C3-KS46 Flashcards
Knowledge of construction bidding and negotiation processes.
1
Q
Per AIA B201 — Article 2.5 Bidding Or Negotiation Phase Services what is the architect responsible for
A
- The Architect shall assist the Owner in establishing a list of prospective contractors.
- The Architect shall assist the Owner in:
- obtaining either competitive bids or negotiated proposals
- confirming responsiveness of bids or proposals
- determining the successful bid or proposal
- awarding and preparing contracts for construction
2
Q
For Competitive Bidding, what duties is the architect responsible for?
A
- Bidding Documents shall consist of bidding requirements and proposed Contract Documents
- The Architect shall assist the Owner in bidding the Project by:
- Distributing Bidding Documents to prospective bidders, maintaining a log of distribution
- Organizing and conducting a pre-bid conference for bidders
- Preparing responses to questions from bidders, issuing addenda
- Organizing and conducting opening of the bids and distributing the bid results
- The Architect shall consider requests for substitutions if permitted by the Bidding Documents
3
Q
For Negotiated Proposals , what duties is the architect responsible for?
A
- Proposal Documents shall consist of proposal requirements and proposed Contract Documents
- The Architect shall assist the Owner in obtaining proposals by:
- Distributing Proposal Documents to prospective contractors
- Organizing and participating in selection interviews with prospective contractors
- Participating in negotiations with prospective contractors
- Preparing a summary report of the negotiation results - The Architect shall consider requests for substitutions if permitted by the Proposal Documents