COMPETENCY KEY POINTS Flashcards
Parent Company Guarantee is?
Guarantee given by contractors ultimate or intermediate holding company in favor of employer to secure performance obligations under the contract.
When might you seek a PCG?
PCGs are commonly used by employers to give them protection in the event of contractor default.
Why PCG over performance bond?
Performance bond usually has time and financial cap. PCG may not.
Although benefit of any caps or limits in the building contract will apply.
PCG usually free to employer. Performance Bond cost added to contract sum and cost dependent on stability.
PCG enforces contractual obligations. PB only indemnifies for loss.
Standard forms of PCG?
No industry-standard form for PCG.
Parent companies should ensure same rights, obligations and limitations apply as contractor has under the main contract.
Can a PCG be requested from a contractor to employer?
Yes, this might occur if the employer is an SPV - gives security to the contractor that the parent company will pay in event of insolvency.
Sectional completion under JCT is defined where?
Clause
Sectional damages contained in contract particulars under JCT SBC & D&B
2.32.2 in SBC
2.29.2 in D&B
Sectional sums set out in contract particulars under JCT SBC & D&B
2.37 in SBC
2.34 in D&B
Sections should be outlined where in JCT ?
Sixth recital and contract particulars in SBC
Fifth recital and contract particulars in D&B
Key documents to be provided under sectional completion are and are set out where?
As built information and health and safety file information.
2.40 and 3.23 in SBC
2.37 and 3.16 in D&B
Sectional Completion Certificate is defined where in JCT?
2.30.2 in SBC
2.27.2 in D&B
SBC color and D&B color cover
SBC is Blue and Yellow
D&B is Pink and Yellow
Types of cashflow
organisational cash flow - measures company expenditure and is linked to strategic planning.
project cash flow - maps expenditure for a project.
Why is an accurate project cash flow important?
A predicted drawdown schedule may be required for developer to obtain financing agreements.
There may be consequences for not aligning with the drawdown schedule such as additional interest.
Relevant guidance notes to cashflow?
Cash flow forecasting GN
What is a procurement strategy?
It is the plan for how the construction works for the project will be secured.
Key considerations for the procurement strategy?
The clients objectives in respect of:
Time
(programme duration, start on site)
Cost
(cost fixity prior to entering contract)
Quality & control
(do they wish to retain design control)
Risk
(sole point of responsibility for design and construction? happy to manage trade contracts directly?)
Key content of procurement strategy
Project status and overview
Client objectives
Outline procurement options
Outline tendering strategies applicable
Outline suitable contracts for procurement options
Outline commercial considerations
Where have you given advice on procurement strategies
For office development - D&B for base build and traditional for fitout
Construction act 1996 states what in relation to interim payments?
Projects longer than 45 days would entitle a contractor to interim payments.
Tell me about interim payment process
Contractor makes application for payment 7 days before end of period.
Valuation of works carried out (usually by QS) in support of advice for CA to issue a payment certificate.
Payment certificate issued 7 days after application for payment.
Employer has a further 14 days to make payment.
What if client disagrees with payment certificate
If client intends to pay different amount they must give notice to the contractor of the amount they intend to pay and the basis for its calculation.
This is known as a ‘pay less notice’
Value of a payment certificate is calculated and shown on certificate how?
Value will be:
Value of work completed
Less amounts paid to date
Less retention
= Total due for payment
Pertinent timescales for CA and payment certs under construction act 1996.
In JCT contracts, a Payment Notice must be issued no later than five days after the ‘due date’.
Guidance notes applicable to payment cycles and certs?
Interim valuations and payment GN
Construction act 96 was amended by what act in respect of payments?
amended in October 2011, by the Local Democracy, Economic Development and Construction Act 2009