C3-KS46 Flashcards

Knowledge of construction bidding and negotiation processes.

1
Q

Per AIA B201 — Article 2.5 Bidding Or Negotiation Phase Services what is the architect responsible for

A
  1. The Architect shall assist the Owner in establishing a list of prospective contractors.
  2. The Architect shall assist the Owner in:
    - obtaining either competitive bids or negotiated proposals
    - confirming responsiveness of bids or proposals
    - determining the successful bid or proposal
    - awarding and preparing contracts for construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

For Competitive Bidding, what duties is the architect responsible for?

A
  1. Bidding Documents shall consist of bidding requirements and proposed Contract Documents
  2. The Architect shall assist the Owner in bidding the Project by:
    - Distributing Bidding Documents to prospective bidders, maintaining a log of distribution
    - Organizing and conducting a pre-bid conference for bidders
    - Preparing responses to questions from bidders, issuing addenda
    - Organizing and conducting opening of the bids and distributing the bid results
    - The Architect shall consider requests for substitutions if permitted by the Bidding Documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

For Negotiated Proposals , what duties is the architect responsible for?

A
  1. Proposal Documents shall consist of proposal requirements and proposed Contract Documents
  2. The Architect shall assist the Owner in obtaining proposals by:
    - Distributing Proposal Documents to prospective contractors
    - Organizing and participating in selection interviews with prospective contractors
    - Participating in negotiations with prospective contractors
    - Preparing a summary report of the negotiation results
  3. The Architect shall consider requests for substitutions if permitted by the Proposal Documents