8.6 Technical Specification Flashcards

1
Q

1 - List ‘Facility Construction’ Divisions 02 through 14 (15-19 reserved for future expansion)

A
02 - Existing Conditions
03 - Concrete
04 - Masonry
05 - Metals
06 - Wood, Plastics and Composites
07 - Termal Moisture Protection
08 - Openings
09 - Finishes
10 - Specialties
11 - Equipment
12 - Furnishings
13 - Special Construction
14 - Conveying Equipment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 - Which Master Format divisions relate to structural elements?

A

2-6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

3 - Which disciplines are found in the ‘Facility Services’ Section of the MasterFormat system? What divisions are those?

A

MECH (21-25)
ELEC (26-28)
Divisions 20-28

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4 - List ‘Infrastructure’ Divisions 30 through 39 (30, 36-39 reserved for future expansion)

A
31 - Earthwork
32 - Exterior Improvements
33 - Utilities
34 - Transportation
35 - Waterway + Marine Construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

5 - MasterFormat is subdivided into a hierarchy, list the 4 main organizational structures.

A
  • DIVISIONS
  • SECTIONS
  • PARTS 1.General 2.Products 3.Execution
  • ARTICLES major subjects comprised of paragraphs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

6 - What are divisions 00 + 01

A

00 Procurement & Contracting Requirements

01 General Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

7 - List the 9 Sections found in Division 00:

A

00 Procurement & Contracting Requirements
00 10 Solicitation (RFP etc)
00 20 Instructions for Procurement (supplemental instructions / meetings, etc)
00 30 Available Information
00 40 Procurement Forms & Supplements (bid forms etc.)
00 50 Contracting Forms & Supplements (agreement form)
00 60 Project Forms (Bond forms, certificates, CA forms)
00 70 Conditions of the Contract (general conditions, supplementary conditions)
00 80 N/A
00 90 Revisions, Clarifications, and Modifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

8 - What is the NMS and who produces it?

A

aka ‘Deletion Spec’
• Library of construction specification sections written in contract spec format (MasterFormat)
• Produced by Federal Government + Private Interests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

9 - List the 9 Sections in Div. 01:

A

01 General Requirements:
01 10 Summary (of work, contracts, restrictions)
01 20 Price + Payment Procedures (allowances, unit prices, alternates)
01 30 Admin. Rqrmts (PM & coordination, progress documentation, submittal procedures etc)
01 40 Quality Rqrmts
01 50 Temp. Facilities + Controls
01 60 Product Rqrmts
01 70 Execution + Closeout Rqrmts
01 80 Performance Rqrmts
01 90 Life Cycle Activities (commissioning, O+M)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

10 - List the 8 Sections in Div. 02

A
02 00 Existing Conditions (maint of existing)
02 10 N/A
02 20 Assessment (Surveys, assessments)
02 30 Subsurface Investigation (Geo)
02 40 Demo + Struc. Moving
02 50 Site Remediation
02 60 Contaminated Site Material removal
02 70 Water Remediation (groundwater)
02 80 Facility Remediation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

11 - List the 8 Sections in Div. 03

A
03 00 Concrete (common work, maintenance)
03 10 Concrete Forming & Accessories
03 20 Concrete Reinforcing
03 30 Cast-in-Place
03 40 Precast
03 50 Cast Decks + Underlayment
03 60 Grouting
03 70 Mass Concrete
03 80 Concrete Cutting + Boring
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

12 - What is found in 04 20 20?

A

04 Masonry (clay, brick, CMU, veneer, glass)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

13 - What are the 5 Sections found in Div. 05

A

05 00 Metals (common maintenance + work, schedules)
05 10 Structural Metal Framing
05 20 Metal Joists
05 50 Metal Fabrications (railings, grates, nosings, stairs)
05 60 N/A
05 70 Decorative Metal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

14 - What are the 8 Sections found in Div. 06?

A

06 00 Wood, Plastics, Composites (common work, maintenance)
06 10 Rough Carpentry
06 20 Finish Carpentry
06 30 N/A
06 40 Architectural Woodwork (casework, stairs/railings, ornamental wood, wood trim, wood frames)
06 60 Plastic Fabrications (solid surface)
06 70 Structural Plastics (composite lumber)
06 80 Composite Fabrications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

15 - What are the 9 Sections found in Div. 07?

A

07 00 Thermal + Moist. Protection (maint. + protection)
07 10 Dampproofing + Waterproofing
07 20 Thermal Protection (vapour retarder, air barrier)
07 30 Steep Slope Roofing
07 40 Roofing + Siding Panels
07 50 Membrane Roofing
07 60 Flashing + Sheet Metal
07 70 Roof + Wall Specialties + Accessories (roof pavers, vents)
07 80 Fire + Smoke Protection (Fireproofing, firestopping, smoke seals)
07 90 Joint Protection (seals, gaskets, rods)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

16 - What are the 9 Sections of Div. 08?

A

08 00 Openings (Maintenance, operation, schedules)
08 10 Doors + Frames
08 20 N/A
08 30 Specialty Doors + Frames (slide glass, coil, etc)
08 40 Entrances, Storefronts + Curtain Walls
08 50 Windows (metal, wood, plastic, composite)
08 60 Roof Windows + Skylights
08 70 Hardware (not schedule! in 00)
08 80 Glazing
08 90 Louvers + Vents

17
Q

17 - What are the 8 Sections in Div. 09?

A
09 00 Finishes (maintenance, common work, schedule)
09 10 N/A
09 20 Plaster + Gypsum Board
09 30 Tiling
09 40 N/A
09 50 Ceilings
09 60 Flooring
09 70 Wall Finishes
09 90 Painting + Coating
18
Q

18 - What are the 8 Sections in Div. 10?

A

10 00 Specialties (operations, maintenance, common work, commissioning)
10 10 Information Specialties (chalkboards, signage)
10 20 Interior Specialties (compartments, partitions, wall, door protection, WC accessories)
10 30 Fireplaces + Stoves
10 40 Safety Specialties (fire extinguishers, emerg. aid)
10 50 Storage Specialties (lockers, shelving, wardrobe)
10 70 Exterior Specialities (exterior clocks, flagpoles)
10 80 Other Specialties (pest control)

19
Q

19 - What division would air-supported structures fall under?

A

Div 13

20
Q

20 - In what division would you find elevators?

A

Div 14

21
Q

21 - In what division would you find fire suppression systems?

A

Div 21 Fire Suppression

22
Q

24 - In what division would you find plumbing?

A

Div 22 Plumbing

23
Q

25 - In what division would you find HVAC systems?

A

Div 23 Heating, Ventilating, and Air Conditioning

24
Q

22 - In what division would you find lighting control?

A

Div 25 Integrated Automation

25
Q

23 - In what division would you find cable, telephone, internet?

A

Div 27 Communications

26
Q

26 - In what division would you find security systems?

A

Div 28 Electronic Safety + Security

27
Q

27 - In what division would you find soil stabilization?

A

Div 31 Earthworks

28
Q

28 - In what division would you find fencing + planting?

A

Div 32 Exterior Improvements

29
Q

29 - In what division would you find storm drainage?

A

Div 33 Utilities

30
Q

30 - In what division would you find stage or gym equipment?

A

Div 11 Equipment

31
Q

31 - What should you avoid specifying if you have specified the results of a material or assembly?

A

The method of install, may cause conflict and expose arch to risk.

32
Q

32 - For what materials must the architect provide a spec?

A

All materials on drawings.

33
Q

33 - What is the Uniformat organizational structure.

A

3 levels of increasingly detailed information subdivided into 3 elements of the building:
A - Substructure
B - Shell
C - Interior