certificate deducted and retained by the employer.
Purpose of retention?
Provides an incentive for the contractor to complete works promptly.
provides financial aid in event of contractor default.
What do not have retention applied?
Loss and expense
Statutory fees
Opening up
fluctuations Options A&B
Employer should do if requested regarding retention monies?
Place in separate bank account
provide statements to the contractor
ensures money is available to contractor in event of Employer Insolvency
Who gets the interest accruing on retention monies?
The Employer
What is recommended % of retention under JCT?
3 or 5% depending on form.
What is a retention bond?
Provided by contractor in lieu of taking retention from interim payments.
Requirement should be in contract particulars.
Standard form provided by JCT.
Aides contractors cashflow.
If contractor does not maintain a retention bond?
Employer can deduct retention from interim payments.
What are fluctuation options under JCT?
Option A: Adjustment for change in statutory contributions levies and taxes.
Option B: Adjustment for changes in labour, materials and statutory costs.
Option C: Adjustment for changes in labour, materials and statutory costs determined by formula.
Retention in context of fluctuation clauses.
Options A&B are NOT subject to retention.
Option C IS subject to retention.
Summarise option B fluctuation:
Allows for adjustments to the contract sum in respect of changes to the price of labour and material cost. It covers adjustments to the market prices of materials, goods, fuel, gas (and more) which were current at the Base Date.
Can a PC certificate be rescinded once issued?
No it can not.
What is the recourse if the contractor disagrees the works are not practically complete?
Adjudication.
Consequences of sectional / practical completion?
Half retention is released
Rectification period begins
Employer needs to insure works / space
Liability for LADs ends
What is partial possession?
Different to sectional completion
employer requests possession of a the / part of works prior to date of completion.
Is at the contractors discretion.
Consequence of partial possession?
For relevant part of works, practical is deemed to have occurred.
Therefore same consequences apply.
How quickly does a contractor need to fix defects during DLP?
Within a reasonable timescale.
Three ways benefits can be transferred under JCT
Collateral Warranties
Third Party Rights
Assignment