Change Management Flashcards

1
Q

Bill of Quantities stands for?

A

List of items with descriptions and firm quantities used as a cost control document under contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Early Warning Notice stands for?

A

EWN - it is a notice of potential change that may affect costs or programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Reasons for change?

A

Requests made by employer or contractor.
Value engineering is carried out to reduce cost.
A relevant event as set out by the contract (JCT)
Revisions to statutory requirements and regulations.
Agreed tender assumptions prove to be incorrect.
Unforeseen ground conditions are encountered.
Specified items are unavailable.
Additional works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who carries the risk of change?

A

The employer is in most cases responsible for a change and can carry the related risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Give an example where the employer may not be responsible for change?

A

If the contractor cannot deliver the obligations he set out to i.e. materials.
Under D&B it is common for the contractor to take the risk of statutory sign off such as building regulations.
If quantities have not been included in the contract and the contractor is taking the responsibility for this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are changes called under the JCT?

A

Variations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Where is variation defined under JCT Standard Building Contract?

A

Clause 5.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where is ‘change’ defined in JCT D&B

A

Still clause 5.1 - less emphasis on client driven change - treated typically as changes to client ERs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who should pay for change?

A

Depends entirely on the reason for it.
Those stipulated in the contract as bearing the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Reporting change, tell me about it?

A

Change items should be registered on a tracker
Distribute and file copies of change documents
Inclusion of any change meeting minutes
Follow up to ensure actions are completed such as issue of revised design information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly